How much cooperation fee should the general contractor charge according to regulations?

Provisions on cooperation fees: Cooperation fees refer to the contractual relationship between the construction unit and the professional construction enterprise directly. The professional construction unit constructs within the construction organization design of the main contracting unit, and cooperates on site, cross construction, and causes labor , mechanical inefficiency, affecting construction progress and increasing on-site expenses.

Prerequisites for calculating cooperation fees:

1. The construction unit directly outsources the contract to the professional construction unit, and the two have a contractual relationship;

2. Professional construction The construction of the unit and the main construction unit are synchronized;

3. The relationship between the professional construction unit and the main contracting construction unit is not between general contracting and subcontracting;

1. The cost quota is based on the unit If the project is customized according to the comprehensive calculation of the project, the construction unit must contract out all the construction and installation work quantities of a unit project to a construction unit. If the construction unit contracts part of the project quantities (such as aluminum alloy doors and windows, aluminum alloy ceilings, aluminum alloy partitions, aluminum Alloy walls, aluminum alloy dado, etc.) shall charge all fees to be absorbed by the construction unit.

2. If the construction unit really has professional needs and the main contracting construction unit is incapable of construction, it must designate a professional construction unit to install, decorate and other parts of the project (such as elevator installation, central air conditioning installation, fire alarm system installation, glass curtains, etc.) are separately divided and contracted to various professional construction units for construction. The construction unit contracting the main project shall charge cooperation fees to the construction unit as the on-site expenses increased by the main contracting construction unit's on-site cooperation and cross-construction, resulting in reduced efficiency of manual machinery and affecting the construction progress.

The standard for calculating cooperation fees is 2% to 5% of the total price of the subcontracted project (excluding equipment fees). This range is determined by both parties based on in-depth cooperation.

The calculation basis for calculating the coordination fee is the value of the fixed base part, excluding the value difference from dynamic management or market factors. Cooperation fees are calculated separately and do not participate in fee collection, only taxes are calculated

3. Each professional construction unit shall construct within the construction organization design of the main contracting construction unit, and both parties shall cooperate and actively cooperate with each other to ensure Construction schedule and project quality. The main contract construction order must provide water, electricity, roads, vertical transportation machinery, scaffolding, etc. to cooperate with various professional construction units for construction.

The water, electricity, vertical transportation machinery shift fees, and periodic material (slats and poles) sales fees incurred between the main contracting construction unit and various professional construction units shall be settled according to the actual situation, and shall be settled by each professional construction unit Paid to the main contracting construction unit.