1) The existing sub-projects were damaged to varying degrees, with a total loss of 200,000 yuan. The owner shall bear the economic responsibility for the repair, and the construction unit shall no longer bear it.
This demand project should be supported and belongs to the owner's responsibility. However, the losses caused by the improper protection of the built project according to the contract requirements shall be borne by the construction unit.
2) The mechanical equipment being used by the construction unit is damaged, resulting in a total loss of 65,438+10,000 yuan; The owner shall bear the economic responsibility of compensation and repair for the loss of 50,000 yuan caused by shutdown, and the worker's slowdown fee is 40,000 yuan, which shall be paid by the owner.
This claim engineer does not support it, because machinery is the equipment of the construction unit; The construction unit is responsible for the use and maintenance, and the resulting shutdown and expenses are also borne by the construction unit.
3) Some personnel of the construction unit were injured, and medical treatment and compensation totaled 50,000 yuan. In addition, the project also caused injuries to passers-by, with medical treatment and compensation totaling 30,000 yuan, and the owner should compensate them.
This idea cannot be supported either. It should be the responsibility of the construction unit itself. FIDIC stipulates that the personal insurance and medical treatment of construction personnel shall be the responsibility of the construction party. Its cost has been included in the project cost. The construction party should seek compensation from the insurance company for accidental losses or treat them as medical insurance or work-related injuries. The loss of the third party (passerby) should also be borne by the constructor, because it is caused by improper protective measures of the constructor.
4) The construction site was shut down for 7 days due to the wind disaster, and it is required to extend the contract period for 7 days.
This can be supported and belongs to the owner's responsibility.
5) Due to the damage of the project, the construction unit cleaned up the site according to the requirements of the owner, and the total cost was 30,000 yuan, which was paid by the owner.
This can also be supported, which is the responsibility of the owner.