Engineering Labor Contract 1 Party A: (hereinafter referred to as Party A)
Party B: (hereinafter referred to as Party B)
According to the Economic Contract Law of the People's Republic of China, the Construction Law of People's Republic of China (PRC), the Construction Project Contract issued by the State Administration for Industry and Commerce and the Ministry of Construction, in accordance with the relevant provisions of provinces and cities, on the principle of equality, voluntariness and consensus, and in combination with the specific conditions of this contract, the two parties have reached the following agreement:
I. Overview of the Project
Project name: Building 5, Furong Community, Xuanyuan Road, xinzheng city
(1) Contract scope: Party B shall undertake the work, and Party A shall be responsible for the tools and raw materials needed by Party B. ..
(2) Exterior wall shall be plastered with tiles (tile specification 6x20), all sides shall be counted, and all internal openings shall not be powdery.
Second, the contract price
Pay lip service to 36 yuan/square.
Three. Party B contracted this project in order to achieve the qualified project required by Party A..
Four. mode of payment
When Party B's workers enter the construction site, Party A shall pay Party B the living expenses in advance. Part of the project will pay 80% of the project cost, the next part will pay 20% of the previous part after completion, and the whole part will pay 80% after completion.
5. This contract is made in duplicate, one for each party, and shall come into effect after being signed by both parties.
Party A (official seal): _ _ _ _ _ _
Party B (official seal): _ _ _ _ _ _
Xx,xx,XX,XX
Employer (Party A) of Engineering Labor Contract 2:
Employee (Party B):
In accordance with the Contract Law of People's Republic of China (PRC), the Construction Law of People's Republic of China (PRC) and other relevant laws and regulations, and following the principles of equality, voluntariness, fairness, honesty and credibility, Party A and Party B have reached an agreement on labor cooperation in construction projects and concluded this contract.
I. Overview of the Project
1, project name:
2. Project location:
3. Mode of labor service:
4. Project content:
Second, the quality requirements
1. Project quality grade: the quality standard of the project completed by Party B shall not be lower than that of the project contract signed by Party A and the general contractor.
2. Party B shall have corresponding construction experience, skilled workers shall have corresponding technical qualifications and production capacity, and the types and quantities of construction workers shall meet the needs of the project.
3. The acceptance of this project shall be carried out in accordance with the relevant construction specifications promulgated by the state, the evaluation criteria for project quality acceptance and the relevant provisions stipulated by the owner.
4. The first acceptance rate of the project constructed by Party B must reach 100%. During the warranty period, Party B shall unconditionally repair the project within the time required by Party A's maintenance notice.
Third, the construction cycle
1. This contract shall come into effect on _ _ _ _ _ _ _ _ _ _ _ _.
2, the time limit for a project postponed and extended:
(1) In the course of construction, if Party B fails to carry out normal construction due to Party A's fault, the construction period agreed in this article shall be postponed accordingly (the extension time shall be subject to the shutdown time within the legal working hours due to Party A's fault).
(2) If the construction content is increased, Party A and Party B shall negotiate separately to determine the extension time of the construction period.
Fourth, the labor cost.
1. Upon negotiation between Party A and Party B, the total contract price is tentatively set at _ _ _ _ _ _ _.
2. The expenses of materials, machinery and equipment (including auxiliary materials) collected or rented from Party A by Party B or its authorized personnel during the construction period shall be included in the service fees payable by Party B, and the service fees payable by Party A to Party B shall be reduced accordingly according to the time when the expenses occur.
3. Party A entrusts _ _ _ _ _ _ _ _ bank to transfer the money into Party B's account in legal tender form on _ _ _ every month.
Verb (abbreviation of verb) Party A's responsibility
1. Party A shall provide Party B with a suitable working environment according to this contract.
2. During the contract period, Party A shall supervise and inspect Party B's work and make timely rectification.
3. Party A has the right to ask Party B to rework the unqualified construction.
4. After receiving the notice of completion acceptance, Party A shall arrange personnel to organize acceptance in time.
5. Party A shall pay the labor fee to Party A in full and on time according to this contract.
The intransitive verb Party B's responsibility.
1. Party B shall abide by the provisions of this contract, Party A's rules and regulations and the command of Party A's representative, and may refuse unreasonable command requirements.
2. When working, Party B shall carry out the work safely and efficiently as stipulated in the contract, and finish the task on time.
3. Party B shall complete the task according to the contract requirements. If there are quality problems, Party B shall be responsible for rework.
4. Notify Party A for acceptance on the day of project completion.
Seven. final acceptance of construction
1. Party B must carry out quality control in accordance with relevant national construction acceptance specifications, design drawings and relevant design notices, quality requirements in the main contract and quality system requirements of Party A, and accept the quality supervision, inspection and control of Party A, the supervisor and the owner.
2. Party B shall be equipped with full-time quality inspectors, establish a perfect quality inspection control system, and cooperate with Party A's third-party inspectors to do a good job in quality inspection and acceptance of each process.
