Implementation Plan of Rural Farmers' Market ConstructionNo. 1 Zhangdonglong Village Center Farmers' Market Construction Method: First, prepare the lawn, and then build the retaining wall.
A, farmers market center construction requirements for concrete construction at the grass-roots level
1, the strength of foundation concrete should be less than or equal to ≤c25, the water cement ratio should be as small as possible, and the rammer should not contain early strength agent.
2. The particle size of the largest aggregate in concrete should be ≤30mm, and the foundation surface must be paved with cement mortar layer with a thickness of ≤ 15mm and ≥10 mm..
3, the slump of concrete should be controlled in 3-4cm, the slump of commercial concrete should be controlled in 12- 14cm.
4. Gravel and plain soil foundation must be compacted or tamped by roller.
Concrete below 10cm shall be vibrated by flat vibrator, and concrete above 10cm shall be vibrated by plug-in vibrator.
5. Roll the platform repeatedly with heavy steel long rollers (the steel rollers should be more than 0.3m wider than the formwork) to make it smooth. When rolling the platform, the foreign objects on the steel roller should be removed. Lift the concrete slurry to ensure that there is no sand and gravel on the surface. In the parts that cannot be operated by steel rollers, the elevation of the platform shall be leveled with templates.
6, after the completion of the concrete floor, should be secrete water treatment.
It is required that the gradation of the bottom concrete is C25 or C20, and the upper concrete is C30 or C25 mortar concrete, with a total thickness of 10-30cm.
Second, the central farmers' market construction steps:
1, concrete surface roughening treatment: Before the initial setting of the concrete surface, add 1cm cement slurry, evenly smooth the water mortar on the concrete surface with a manual iron plate, and roughen the surface.
2. Spreading hardening material: In the initial setting stage, evenly spread 2/3 of the specified amount of hardening agent on the concrete surface. After the hardened material is soaked by water, use a manual iron plate to level and collect light to complete the first operation. After the hardened material is initially set to a certain stage, conduct the second leveling operation of 1/3 material spreading and light collection.
3. Leveling light-hardened materials: According to the hardening condition of concrete, the artificial iron plate should be leveled by light for at least three times, and the light-receiving operations should be staggered.
4. Spreading demoulding powder: In a certain initial setting stage of the hardened material, under the condition that the surface is dry and there is no obvious moisture, evenly spread a layer of demoulding powder matching with the hardened material.
5. Press out the pattern with the mold to keep the mold fixed and flat. The pressed pattern should be formed at one time without great pressure.
6, to achieve a variety of design styles, textures and colors, but also can carry out interactive design of a variety of colors.
Third, the central farmers' market later maintenance and requirements
The construction of materials in the central farmers' market is generally carried out outdoors, and it should be prevented from being carried out in rainy and windy weather. The construction environment temperature is generally above 2 degrees Celsius. Rinse the floor surface: After the hardened floor tiles are completely dried and solidified, the surface can be rinsed with water or detergent for at least 2-3 days, and the cleanness of the whole floor must be ensured, otherwise the color of the floor will be different. Coating brightener: Liquid brightener can be applied for at least one day after the cleaned and hardened floor tile surface is completely dry and moisture-free, so as to maintain and enhance the brightness and make the floor tile surface anti-fouling and anti-skid and re-strengthened. The finished floor tile is not only decorative, but also has very stable physical properties. In the maintenance stage of floor tiles, it is necessary to prevent people from entering and leaving casually or carrying out construction work of other projects. The effective function of floor tiles is closely related to the construction technology and artistic embossing materials, which should be strictly guaranteed by professional knowledge and years of experience.
Implementation Plan of Rural Farmers' Market Construction 2 ×× Implementation Plan of Rural Market Construction In order to build a well-off society in an all-round way, accelerate the economic construction in the urban-rural fringe, build my hometown into a commodity distribution center with obvious advantages, create conditions for farmers to find jobs and do business, and attract rural labor to transfer to secondary and tertiary industries, my hometown decided to build a farmers' market, and build a comprehensive wholesale trading market integrating vegetable wholesale processing, fruit wholesale and livestock and poultry trading at the junction of Yongding County and Sangzhi County.
