How to write a project construction program

Question 1: How to write a project construction implementation program? xxxx City Center Hospital

Ward building project construction implementation plan

First, the guiding ideology

In order to accelerate the pace of construction of ward building, alleviate the tension of hospitalization in the hospital district, improve the patient's hospitalization environment to meet the needs of patients, and better provide quality services for the patients, while enabling the ward building to play an economic benefit as soon as possible. To complete the 2011 economic income targets and five-year plan to lay the foundation.

Second, the construction goals

The construction of the ward building to meet the design requirements, that is, to complete the internal and external renovation, the installation of internal equipment in place, with the conditions for receiving patients.

Third, the establishment of the organization

Group Leader: xxx

Deputy Group Leader: xxx

Members: xxxx,xxxx

Fourth, the specific measures

1, the development of the construction plan, drawing construction nodes to complete the detailed drawings.

2, in accordance with the construction plan, the organization of construction units to discuss, analyze, and determine the unit construction program and progress.

3, the main line of construction of the interior decoration, the development of monthly and weekly construction plans. Installation and other ancillary construction according to the interior plan to develop construction programs and implementation of the construction plan. Ensure that the progress of the renovation to the end.

4, take cross construction, shift work way to promote the construction progress.

5, the development of incentives and penalties to ensure that the construction of the ward building construction progress on schedule.

V. Assessment and rewards and punishments

1, the ward building put into use, the early completion of the target tasks related to the hospital with the department and individual rewards.

2, the implementation of monthly quantitative assessment of the progress of the project, the amount of work completed on time to plan the construction unit in the allocation of funds to give priority to. Failure to complete the construction program on time to give economic penalties.

Sixth, the progress of the plan

1, outside the decorative works: February 25 - May 27 to complete the construction of decorative panels on the exterior walls. This includes the east elevation completed before March 8th. West elevation completed before March 11th. North elevation completed before March 25th. South elevation to be completed by April 18th. Roof and sixth floor to be completed by April 30th. Decorative board painting, completed before May 27th.

2, interior decoration works: March 1 - May 20 to complete the decoration works. Among them, the construction of floor and wall tiles was completed on April 12th. Ceiling, curtain box, sealing wall construction completed before May 20th. Stairwell, ward, office room wall paint construction completed on May 10th. Stainless steel tie rod construction completed on May 12th.

3, civil engineering: March 1-April 30 to complete the civil rough construction.

4, water supply and drainage works: March 1 - June 2 to complete the construction of water supply and drainage works. Among them, hot and cold water system construction completed before May 25th. Drainage system construction completed before May 17th. Sanitary ware installation completed before June 2nd.

5, strong electrical engineering: March 1 - June 9 to complete the construction of electrical engineering.

Among them, layer bridge, wire pipe, wiring, cable. completed before April 10th. Distribution box installation and pressure line completed before May 9th. Cable laying and pressure line completed before April 24th. Lighting, panel installation completed by June 2nd. Bathroom exhaust fan hanger and duct installation completed before March 26th. Lightning protection and grounding completed before April 19th. Power running debugging completed on June 9th.

6, other projects: fire systems, weak power systems, air conditioning systems, medical gas systems, purification systems, corridor construction, peripheral pipeline construction and hardening and other ancillary construction to actively cooperate with the internal and external renovation construction progress, before May 30th, with the conditions for delivery.

7, the project follow-up work: July reported to the competent authorities to give the organization acceptance, and organization of all engineering information to verify, do a good job before the audit of the preparatory work. August will be the final account of the project information reported to the audit department for audit. Strive to end the audit before the end of the year.

VII, the central hospital ward building 2011 progress schedule (attached)

March 13, 2011

Question 2: engineering project proposal to be written Chengdu Zhongzhe for your answer

Engineering construction cost in China for a long time there is a budget estimate over the estimate, budget over the estimate, final account over the budget of the three super phenomenon, a serious plague on the construction engineering Investment efficiency and management. Engineering construction project proposal is to optimize the construction program, design program on the basis of the various stages of the construction process, the use of certain methods and measures to control the incidence of construction costs within a reasonable range and approved cost limits and put forward the project proposal.

