I. Single machine commissioning
Personnel, supporting materials, schedule, records, reports, rectification and verification
II. Linkage commissioning
Personnel, supporting materials, linkage program, records, reports, optimization and improvement
III. Sludge cultivation
(A) Pre-preparation
1. p>
1, the site should have the commissioning conditions, personnel to complete job training
2, activated sludge cultivation of materials required for the preparation
3, water quality analysis preparation
(2) activated sludge cultivation
1, cultivation of the idea p>
2, cultivation program p>
a, bored aeration of the inoculation p>
b, dynamic culture
c, continuous load operation
d. Stable operation
e, culture schedule
f, during the cultivation of analysis and detection of indicators: indicators to be analyzed by the laboratory; operation of direct detection, observation of the indicators: microscopy, aeration tank water temperature, SV30, etc..
Four, the water area of the whole process load operation
Five, the mud area of the whole process operation
Six, abnormalities
The commissioning of the wastewater treatment plant is a systematic process, the various links are interlinked, constraints, a link of the abnormalities, failures will affect the normal conduct of the commissioning. Factors affecting include:
1, power outages, power system equipment failures;
2, water treatment equipment mechanical and electrical failures;
3, pipelines, structures, equipment clogging;
4, water quality and water quality;
5, force majeure such as natural disasters.
VII, commissioning summary
VIII, comments and suggestions