I. Project background
The project is located in XX village, the economic and cultural center of XX township, only * * kilometers away from the city center, close to XX township and XX township, with convenient traffic analysis and complete water circuit facilities.
The market has a long history. Since ancient times, it has been an important place for residents in XX, XX, XX and XX to gather and trade. Now my hometown has changed a lot, and the infrastructure such as water, electricity and roads have been greatly improved. In particular, the XX highway runs through the whole line, and now it is only * * kilometers away from the city center, which greatly promotes the prosperity of the hometown bazaar and the rapid development of the local economy.
This market has made great contributions to the local economic development. It meets on the 6th, 4th and 7th of every month (basically once every three days), and the number of people attending the fair reaches as many as ten thousand. Because the market is extremely irregular, there are no market stall facilities, and there are no functional facilities such as drainage, garbage cleaning, fire prevention and fire fighting in the market, which leads to serious dirty, chaotic and poor market. On a sunny day, garbage is everywhere and smells bad. The number of people going to the fair is increasing year by year, and the chaotic and backward market can't keep up with the needs of economic and social development, so it is urgent to build it immediately. After the market transformation, the service function will be complete and the economic and social benefits will be considerable. We must build the project well.
Second, the status quo of the project
(1) Project Name: XX Rural Agricultural Products Market Construction Project
(II) Project Location: XX Village
(3) Project area: * ㎡.
III. Reconstruction and construction tasks and cost estimation
There are 220 1. booths, each with a height of 1.2m and a brick-concrete structure. The estimated construction cost of each booth is 150 yuan, of which the material cost is 100 yuan, and the construction salary is 50 yuan, so the estimated total construction fund of the booth is 33,000 yuan.
2. Build four new garbage pools. Each garbage pit is 3m×4m in size and 2m in height. The construction cost of each garbage pit is estimated to be 3,000 yuan, and the total investment of garbage pit is estimated to be * * * 1.2 million yuan.
3. The newly-built market rain shed, 300 meters long and 7 meters wide, is made of brick and wood structure and covered with cement tiles. According to the cost per square meter 100 yuan, the estimated investment is 2 10000 yuan.
4. Two new drainage ditches, * * * 960m, with specifications of 80cm×50cm, are covered with plates. According to the estimated cost per meter of 200 yuan, * * * needs to invest192,000 yuan.
5, the installation of lighting circuit square meters; Green engineering square meters.
6. The hardened area of the market floor is * * * ㎡ and the thickness is 20cm. According to the cost estimate of 80 yuan per square meter, * * * needs to invest 323,200 yuan.
7. The project construction management and surrounding coordination cost is about 30,000 yuan.
8. The land requisition amount is 200,000 yuan.
The budget investment of all projects is 1000200 yuan.
Four. Starting and ending years of construction V. Evaluation of economic and social benefits
The completion of this project can solve the employment of more than 20 surplus laborers in * * Village Committee 120, greatly promote the stability and development of local economy, play a good role in actively promoting the development of township economy and implementing the long-term planning of * * urban area, create conditions for urban and rural residents to find jobs and do business, and attract urban and rural laborers to transfer to secondary and tertiary industries, which will play a certain role in promoting.
Chapter III: Implementation Plan of Rural Farmers' Market Construction Project
In order to ensure the smooth implementation of the standardized farmer's market construction project in the ancient town of Saisisi Town and put it into use as soon as possible, the implementation plan of this project is formulated according to the project requirements and the actual situation of the ancient town.
I. Guiding ideology
Firmly establish Scientific Outlook on Development, optimize the layout of industrial structure, cultivate and expand the tertiary industry, improve the service function of small towns, enhance the radiation effect, activate the rural market and increase farmers' income.
Second, the construction principle
Reasonable layout, perfect functions, zoning planning and moderate scale.