An engineering construction project from the plan to build to be completed and put into operation, generally through the construction decision-making, construction implementation and delivery of three stages. Zhongzhe consulting suggests that the main steps are:

1, the project proposal

The project owner according to the national economy and social development of long-term planning, industry planning and construction of the unit where the town planning requirements, according to the unit's development needs, after the investigation, prediction, analysis, compilation of engineering and construction project proposal.

2, feasibility study report

After the approval of the project proposal, the project owner commissioned the appropriate qualifications of the professional writing institutions, the proposed project in technology, engineering, economic and external collaboration conditions and other aspects of the feasibility of the project, to conduct a comprehensive analysis, demonstration, comparison of the program, and recommend the best program.

3, preliminary design

After the approval of the feasibility study report, the project owner commissioned a qualified design unit, in accordance with the requirements of the approved feasibility study report, the preparation of preliminary design. After the approval of the preliminary design, the design estimate is the maximum limit of investment in the project, without approval, shall not be arbitrarily exceeded.

4, construction design

After the approval of the preliminary design, the project owner entrusted the design unit with appropriate qualifications, in accordance with the approved preliminary design, the organization of construction design.

5, the annual investment plan

The construction project proposal, feasibility study report, preliminary design approval to the competent authorities to apply for inclusion in the investment plan.

6, the commencement report

7, completion and acceptance

To control the choice of design options and preliminary design cost estimates with investment estimates; cost estimates to control the cost of technical design and revised estimates; engineering and construction projects must be used appropriately, cost estimates or revised estimates to control the cost of construction drawings and budget costs. In order to rationalize the use of human, material and financial resources, to achieve better investment efficiency.

Question 3: how to write the building construction program plan? Construction Organization Design

A project overview

(a), the preparation of the basis, design specifications and construction standards

1, engineering construction design documents and construction design drawings and related design documents.

2, bidding documents, bidding minutes and other relevant information.

3, the state and higher units and the company's safety, civilized construction regulations, rules.

4, the natural conditions of the construction site and specific circumstances. (hydrogeology, meteorological environment, transportation, water supply and power supply, etc.).

5, the company's quality system based on ISO9001 relevant documents.

6, the current national mandatory standards for engineering construction:

7, provincial, industry regulations, norms:

8, quality acceptance norms, standards:

9, China's other current construction acceptance norms and operating procedures.

10, my company's existing technology, equipment and years of accumulated construction experience in similar construction projects information.

(ii), the location of the project

(c), architectural design

(d), structural design

(e), process design

(f), quality standards

The quality of this project has reached the qualified standard.

Second, the overall construction program and construction preparation

(a), the mobilization cycle

(b), the construction of the guiding ideology

(c), the construction of the unfolding order

(d), the progress of the project

Specific construction deadlines:

(e), the construction of the task of the division of

(f), Temporary facilities works

(7), the list of temporary works

No. name area m2 location start date

(8), the main construction machinery, equipment requirements plan

construction machinery and equipment list

Serial name specifications need to be Remarks

unit number

Third, the general sub-parts of the project Project construction program

(a) construction sequence

(b) construction measurement

1. Measuring instruments

construction measuring instruments see "Measuring Instruments Selection Table". As follows:

Measuring apparatus selection table

Name model number accuracy use

2, Reinforcing steel works

Project allowable deviation (mm) test method

(F), template works

(G), concrete works

(H), expansion joints, construction joints retention

(IX), scaffolding works

(J), water test

Fourth, construction technology measures

(A), bedding construction

(B), bottom construction

(C), column construction

(D), wall construction

(E), the top construction

(F), the construction of watering zone

(G), the prevention and control of quality of the concrete disease

V. Project quality assurance system and measures

(I.) Quality policy:

(ii.) Quality objectives:

(iii.) Quality Management

Quality Management Program

1. Quality Assurance Program

2. Process Quality Execution Program

(IV.) Quality Control

VI. Safety Measures to Ensure the Project

(I.) Management Objectives

(II.) Organizational Management

(III.) Safety Management System

(IV.) Behavioral Control

(V.) Management of Labor Employment

(VI.) Construction Safety Precautions

VII, Civilized construction and environmental protection measures

(a), management objectives

(b), organizational assurance

(c), the work system

(d), civilized construction measures

(e), to prevent air pollution

(f), to prevent water pollution

(g), to prevent the construction of noise pollution

(d) Safety production management system

(e) Construction organization and management structure of efficient operation of the safeguard measures

(f) Guidelines and target management

Nine, the main labor force arrangements

Ten, the main materials, components plan

Eleven, the main machinery and equipment supply plan

Twelve, to ensure that Guarantee measures to ensure the construction progress plan

(a), schedule commitment

(b), to ensure that the construction progress plan of the technical and organizational measures

xiii, winter, rainy season construction measures

(a), the seasonal construction technical measures

(b), the rainy season construction program

(c), the winter construction technology

Fourteen, financial security and construction measures to reduce construction costs

(a), financial security measures

(b), construction measures to reduce construction costs

Fifteen construction organization to ensure that measures ... >>

Question 4: engineering construction bidding program, there is no model? MBA Think Tank document should have this kind of reference model, you go there to look for look at it.

Question 5: engineering construction report outline how to write? General product production engineering project feasibility report outline Zhengzhou Jingliu Zhicheng enterprise management consulting preparation

General

1.1 Project name and project unit

1.2 Project construction location

1.3 Project construction scale and content

1.4 Project investment estimation and financing

1.5 Preparation of scope and

1.6 Conclusion and Recommendation

1.7 Main Technical and Economic Indicators

Chapter 2: Background and Necessity of General Product Production Project Construction

2.1 Background of General Product Production Project Construction

2.2 Necessity of General Product Production Project Construction

Chapter 3: Analysis of Market Demand

Chapter 4: Analysis of Market Demand <

Chapter 4 Construction Conditions and Site Selection of General Products Production Project

4.1 Geographic Location

4.2 Natural Conditions

4.3 Socio-Economic Condition

4.4 Infrastructure Condition

4.5 Transportation Condition

4.7 Site Selection.

Chapter 5 Construction Program of General Product Production Project

5.1 Construction Content

5.2 Construction Principles

5.3 Planning Program of General Product Production Project

5.4 Engineering Program

Chapter 6 Utility Projects of General Product Production Project

6.1 Water Supply and Drainage <

6.2 Power Supply and Distribution

6.3 Ventilation and Air Conditioning

6.4 Maintenance

Chapter VII General Products Production Project Energy Saving and Water Saving Measures

7.1 Energy Consumption Standards and Energy Saving Specifications

7.2 Energy Saving Measures

7.3 Energy Saving Management

7.4 Water Saving Measures <

7.5 Comprehensive Utilization of Resources

Chapter 8 Environmental Protection

8.1 Environmental Protection Enforcement Standards

8.2 Main Pollution Sources and Pollutants

8.3 Environmental Protection Measures

8.4 Conclusion on Environmental Protection

Chapter 9 Labor Safety, Health and Fire Fighting of General Products Production Project

9.1 Labor Safety and Health

9.2 Fire Safety

Chapter 10 General Product Production Project Organization and Human Resource Allocation

10.1 Organization

10.2 Labor Fixing

10.3 Project Management for General Product Production Project

Chapter 11 General Product Production Project Implementation Progress and Bidding

11.1 Implementation Progress

11.2 Bidding

Chapter 12 Investment Estimation and Financing of General Products Production Project

12.1 Investment Estimation

12.2 Financing

Chapter 13 Financial Evaluation of General Products Production Project

13.1 Basis and Scope of Financial Evaluation

13.2 Selection of Basic Data and Parameters

13.3 Estimation of Financial Benefits and Costs

13.4 Financial Analysis

13.5 Analysis of Uncertainty

13.6 Conclusion of Financial Evaluation

13.7 Risk Analysis

Chapter XIV Conclusions and Recommendations

14.1 Conclusions

14.2 Recommendations with Figures and Schedules

Question 6: How to write a construction proposal for a building project bid know (1) Bidding letter;

(2) Bidding letter appendix;

(3) Bidding deposit;

(4) Certificate of identity of the legal representative;

(5) authorization letter for signing the bidding documents;

(6) other information required by the bidding documents to be submitted by the bidder (there is no format for this item, and the bidder will put forward in text or table form when needed).

