What are the requirements of the archiving program for engineering information

I. Filing content

1. Preliminary documents:

Serial number

Contents

1

Project proposal and the approval of the opinion, the notice of preliminary work

2

Feasibility study report (including annexes) and the approval of the opinion

3

On the establishment of the project-related Minutes of meetings, leadership speeches

4

Survey information and project evaluation and research materials, expert advice

5

Construction project siting opinion (including survey red line map)

6

Land use submission form, land use approval and other process documents and materials

7

Land allocation and transfer of Construction land use documents (land allocation decision, transfer contract and process documents)

8

Construction land use planning permit, annexes and attached maps, state-owned land use certificate (copy)

9

Demolition and resettlement documents (opinions, agreements, programs, etc.)

10

Engineering, hydrogeological investigation report

11

Survey and demarcation (land requisition and sampling), land mapping results, positioning, ± 0.00 detection sketch

12

Landscape, sunshine analysis

13

Programs, preliminary design (text) and approval of the documents (including attached drawings)

14

Related administrative Authorities (fire, human defense, environmental protection, environmental assessment, transportation, traffic assessment, gardening, municipal, cultural relics, seismic, education, health, etc.) approval of documents or relevant agreements obtained

15

Construction drawings and design review documents and approval of opinions

16

Construction projects included in the annual plan of the declaration, approval of the documents, the annual plan of the project table

17

Construction project planning permit, annexes and accompanying drawings

18

Investment permit, audit certificate, proof of fees and charges for human defense, infrastructure support, bulk cement, wall reform, termite prevention and treatment (including contracts), quality and safety supervision certificate, letter of guarantee, etc.

19

Construction project construction permit

2 Bidding Documents:

No.

Contents

Remarks

1

Bidding Announcement

2

Aggregate List of Bidding Applicants

3

Bidding Pre-qualification Report and Attachment

4

Bidding Document

5

Tender Q&A

6

Record of Tender Opening

7

Tender Evaluation Forms and Reports

8

Tender Determination Report

9

Bidding Documents of Successful Bidder (Technical and Commercial Bids, and Post-qualification)

10

Notification of Successful Bid

11

Complaint report, report receiving, processing correspondence and other processing information

12

Survey Contract

13

Design Contract

14

Construction Contract

15

Supervision Commissioning Contract

16

Other engineering contracts (e.g. A subcontract, A-supplied main material contract)

3. Supervision documents:

Serial No.

Intent

Remarks

1

Supervision planning

2

Supervision implementation rules

3

Supervision monthly report

4

Minutes of Supervision Meetings

5

Project Commencement/Resumption Reporting Forms, Project Suspension Orders

6

Supervision Notices, Notice Response Forms, Quality Accident Reports and Handling Opinions

7

Project Completion Final Accounts Audit Opinions

8

Progress Extension report and approval

9

Contract changes, disputes, breach of contract materials and processing opinions

10

Summary of supervision work

4, construction documents:

Serial number

Contents

Remarks

1

Opening and completion reports

2

Construction site quality management inspection records

3

Engineering measurement and positioning records, building settlement observation measurement records

4

Drawing review

5

Design changes, negotiation records and summary tables

6

Engineering quality accidents and accident investigation and handling Data

7

New materials, new technology construction records

8

Energy-saving division data

(1)

Insulation materials factory certificate, promotion certificate, inspection report and retest test report

(2)

Covered project acceptance records

(3)

On-site physical inspection report of building energy-saving projects (on-site heat transfer coefficient of walls and roofs; heat transfer coefficient of windows; on-site airtightness of windows; energy-saving structure of external walls, etc.)

(4)

Other information

9

. Steel, cement, brick, prefabricated components, ready-mixed concrete, welding, waterproofing, decoration and other materials summary table, factory documents, retest test report

10

Construction test reports and witness test reports (such as: concrete, mortar test block compressive strength test report, concrete seepage resistance test report, steel welding test report, etc.)

11

Record of acceptance of concealed works of foundation

12

Construction records (e.g., concrete construction diary, technical review records, foundation groove inspection, etc.)