3. Party B shall take full responsibility for the construction quality of the project it undertakes. In case of quality accident, report to Party A within _ _ _ _ _ _ hours, and be responsible for the rework of construction quality defects and bear relevant expenses; For unqualified products, Party A has the right to require Party B to rework, and bear the economic losses and delays caused thereby; For projects that do not meet the quality requirements, Party A will not make measurement and settlement.
4. Party B shall carry out quality inspection and acceptance of the whole process in strict accordance with the requirements of Party A's construction process quality acceptance procedures. Only after the products are accepted by the supervisor and Party A can they be transferred to the next working procedure. ..
Eight. responsibility for breach of contract
1. Both parties shall strictly abide by the agreement. If there is any violation, it shall be liable for breach of contract according to the relevant provisions of this agreement.
2. If the construction period is delayed, Party B shall bear the liquidated damages of% of the total contract price for each day exceeding, or pay RMB to Party A every day.
3. In case of quality problems and violation of other agreements in this agreement, Party B shall compensate all economic losses caused to Party A, and Party A may require Party B to bear _ _%-_ _% of the total contract price as penalty according to specific conditions.
Nine. Dispute mediation
Any dispute arising from the execution of this agreement shall be settled by both parties through consultation. If negotiation fails, both parties may bring a lawsuit to the people's court of the place where the contract is signed and the place where the contract is performed.
X. supplementary provisions
1. This agreement shall come into force after being signed by both parties, and shall become invalid after the obligations of both parties are fulfilled.
2. This Agreement was signed on _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
3. Matters not covered in this contract shall be settled by both parties through consultation.
Party A:
Party B:
Xx,xx,XX,XX
Engineering Labor Contract 3 Party A:
Party B:
In accordance with the Contract Law of People's Republic of China (PRC), the Construction Law of People's Republic of China (PRC) and other relevant laws and regulations, and in line with the principles of fairness, justice, equality and mutual benefit, honesty and trustworthiness, Party A and Party B reached an agreement through consultation.
I. Overview of the Project
1, project name:
2. Project location:
3. Party B's contracting scope: pasting the living room wall and floor, etc.
Second, the way of cooperation.
Party A contracts to Party B in the form of single work. During the construction, Party A only provides qualified materials, and Party B provides any tools generated during the construction. ..
Three. Manual valuation method: adopt the following methods.
The first method: the total contract price. Party A and Party B negotiate according to the market situation and give the total contract price of the contracted project.
The second way: hourly wage. The salary standard of Party B is (bricklayer) yuan/day/person, and Party A shall settle the final salary with Party B according to the actual attendance days of Party B multiplied by the standard salary.
The third way:
Fourth, the quality requirements
Party B shall strictly control the quality to ensure the first acceptance. The rework, materials and labor costs caused by unqualified construction quality shall be borne by Party B, and Party A only provides technical guidance.
Five, the construction period requirements
Start employment? Year month day, end of employment? Year month day. According to the actual situation, Party A and Party B can solve it through consultation.
Six, civilized construction and safety
Party B must strictly control production safety and take protective measures for safe construction to prevent accidents. Party B shall not intentionally waste materials during the construction. If found, Party B shall compensate at the original price. Party B shall unite with Party A's employees during the construction period, and shall not quarrel or fight with anyone at the construction site.
Vii. Terms of payment for acceptance settlement
After the completion of this project, Party A and Party B shall organize personnel from relevant departments for acceptance. After the acceptance, Party A shall pay the salary to Party B within one week.
This contract is made in duplicate, one for each party, and shall come into effect after being signed and sealed by both parties.
Party A:
Party B:
Xx,xx,XX,XX
Project Labor Contract 4 Employer (hereinafter referred to as Party A):
Employer (hereinafter referred to as Party B):
Party A and Party B sign this contract on the basis of equality, voluntariness and consensus.
I. Employment agreement:
1. After the signing of this contract, both parties determine the labor and employment relationship.
2. Validity period of the contract: This contract shall come into effect from the date of signing and shall be valid for one year.
3. After the expiration of this contract, if Party A continues to employ Party B, this contract can be renewed. If Party A ceases to employ, the Contract shall be terminated immediately;
4. If Party B requests to resign within the contract period, it shall notify Party A in writing 7 days in advance.
Second, the job responsibilities:
1. Party B shall obey the work arrangement of Party A and complete the work on time, in good quality and in good quantity according to the post responsibilities determined by Party A. ..
2. Party B shall abide by Party A's rules and regulations and national laws and regulations.
3. Party B shall seriously implement the post responsibility system and safety operation rules to prevent all kinds of accidents. I violate the safety operation rules, command in violation of regulations, and take corresponding responsibilities if an industrial accident occurs.
4. Party B shall not harm the interests of Party A during the employment period. If Party A suffers economic losses due to his personal behavior, Party B must bear all the compensation responsibilities.