The commercial part mainly includes the following:

Using the comprehensive unit price form:

(1) the requirements of the tender offer;

(2) the tender offer summary table;

(3) the main materials list offer table;

(4) equipment list offer table;

(5) the works list offer table;

(6) price calculation table for bill of quantities items;

(7) other information required for the tender offer (this item is not in the form, if necessary, by the bidder in the form of text or tables, or the bidder in the tender offer).

Using the form of unit price:

(1) the requirements of the bidding price;

(2) the bidding price summary table;

(3) the list of the main materials quoted table;

(4) the list of equipment quoted table;

(5) division of the project work and material price table;

(6) the cost of the project division;

(6) the cost table;

(8) the cost table;

(9) the cost table;

(10) the cost table. Calculation table;

(7) tender offer other information required (this item is not in the form, when needed by the bidder in writing or form, or the bidder in the tender offer).

11.4 The technical part mainly includes the following:

(1) construction organization design or construction program

a. The main construction method of each sub-projects;

b. The main construction machinery and equipment invested in the project, and the main construction machinery into the field plan;

c. The labor force scheduling plan;

d. The technology to ensure the quality of the project. Technical organization measures to ensure the quality of the project;

e. Technical organization measures to ensure production safety;

f. Technical organization measures to ensure the civilization of the construction;

g. Technical organization measures to ensure the duration of the construction period;

h. Construction of the general plan;

I. It is necessary to explain the other contents.

(2) Project management organization

a. Project management organization table;

b. Resume table of project manager;

c. Resume table of project technical person in charge;

d. Other auxiliary explanatory information. (3) The name of the project to be subcontracted and the subcontractor.

Application for Qualification includes:

(1) General information about the bidder;

(2) Annual turnover data sheet;

(3) List of works completed in the last three years;

(4) List of works currently under construction;

(5) Statement of financial status in the last three years;

(6) Statement of status of the joint venture.

(7) experience in similar projects;

(8) experience in construction with similar site conditions;

(9) other information required by the bidder.