Third, the architectural layout
According to the overall planning of the construction of the ancient town of Saisisi Town, the farmer's market is located in the business district on the east side of the town, 50 meters north of the provincial highway Yongtian Highway.
Fourth, the scale of construction.
According to the regulatory detailed planning of the construction of the ancient town of Saisisi Town, the commercial land is 6600 square meters, and the commercial building is a two-story frame structure building with a construction area of 8375 square meters. Equipped with public service facilities such as water supply and drainage, garbage bins, street lamps, green belts, public toilets, fire fighting, warehousing, parking, etc., and arranged for 65,438 merchants to stay.
Verb (abbreviation of verb) source of construction funds
The estimated total investment of the project is15.4 million yuan, including 6.5 million yuan from the state, 9.8 million yuan from foreign investment and1654.38 million yuan from other investments.
Six, the construction progress plan
20xx65438+1October-March to complete the project declaration, project establishment and bidding;
20XX completed the demolition of temporary buildings and site leveling in April to meet the requirements of "three links" construction;
20XX may-10 completed the main commercial housing construction project; 20XX 1 1 month -—20XX April shutdown winter break;
20XX May-June 20xx Complete indoor and outdoor decoration and outdoor supporting works of commercial buildings;
20XX was completed and put into use in July.
Seven, engineering quality management
1, set up a market construction project leading group, with the main government leaders and leaders in charge as deputy heads, and cadres from the project office, community and finance office responsible for project supervision, affairs coordination and fund management.
2, by the supervision company for many years in supervision personnel on-site supervision of engineering quality.
3, according to the construction progress regularly invite urban construction quality inspection department to supervise the quality of the project.
4, joint development and reform, urban construction, finance, commerce, safety supervision and other departments to supervise the quality of the project.
Eight, the market follow-up management
1. Under the supervision and guidance of the industrial and commercial departments, we will thoroughly publicize the relevant policies and regulations on the management of the socialist market economy, carry out the activities of establishing a "farm shop with thousands of villages and thousands of townships", and advocate law-abiding, honest and civilized management.
2. Under the specific guidance of individual associations, give full play to the main role of merchants, do a good job in the orderly management of the market, implement the "three guarantees" of environmental sanitation in front of the door, take turns to watch the market, and improve the machine defense facilities such as strengthening monitoring.
3. Strengthen the self-discipline awareness education of merchants, improve the purchase ledger, ensure the quality of goods and food safety, and create a safe and honest market that the masses are satisfied with.
Implementation Plan of Rural Farmers' Market Construction Chapter III Farmers' Market is a market for fresh agricultural products. It sells agricultural products in a natural state, which is an important part of perfecting the market system and one of the public service facilities closest to residents' lives. Its image can reflect the civilization and economic development level of the city from the side. In recent years, the market layout and construction pace of county towns have seriously lagged behind the actual needs of residents. In order to completely change this situation, after extensive investigation and full demonstration, the planning and layout scheme of county (district) farmers' market is put forward.
I. Work objectives
Through the overall planning of the market in the county, we will speed up the construction and transformation of the farmer's market, gradually change the problems of mixed people and vehicles, chaotic traffic, poor shopping environment, simple hardware facilities and small capacity in the existing farmer's market, meet the growing needs of residents in our county, gradually use beautiful environment, standardized facilities, perfect functions and standardized management, and strive to create a fair, hygienic, safe and assured consumption environment to ensure the health of the people.
Second, the principle of planning and construction
1, planning first, people-oriented. According to the actual needs of county residents, the farmers' market is planned in advance to form a scientific, reasonable and convenient distribution of vegetable market outlets. After the completion of the whole market, the overall goal of having a residential vegetable market every 10 minute will be achieved.
2, combined with other commercial outlets in the county. Form a market-based vegetable market system with supermarkets as the focus and convenience stores as the supplement.
3. Reasonable zoning, complete functions and complete supporting facilities. According to the consumption characteristics and regional characteristics of their respective regions, each farmer's market is required to have prominent business focus, reasonable market division and complete functions, and do a good job in supporting their respective water circuits, vehicle parking areas and other related service facilities.