Three. Working hours:
1. During Party B's work in Party A, Party A shall pay the salary according to the provisions of the Labor Law.
2. During the employment period, Party A shall establish an attendance book and distribute the Labor Wage Management Manual printed by Weifang Construction Administrative Department to Party B free of charge.
3. Party B must go to Man Qin according to the agreed working time, and the absentee must ask for leave from Party A in writing one day in advance, otherwise it will be treated as absenteeism. Absenteeism will be deducted from the day's salary. If it exceeds 10 days, the labor contract shall be terminated as incompetence.
Four. Labor protection and working conditions:
Party A shall provide Party B with necessary living and accommodation conditions, labor tools and labor protection articles according to work needs, and Party B shall return the labor tools to Party A when he leaves his post.
Verb (abbreviation for verb) Labor remuneration:
1. The salary distribution of Party A shall follow the principle of distribution according to work; Where the fixed-time wage system is implemented, Party A shall pay Party B the salary in cash every month, and the salary shall be calculated according to the individual building volume or daily salary, and adjusted with the market price.
2. Party A shall pay the salary to Party B on the principle of monthly payment, full payment, personal collection and on-site publicity.
In case of any of the following circumstances of intransitive verbs, Party A may terminate this Agreement:
1. Party B violates Party A's labor discipline and rules and regulations;
2. Party B's dereliction of duty causes losses to Party A's interests;
3. Disobeying Party A's work arrangement and violating the law and discipline;
4. Failure to implement the post responsibility system and safety operation procedures, resulting in quality and safety accidents;
5. Concealing health and affecting workers;
6. Party B is investigated for criminal responsibility or reeducation through labor according to law;
7, there are violations of law and discipline.
Seven. Others:
1. This agreement shall come into effect after being signed by both parties.
2. Matters not covered in this agreement shall be implemented in accordance with other relevant national laws, and shall be amended and supplemented after both parties reach an agreement through consultation.
3. This Agreement is made in duplicate, with each party holding one copy.
4. As mentioned in this agreement, Party A must be a construction enterprise with construction qualification, and Party B must be a healthy China citizen aged 65,438+08.
5. This agreement is the basis for Party B to safeguard its legitimate rights and interests and demand labor remuneration.
Party A (official seal): _ _ _ _ _ _
Party B (official seal): _ _ _ _ _ _
Xx,xx,XX,XX
Project Labor Contract 5 Project Contractor: (Party A)
Labor Subcontractor: (Party B)
In accordance with the Contract Law of People's Republic of China (PRC), the Construction Law of People's Republic of China (PRC) and other relevant laws and regulations, and following the principles of equality, fairness, honesty and credibility, the Contract is concluded through negotiation between both parties on the subcontracting of labor services.
1, the object of labor subcontracting and the content of providing labor services
Project name:
Project location:
Subcontracting scope:
Building area:
2, the subcontract work period:
3. Project quality. The quality of this project meets the requirements of Code for Construction and Acceptance of Building and Installation Engineering, Standard for Quality Evaluation of Building and Installation Engineering and drawing design. The construction standards required by the construction unit must reach the intermediate decoration level.
4. Contract method: contract scope and contract unit price.
A) Contract method: settle the labor cost of packaging.
B) Scope of contract: all indoor and outdoor wall plastering, external wall insulation, ceiling and gutter facade insulation and plastering, stair plastering and marble paving, indoor floor, roof tile, waterproof upper protective layer, chimney plastering and parapet plastering (excluding ceiling plastering).
C) The unit price of this project is /m2 (calculated according to the actual construction area of this project).
5. Standard scope
Unless otherwise agreed in the project contract:
A) If the design of the engineering drawings changes, Party A and Party B shall negotiate separately.
B) Party A shall be responsible for the delay in the construction period and the labor waste of Party B caused by Party A's insufficient material supply and labor cost.
C) Party B shall be responsible for the delay in the construction period caused by Party B.
6, civilized construction and safety responsibility
The subcontractor shall take civilized construction and safety measures according to the requirements of the general contractor, and the responsible party shall be responsible for any safety accident.
7, tool use and material management
Labor subcontractors shall bring their own small tools, other large tools, aluminum alloy guide rails and consumables shall be provided by the general contractor, and the materials used on site shall be provided by Party A. Party B shall not waste materials and clean up the site after work. If the materials are wasted by Party B, Party B shall be responsible for compensation.
8, time limit for a project and payment method
From the commencement of this project to the completion of plastering the internal and external walls of each building, Party A will pay 70% of the completed project, 80% of the completed project amount after the completion of benzene board pasting and roofing tile construction, 95% of the remaining project amount after the completion of other projects and the withdrawal of workers, and the balance will be paid in one lump sum after the project completion acceptance.
9. Others
In case of irresistible natural disasters during the construction period, the construction period will be postponed accordingly.
10, this contract is made in triplicate.
Party A (official seal): _ _ _ _ _ _
Party B (official seal): _ _ _ _ _ _
Xx,xx,XX,XX