Question 7: engineering and construction procurement documents need to write the technical bid, how to write the project implementation program ah? Write specific construction methods? Or something else? Description of the bidding documents for the model, bidding units bidding should be based on their own actual situation and bidding documents, bidding applicants pre-qualification instructions and other documents to prepare the bidding documents, bidding documents by the bidding letter part, the business part and the technical part of the three parts. Project construction bidding tender documents Project No.: Project Name: Bidding documents: Bidding documents bidding letter part Bidder: (seal) legal representative or his proxy: (signature or seal) Date: Table of Contents legal representative certificate of identity bidding documents signed authorization power of attorney bidding letter bidding letter Appendix Bidding stretcher Bank Guarantee Format Tender Guarantee bidding documents required to be submitted by the bidder to the other bidding information Name of organization: Nature of organization: Date of establishment: Period of operation: Name: Sex: Age: Position: He is the legal representative of (Name of Bidder's organization). Hereby certify that. House building and municipal infrastructure construction tender documents model two, tender documents signed by the authorization letter This power of attorney declares: I (name) is the (name of the authorized person) of the legal representative of the (name) is authorized to entrust the (name) of the (name of the unit) for the company to sign the bidding documents of the project's legal representative of the authorized agent, I acknowledge that the agent of the bidding documents signed on behalf of my full authority for the project. Content. I recognize that the agent has full authority to sign the bidding documents for this project on my behalf. The agent has no right of sub-delegation and is hereby authorized. Agent: (signature) gender: age: ID card number: position: legal representative: (signature or seal) entrusted to authorize the date: to: (name of the bidder) 1, according to your bidding project number for the project bidding documents, in accordance with the relevant provisions of the project site and study the above bidding documents of the bidding instructions, the terms of the contract, drawings, construction standards and bill of quantities of the project and other relevant documents, we would like to be the first to sign the tender documents for this project. After visiting the project site and studying the bidding instructions, contract terms, drawings, construction standards and bill of quantities and other relevant documents in the above mentioned bidding documents, we are willing to offer a bid in (currency, amount, unit) (lower case) and contract for the construction of the above mentioned project according to the above mentioned drawings, contract terms, construction standards and bill of quantities and assume the responsibility of warranty for any quality defects. 2,We have examined all the bidding documents in detail, including the modification documents (if any) and the relevant attachments. 3,We acknowledge that the addendum to the bidding letter is an integral part of our bidding letter. 4, If we are awarded the tender, we guarantee to complete and hand over all the works within the calendar days of the construction period specified in the contract agreement. 5, If we are awarded the contract, we will submit a bank guarantee for % of the above total price or a performance guarantee for % of the above total price issued by a qualified and competent surety organization as a performance guarantee in accordance with the provisions of the contract. 6,We agree that the bidding documents submitted by us shall be valid during the bidding period specified in Clause 15 of the Instructions to Bidding Applicants and we shall be bound by the same if we are awarded the bid within this period. 7. Unless otherwise agreed and effective, your notification of award and this tender document will become part of the contractual documents binding the parties. 8,We will submit (currency, amount, unit) as a bid security together with this bid letter. Legal representative or agent: (signature or seal) name of the bank: account bank account number: date four, the bid letter appendix No. item content of the contract terms and conditions of the contract No. agreed content Remarks performance bond bank guarantee performance guarantee amount of the contract price of the % of the construction of the construction of the preparatory time after the signing of the contract after the days of the missed liquidated damages amount of yuan days missed compensation fee limit of the early deadline award the construction of a total construction period of calendar days of quality standards of the quality of the project Advance Payment Amount Advance Payment Guarantee Amount Progress Payment Time Days after Issuance of Monthly Payment Voucher Completion Settlement Payment Time Days after Issuance of Completion Settlement Payment Voucher Warranty Period Based on the Period Agreed in the Warranty Letter IV. Bidding Documents V. Format of the Bidding Guarantee Bank Letter of Guarantee (Specific Format to be Provided by Guarantee Bank) VI. (hereinafter referred to as the Bidder) and (Bid Guarantee Agency) as the Guarantor (hereinafter referred to as the Guarantor)*** together assume the responsibility to pay (currency, amount, unit) (lower case) to (name of Bidder) (hereinafter referred to as the Bidder), and both the Bidder and the Guarantor shall be bound by this Guarantee. The Guarantor is willing to provide the Bidder with a Bid Security in view of the Bidder's participation in the Bidding for the Bidding of the Bidder's (Bidding Project). This guarantee is conditional upon the Bidder failing or refusing to sign the Contract Agreement as required by the Instructions for Bidding, failing or refusing to submit the Performance Bond as required by the Instructions for Bidding, or withdrawing the Bidding Documents during the Bidding Period if the Bidder receives a Notice of Award from you during the Bidding Period. Insofar as you specify the conditions that give rise to any of the foregoing, ...... >>

