Construction method of secondary grouting material

Step 1: Basic treatment

The foundation surface should be chiseled. Clean the foundation surface, and there shall be no debris such as gravel, laitance, floating ash, oil stain and release agent. irrigate

24 hours before grouting, the foundation surface should be fully wet, and 65438 0 hours before grouting, the accumulated water should be removed.

touch

1, formwork support shall be carried out according to grouting construction drawing. Joints between formwork and foundation, formwork and formwork shall be sealed with cement slurry and adhesive tape to achieve integrity.

The degree of waterproof formwork.

2. The horizontal distance between the formwork and the equipment foundation should be controlled at around 100mm to facilitate grouting construction.

3. The elevation of the top of the formwork shall be 50 mm higher than the upper surface of the equipment base.

4. If slurry leakage is found during grouting, it shall be handled in time.

Step 3: Preparation of grouting materials.

1. Generally, the reinforced type is mixed with water according to the standard of 12- 14%, and the pisolite reinforced type is mixed with water according to the standard of 9- 10%.

2. It is recommended to use mechanical stirring, and the stirring time is generally 1-2 minutes (hand electric drill agitator is strictly prohibited). When manual stirring is used, 2/3 water should be added to stir for 2 minutes, and then the rest water should be added to stir evenly.

3. The amount of stirring each time depends on the dosage, so as to ensure that the materials are used up within 40 minutes.

4. It is forbidden to mix any admixture or foreign admixture into HGM grouting material when it is used on site.

Step 4: Grouting construction method

1, long equipment or track foundation shall be constructed in sections.

2. Secondary grouting shall meet the following requirements. (1), secondary grouting, grouting must be carried out from one side or two adjacent sides until it overflows from the other side, so as to facilitate air exhaust during grouting. Grouting shall not be carried out from all sides at the same time. (2) After grouting starts, it must be carried out continuously without interruption. And shorten the grouting time as much as possible. (3) Vibration is strictly prohibited during grouting. When necessary, the grouting booster can be used to push the HGM grouting material along the bottom of the grouting layer, and it is forbidden to push it from the middle and upper part of the grouting layer to ensure the uniformity of the grouting layer. (4) After the grouting of the equipment foundation, a 45-degree oblique angle (see the figure below) should be cut along the edge of the equipment 3-6 hours after grouting to prevent cracks at the free end. If the cutting edge is treated, the surface of the grouting layer should be polished with a spatula 3-6 hours after grouting. ⑤ When the thickness of grouting layer exceeds 150mm, high-strength non-shrinkage grouting material reinforced by pisolite should be adopted. ⑥ When the grouting quantity of equipment foundation is large, the mechanical mixing method should be adopted for the mixing of pisolite reinforced grouting materials to ensure the grouting construction.

Step 5: Cure 1. Immediately after grouting, cover it with wet grass cover or rock wool and keep it moist. 2, winter construction, maintenance measures should also comply with the current & gt(GB50204). 3. After the grouting material reaches the film uncovering time, the equipment can be installed. Please refer to the relationship table of demoulding, curing time and ambient temperature for specific time. 4. After the grouting of the equipment foundation is completed, if there is any part that needs to be removed, it can be removed gently with a spatula or shovel 3-6 hours after the grouting is completed, that is, before the grouting layer hardens. 5. The vibration of the running machine should not be transmitted to the equipment foundation, and it should be stopped for 24-36 hours after secondary grouting to avoid damaging the unhardened grouting layer.