13

Inspection of foundation and sampling test data

14

Basement waterproofing effect inspection records

15

Intermediate structure acceptance record

16

Separately filed sub-division construction data (e.g., piling sub-division)

(1)

Piling commencement report, handover acceptance certificate

(2)

Material summary table of piling project steel, cement, bricks, prefabricated components, etc., factory certification documents, retesting test reports

(3)

Concrete, mortar test block compressive strength and steel welding test report

(4)

Driving (test) pile records

(5)

Concealed project acceptance records

(6)

Pile position review records, pile deviation records

(7)

Pile testing reports (including static load and dynamic measurement)

(8)

Piling as-built drawings

(9)

Other information

17

Main body construction test report and witness test report

18

Building verticality, elevation, full height measurement records

19

Main body hidden work acceptance Records

20

Body construction records (e.g., concrete construction diary, technical review records, etc.)

21

Body structural inspection and sampling test data

22

Body intermediate structural acceptance records

23

Separately filed sub-division of construction data (e.g.: Steel Structure Sub-division)

(1)

Materials, fittings factory certificates, incoming inspection (test) reports

(2)

Steel Structure Inspection and Sampling Report

(3)

Concealed Work Inspection Records

(4)

Construction Records

(5)

Other Information

24

Decorative decoration construction test report and witness test report (doors and windows, dry hanging, anti-extraction)

25

Record of water storage test for floors with waterproofing requirements

26

Record of acceptance of concealed works of the decorative decoration

27

Record of inspection of air extraction (air) ducts

28

Decorative decoration construction records (e.g., concrete construction diary, technical review records, etc.)

29

Curtain wall and exterior window airtightness, watertightness, wind pressure inspection report

30

Separate archived sub-division construction data (e.g., curtain wall sub-division)

(1)

Design basis Documents, calculations

(2)

Design changes, negotiation records

(3)

Materials, fittings factory certificates, incoming inspection (test) reports

(4)

Covered project acceptance records

(5)

Curtain wall of building use and maintenance manuals

6

Other information

31

Roofing construction test report and witness test report

32

Roofing drenching test record

33

Roofing concealed work acceptance record

34

Roofing construction records (e.g., concrete construction diary, technical review records, etc.)

35

Roofing separately filed sub-division construction data

36

Installation of drawing review

37

Installation of design changes, negotiation records and summary tables

38

Installation of (water) materials, fittings factory certificates and incoming inspection (test) report

39

Installation (water) piping, equipment strength test, tightness test records

40

Installation (water) hidden works acceptance records

41

Installation (water) equipment foundation acceptance records

42

Installation (water) system cleaning, flooding, water and ball test records

43

Installation (water) construction records

44

Installation (water) heating pipes, radiators pressure test

45

Installation (water) sanitary appliances full water test records

46

Installation (electricity) materials, equipment factory certificates and incoming inspection (test) inspection report

47

Installation (electrical) equipment commissioning records

48

Installation (electrical) grounding, insulation resistance test records

49

Installation (electrical) hidden works acceptance records

50

Installation (electrical) construction records

51

Installation (electrical) Energized, lighting full load test records, large lamps and lanterns firmness test records

52

Installation (electrical) wiring, sockets, switches and grounding inspection records

53

Engineering design changes (water and electricity) contact sheet summary

54

Air-conditioning materials, equipment and factory certificates of conformity and incoming inspection (test) and test reports

55

Refrigeration, air-conditioning water pipeline strength test, tightness test records

56

Air-conditioning hidden engineering acceptance records

57

Air-conditioning foundation acceptance records

58

Air-conditioning and refrigeration equipment operation commissioning records

59

Ventilation, air conditioning system commissioning records

60

Air conditioning construction records (such as: air ducts, air outlets, fan equipment installation records, etc.)