Question 8: planning design program and construction engineering program design what is the difference between the engineering construction process is as follows: project proposal ---------- preliminary design stage - - construction drawings design stage - - bidding stage - - contract implementation stage - completion and acceptance of the stage and feasibility of the stage of the paragraph ||||| investment estimates ---------- Design estimate ------ budget cost ---------- contract price ------- settlement price ----- actual cost (final price) budget estimates have feasibility study investment estimates and preliminary design estimates of two kinds, the budget and construction drawings design budget and construction budget, capital construction budget is the general name of the above estimates, estimates and budgets. In the different stages of the project, project investment has estimates, budget estimates, budgets, settlements and final accounts and other different names, these "calculations" based on different roles, and its accuracy is also "progressively more detailed", one more than a more realistic reflection of the actual investment in the project. 1. Estimation, also known as investment estimation, occurs in the project proposal and feasibility study stage; Estimation is based on the project planning program (program design), the project may incur engineering costs (including construction and safety works, outdoor works, equipment and installation works, etc.), other costs of engineering and construction, preparatory costs and interest during the construction period (if there is a loan) for the calculation of the scale of the investment in the project and the choice of financing options, for reference by the project investment decision-making department. For the project investment decision-making departments for reference; estimates should pay attention to accurate and comprehensive calculation of other costs of construction, this part of the cost of regional and policy is strong. 2. Estimates, also known as the design estimates, occur in the preliminary design or expansion of the preliminary design stage; estimates need to have a preliminary design or expansion of the preliminary design drawings, the construction costs of the project construction costs calculated to determine the cost of the project; preparation of budget estimates should pay attention to not omitted, missing items or double-counting, the standard should be consistent with the fixed amount. Budget is also called construction budget, which occurs in the stage of construction design; budget needs to have construction drawings, summarize the project man, machine, material budget, determine the cost of construction and safety works; the key to prepare the budget is to calculate the amount of work, accurately applying the budget quota and fee standards. 4. Settlement is also called the completion of the settlement, which occurs in the stage of acceptance of the completion of the project; the settlement is generally made by the engineering contractor (construction unit). Contractor (construction unit) submitted, according to the project construction process of change negotiation, adjust the construction budget to determine the final settlement price of the project; settlement is based on the construction contract and change negotiation records (note that all parties sign), accurate calculation of the tentative price and the actual amount of the deviation, against the relevant amount of standards, calculating the construction budget of the construction of the omission and lack of part of the project cost entitlement.

Question nine: how to write the construction project is construction contracting "program". Wenshan County Xinpingba urban village renovation project implementation plan

First, the project renovation implementation plan

In order to improve the appearance of the village of Xinpingba village, so that the village has become a set of logistical support with the Wenshan Panax ginseng park, ethnic customs, food culture as one of the new rural areas, to solve the villagers in the loss of the land of the life of the way out of the issue of the full implementation of the Wenshan County, the transformation of the old city, to speed up the pace of urban construction, to add to the cityscape, the pace of construction of the city, and to solve the problem of the villagers in the loss of land. The pace of construction of Wenshan County, adding bricks and mortar to the cityscape and creating a better economic atmosphere. With reference to the State Council Decree No. 305 "urban housing demolition and relocation management regulations" and the Yunnan Provincial People's *** Decree No. 109 "Yunnan Provincial Urban Housing Demolition and Relocation Management Provisions" of the relevant provisions of the actual situation, combined with the new Pingba villagers group, the new Pingba villagers group to apply for research by the Wenshan County People's *** agreed to the Wen Zheng Ban Fa [2005] No. 487 approved by the new Pingba villagers group to organize the implementation of the old village renovation of the new Pingba village. Implementation of the new Pingba village old village renovation work, in order to make this work smoothly, especially the development of this implementation plan.

(a) the scope of the demolition

New Pingba old village within the scope of the renovation, the land owned by farmers, houses and appurtenances.

(2) demolition and resettlement work steps and time

1. The legal title of the farmers' houses and appurtenances for the assessment of the farmers' land (containing the use of certificates, undocumented, self-reserved land) for the measurement of the announcement. (Time for November 2005-February 2006)

2. Publicity and mobilization, the demolition announcement. (Time for November 2005-February 2006)

3. Signing the old village transformation agreement with each farmer. (Time for 2006 January - March 2006)

4. Organize the demolition of houses and appurtenances of farmers, building temporary housing. (Time for February 2006-March 2006)

5. Planning area site leveling, construction of road rough. (Time for March 2006-April 2006)

6. Cashing in the land for resettlement of farmers and building houses by each farmer. (Time for March 2006-December 2006)

7. Collectively improve the construction of roads and electricity, telecommunications, water supply and drainage, put into use. (Before December 30, 2006)

(C) Compensation

After the assessment report on the farmers' house property rights was made by Lianyi Appraisal Company, Xinpingba villagers' group gave one-time compensation according to the assessment price. There is no monetary compensation for homesteads, self-reserved land, and vacant land.

The expropriation price of contracted land is uniformly 62600 yuan/mu, which is a one-time compensation from Xinpingba villagers' group.

