Wastewater treatment plant project acceptance procedures should be divided in accordance with the following provisions:
1 unit project of the main parts of the project quality acceptance;
2 unit project quality acceptance;
3 equipment installation project stand-alone and linkage test run acceptance;
4 wastewater treatment plant project handover acceptance;
5 water commissioning test run;
6 Acceptance of the completion of the sewage treatment plant.