4, scientific and technological support, complete facilities. Strengthen the construction of science, technology and information technology in the farmer's market, focusing on equipping the market with microcomputer management systems, including electronic screen display, electronic scales, price monitoring of shopping guides, and product quality inspection systems. Use the developed closed equipment for live poultry slaughter to improve the grade of farmers' market.
5. Scientific management and sound system. Specific management measures, such as points system, margin system and bidding system, are implemented for the completed farmers' market to realize scientific and refined management and ensure management level and efficiency.
Third, the implementation method and scope
(1) Implementation measures. According to the urgency of the living needs of residents in existing residential areas, the method of planning in advance, implementing step by step and steadily advancing is adopted.
(2) scope of implementation. County planning area.
Four. Opinions on planning and site selection
(1) Plan to build three new retail farmers' markets.
1, Chengdong Farmers' Market (Fuzhiyuan Farmers' Market)
It has been located at the junction of South Chaoyang Street and Quanping Road in Hucheng Community. The total area is 7 mu, and the effective utilization area is 4.5 mu. Considering that there are many people in the east of the city, it is suggested that the market should be built on two floors. After completion, the market transaction area will be about 4,200 square meters. After the completion of the East Market, it can cover the housing needs of 28,000 people near Anfu East Road, Chaoyang East Street, People's Hospital and County Vocational School, and radiate the residents of Yangban and Huo Feng.
2. Chengxi Farmers Market
The site is located in the existing site of West Bus Station, with a construction area of 9,000 square meters and an effective area of 5,000 square meters, with a total investment of about 3 million yuan. After the project is completed, it can cover the housing needs of nearly 25,000 people in the west of the city, and radiate residents in Sheshi, Wen Jia and Chen Er.
3. Chengnan Farmers' Market
The site is located in Houping of Wentang Community Neighborhood Committee. There is a large space here, and the land belongs to the collective, which is suitable for the market layout. It can build 1 market with an area of about 4,000 square meters, and the investment in the market part is about 3 million yuan. After the completion of Chengnan Market, it can radiate the housing needs of nearly10.5 million people near Wentang Community, and cover the residents in Sixiangang, Chen Er, Taifu and other regions.
(2) Two agricultural products supermarkets are planned and constructed.
1, agricultural products supermarket in industrial park. The project is laid out together with the commercial center of the industrial park, with a supermarket area of about 500 square meters. After the project is completed, it will mainly provide supporting services for manufacturers and enterprises in the industrial park.
2. Bund New Town Agricultural Products Supermarket. It is laid out together with the planned Bund commercial pedestrian street, with an area of 300 square meters, mainly serving the residents of the community.
(3) Planning and construction of 15 agricultural products convenience store.
It is mainly built in developed residential areas and main street centers such as Chutian Haoyuan, Xingqing Bay, Jinniu and Meizhiyuan. Covering an area of about 20-50 square meters, it mainly sells rice, cooking oil, spices and other related necessities to provide residents with nearby services.
(four) planning and construction of agricultural products wholesale market 1.
The plot is located on the east side of Lingang Highway, with a controlled area of about 100 mu and a total investment of over1000,000 yuan. Mainly for Changde, radiating northwest Hunan, and developing wholesale trade of agricultural products.
Verb (abbreviation of verb) construction period
20XX—20XX will complete three market construction tasks in the east, west and south of the city and the transformation task of Chaoyang market within two years.
Relevant requirements of intransitive verbs
1, do a good job in site selection planning and control of all farmers' markets.
The planning and commercial departments of the housing and construction departments prepare topographic maps and red line maps of the planning and site selection of each farmer's market, and the housing and construction departments and the land departments plan and control the market site selection area according to the red line map, strictly restrict the site selection for other construction, and ensure the matching of the county market.
2. Scientific positioning of new markets.
It is suggested that the functions of the newly-built market should be scientifically set, in which the east market highlights the sales of dry goods and local agricultural specialties, the west market highlights the wholesale sales of fruits, and the south market highlights the trading of aquatic products and seafood.