(D) resettlement

1. Old village renovation farmers land cash

(1) local resettlement of farmers, according to the original certificate area and the area of undocumented area (including self-owned land) of the total area of the resettlement of the land cash, the delineation of the land according to the 10-meter-wide unit, the resettlement of the land area is calculated to include the housing footprint, the area in front of the door to the area of concession, the area of the open space behind the house. Less than a unit of area, by the collective acquisition of 100 yuan / square meter to the farmers, the farmers can not be privately transferred to the outside world.

(2) local resettlement of farmers, according to the original certificate area and the total area of undocumented area (including self-owned land) to cash resettlement land, land allocation according to the 10-meter-wide unit, the resettlement area is calculated to include the area of the house, the area of the front concessions, the area of the open space behind the house, less than the area of a unit of $ 100 / square meter by the farmers to the collective to buy, but farmers can not be used for the external The company's website is not available to the public.

(3) Land use certificates are issued for state-owned land use certificates according to the actual realized area. The houses, walking roads and green areas within the scope of the land use certificates are constructed by the user in accordance with the planning (the part of the setback next to the driveway is constructed by the collective), and the construction must be carried out in strict accordance with the planning.

(4) resettlement plots in accordance with the first signed agreement to the order of the day of the lottery to prioritize the selection of local resettlement sites. Not in the local resettlement of farmers, by the villagers group in accordance with the assessment of the company's compensation price to implement the resettlement, the collective is responsible for the resettlement of the area of the road, water supply, power supply work. Farmers who are not in the planning area (with Wenma Highway as the boundary) are willing to participate in the planning, according to the area of each farmer's own land as the standard land, such as less than one, the difference in the area of the part of the area of 500 yuan / ?O to the collective purchase.

(5) Arrangement of temporary resettlement land and compensation for resettlement subsidies

The demolition is carried out by the first group of 70 meters of the Sanqi Industrial Park, and the second group of 60 meters inward in turn. Temporary resettlement land in Sanqi Industrial Park, each household is allocated to 80?O temporary resettlement land, the first demolition of the first recognized land. In February 15, 2006 before the signing of the agreement, February 28 before the relocation of the demolition of the farmers, by the villagers group to give 1000 yuan / household resettlement subsidy fee incentives, the construction of the planning area of the farmers must be in March ...... >>

Question ten: how to write a construction project planning application A so-and-so limited company document so-and-so [2007] 06 on the request to give "so-and-so" district construction project report Luqiao District Development and Reform Bureau: Luqiao District "so-and-so "District (tentative name) is located in the streets of Luqiao District, the land by the Taizhou City Bureau of Land and Resources Luqiao Branch in December 8, 2005 announcement by auction. December 29, 2005 by the Taizhou City Limited company to ten thousand yuan price bidding to obtain the right to use the land, and pay the deed tax of ten thousand yuan, and June 16, 2006 to obtain the land certificate. The project has obtained the environmental impact report form of Taizhou city limited company's new road community project environmental impact report form approval and road water sea fishery [] No. on Luqiao District Lotus Pond Jiayuan community project soil and water conservation program approval. In accordance with the approval of the construction detailed planning of Taizhou Luqiao District by the No. of Taizhou Jianzhu [], the land area of the district of Taizhou Luqiao District "" is from the north to the land boundary, from the south to the planning road, from the east to Yinyuan Road, from the west to the planning road, with the area of requisitioned land of square meters, and the net area of land of square meters. The total construction area is square meters (excluding basement), of which the residential construction area is square meters, the club building area is square meters, and the property management is square meters. The basement construction area is square meters. It consists of a small high-rise residential building and a clubhouse. It is expected that the project construction investment of 100 million yuan (excluding land payment), the funds will be invested by our company in batches, take the side of the development and sales, the lack of bank loans and self-financing to solve the problem. I earnestly request your bureau to establish the project. Hereby report! Taizhou City, Ltd. July 4, 2007 Subject: construction project project report Taizhou City, Ltd. Office issued on July 4, 2007 must be red-title documents (internal information was deleted by me please understand)