1, the construction unit shall submit the following materials:
(1) application report for project completion acceptance (including project completion, inspection results of acceptance conditions, preparation of acceptance organization, suggested acceptance time, place and participating units);
(2) Project construction management work report;
(3) memorabilia of engineering construction;
(4) List of pending projects, list of unfinished projects, construction arrangement and construction period of unfinished projects, existing problems and solutions;
(5) Preliminary acceptance report;
(6) Completion Acceptance Certificate (draft);
(7) Engineering application and flood control scheme;
(eight) the project construction supervision work report;
(9) Engineering design work report;
(10) water conservancy and hydropower engineering quality evaluation report;
(1 1) project construction management work report;
(12) Special report on major technical issues;
(13) Project operation management preparation report;
(14) Report on compensation and resettlement for land requisition for engineering construction;
(15) project file self-inspection report;
(16) Audit report or audit opinion on final accounts of project completion
2. Examination and approval procedures: The water conservancy (water affairs) bureau will examine and approve and organize the acceptance.