61

Ventilation, air conditioning system commissioning records

62

Air volume, temperature test records

63

Cleanroom cleanliness test records Record

64

Elevator equipment factory certificate and unpacking inspection records

65

Elevator hidden works acceptance record

66

Elevator foundation acceptance record

67

Elevator construction record

68

Elevator grounding, insulation Resistance test records

69

Load test of elevator, safety device inspection records

70

Elevator operation records

71

Elevator safety device test report

72

Labor and technical supervision department acceptance report

73

Intelligent materials, equipment factory certificates and incoming inspection (test) report

74

Intelligent hidden works acceptance records

75

Intelligent system function determination and equipment debugging records

76

Intelligent system technology, operation and maintenance manuals, training records

77

77 p>

Intelligent construction records

78

Intelligent system test reports and operation records

79

Intelligent system power supply and grounding test report

80

Fire protection engineering construction data

(1)

Fire protection waterproofing materials, accessories factory certificates, incoming inspection (test) reports ) inspection report

(2)

Fire piping, equipment strength test, tightness test records

(3)

Fire water hidden project acceptance records

(4)

System cleaning, flooding, water, ball test records

(5)

Fire water construction records

6

System and equipment commissioning records

(7)

Fire electrical materials, fittings factory certificates, incoming inspection (test) reports

(8)

Equipment commissioning records

(9)

Grounding, insulation resistance test records

(10)

Fire electrical hidden works acceptance records

(11)

Fire-fighting electrical construction records

(12)

System commissioning records

(13)

Other information

81

Construction documents for outdoor installations (water supply, rainwater, sewage, heat, gas, telecommunication, electric power, lighting, TV, and fire-fighting, etc.)

82

Outdoor built environment (architectural vignettes, water features, road landscaping, etc.) construction documents

83

Unit (sub-unit) project quality completion acceptance records, control information verification records, verification of safety and functional inspection information and records of sampling of the main functions, quality inspection records of the view (G Tables 1, 2, 3, 4), division (sub-division) project quality acceptance records, residential Project quality inspection records, summary tables, indoor net height and net opening dimensions of the sampling table

5, as-built drawings:

1

General layout (including buildings, architectural vignettes, water features, lighting, roads, landscaping, etc.)

2

Vertical layout

3

Outdoor water supply, drainage, heat, gas, electricity, etc. (including electricity, telecommunications, television systems, etc.) pipeline network comprehensive plan

4

Outdoor pipeline diagram (water supply, rainwater, sewage, heat, gas, telecommunications, electricity, television)

5

Outdoor environment plan (roads, landscaping, vignettes, water features, lighting, etc.)

6

Outdoor fire protection Diagrams

7

Structural as-built drawings

8

Architectural as-built drawings

9

Decoration and decoration (including curtain wall), energy-saving engineering as-built drawings

10

Electrical (including fire-fighting electricity), elevator, intelligent engineering as-built drawings

11

Water supply and drainage (including fire water) engineering as-built drawings

12

Heating, ventilation and air-conditioning engineering as-built drawings

13

Gas engineering as-built drawings

6, completion and acceptance of the documents:

1

Project profile, approval of the use of geographical names, the building number and the name of the building number of the cross-references

2

Built Unit project completion acceptance report, survey, design, construction, supervision unit quality inspection (assessment) report

3

Completion acceptance filing form

4

Government departments of the special acceptance of various acceptance documents (planning, fire, environmental protection, health, human defense, traffic police, greening, etc.) and fire, environmental protection, indoor environment testing reports, water, Lightning and other testing documents

7, financial documents:

1

final account documents

8, audio-visual, micro, electronic files:

1

project photographs

2

audio, videotapes

3

microfilm, CD-ROMs, disks

9, the completion of underground pipelines. >9, underground pipeline as-built measurement data:

1

Technical reports, results of the table and other textual materials

2

Specialized, comprehensive pipeline as-built drawings

3

Underground pipeline as-built measurement of CD-ROM

4

Other information

Two, the requirement:

1, archived information for the original.

2, the preliminary information will be filed after receiving the construction permit for the construction of the preliminary processing of information and lists.

3. Bidding documents will be filed with the bidding information and list after the bidding is completed.

4, construction documents (one original, one copy), as-built drawings (three sets of originals), supervision documents (one original, one copy) and completion and acceptance of the file within three months after the completion of the project.

5, the final account of the project documents filed within six months after the completion of the project.