What formalities are required to open a gas filling station in the suburbs of Chengdu County and how much capital is invested?

Requirements for filling station formalities

1.1 When the construction of a filling station is completed, the construction formalities that should be available are as follows:

1 Preliminary formalities:

Project feasibility study report (or project proposal),

Project approval (Planning Commission),

Approval of construction site,

State-owned land-use certificate (State-owned Land Resource Bureau),

Topographic survey map (with vectorized CD-ROM, surveying and mapping unit),

Planning red line (Planning Bureau),

Geological survey report (survey unit),

Construction design (design unit),

Planning permit (Planning Bureau),

Construction plan examination and approval letter (Municipal Construction Commission's examination and planning office),

Construction Permit (Municipal Construction Committee),

Fire Protection Design Review Opinion of Construction Project (Fire Protection Bureau),

Safety Evaluation Report Approval (Administration of Work Safety),

Environmental Evaluation Report Approval (Environmental Protection Bureau),

Pressure Piping Installation Safety and Quality Supervision and Inspection Declaration Form (Party A Declares Technical Supervision) unit)

Special equipment installation, transformation and maintenance notice (after the construction unit to declare the technical supervision unit, submit a copy to Party A to retain).

2 Post-construction formalities:

Fire Acceptance Opinion of Construction Project (Fire Protection Bureau),

Dangerous Chemicals Operation License (Administration of Work Safety)

Pressure Vessel Product Quality Supervision and Inspection Report (Autonomous Region Institute of Quality and Safety Inspection of Boiler and Pressure Vessel)

Business License (Industrial and Commercial Administration),

Enterprise Organization Code Certificate (autonomous regions of Quality and Technical Supervision)

Lightning and anti-static facilities inspection report (autonomous regions of Product Quality Supervision and Inspection Institute)

Pressure vessel license, cylinder filling license (autonomous regions of Quality and Technical Supervision)

Property license and so on.

1.2 Gas filling station preliminary procedures:

1 natural gas filling station construction must be in accordance with the relevant national construction regulations and procedures for construction approval. The preliminary procedures of the gas station is a prerequisite and necessary condition for the smooth implementation of the construction of the gas station, as well as the basis and guarantee for the later operation procedures of the gas station.

Construction Procedures of Filling Station

The compressed natural gas operated by the filling station is a kind of high-pressure gas, so the construction of the filling station is different from the general construction of ordinary buildings, and the construction process should be subject to strict scrutiny, and the construction should be completed after the initial inspection and examination, and then the acceptance by the governmental authorities and the relevant departments should be obtained and the certificates should be issued.

After the project is finalized, the CNG filling station construction procedures are:

I. Site selection

The company should be familiar with the policy and standard specifications for the construction of the station, in the urban area of the city or the main traffic arteries, according to the proximity of water, electricity, close to the source of the vehicle, refueling is convenient, and basically in line with the urban planning and standard specifications for fire, environmental protection and safety requirements, the initial selection of the station's address;

1. the Ministry of the Administration of automotive gas management department, the Construction Commission, planning, fire, environmental protection, design to the site of the fixed point;

< p>2. land acquisition procedures and land certificates in the land department;

3. planning land permit and construction permit in the planning department.

II. Establishment of the project

1. The Vehicle Gas Division submits an application for the construction of the station to the Construction Committee;

2. Provides the appropriate information: project report, feasibility study report, and report on the location of the site;

3. The Construction Committee approves the establishment of the project.

III. Design

1. Before the preliminary design, the Automotive Gas Division to provide information to the design institute: topographic maps of the station site, natural gas gas gas data, meteorological data, seismic data, water and electricity, gas source data, equipment selection, ground investigation data, environmental impact assessment report, safety impact assessment report and some other relevant information.

2. The design institute to do the preliminary design: general layout, monomer plan, monomer structure, equipment configuration, engineering water and electricity process preliminary design, architectural rendering, drawing instructions and additional instructions; whether the instructions comply with national norms and other norms; gas station fire, environmental protection, safety and other standards in line with the requirements.

3. Review of the preliminary design: the Department of Automotive Gas, Construction Commission, planning, fire, environmental protection, safety assessment, design institute to participate in the review of the preliminary design.

4. Automotive Gas Division, Construction Committee and relevant departments to issue comments.

5. Construction Drawing Design: The design institute will design the process design of the CNG filling station accordingly, and design the general drawing, building, structure, water and electricity, water supply and drainage, HVAC design, and issue the construction blueprints.

IV. Construction

1. Preliminary design for fire, environmental protection review, and issue approval, safety assessment for safety certificate;

2. Preliminary general layout plan (including fire, environmental protection, safety assessment approval) for planning review, survey and demarcation;

3. Planning for planning permit, construction commission for engineering construction permits;

5. Construction

1. for civil construction, installation, water and electricity supply, supervision of bidding, signing of contracts;

2. to the quality inspection department for the quality inspection commission;

3. to the Construction Committee for the contract visas;

4. organization of construction.

VI. Acceptance

1. to carry out quality inspection of the project and issue a quality inspection report;

2. to carry out single acceptance of fire, safety, environmental protection, pressure vessels, and issue a single acceptance report, hazardous chemical safety evaluation report, lightning and static electricity detection report, safety evaluation report in the safety assessment department for safety evaluation report, environmental evaluation and testing report;

3. to apply for the Quality Supervision Bureau of the pressure vessel Use permit, filling registration certificate;

4. QC department for inspection and calibration of gas dispenser, and issued measurement and use permit;

5. Employees to the relevant departments for technical training and learning, and obtain a certificate of attendance;

6. Trial operation, acceptance rectification and improvement;

7. Comprehensive acceptance of the vehicle before the gas division to prepare applications for Completion acceptance report, relevant approval documents, design data, construction data, completion data, quality inspection data, supervision data, material testing data, management system, accident handling emergency plan and other related information;

8. Vehicle gas division hosted by the Construction Committee, planning, fire, environmental protection, safety assessment, quality supervision, design institutes to participate in the completion of the acceptance;

9. Vehicle gas division to handle Gas business license, the Administration for Industry and Commerce for business license, gas management department for the relevant qualification certificate;

10. put into operation.

Section I Gas Station Project Construction Process

Any construction project should have its own project construction process, gas station is no exception, also has its own project construction process, the specific process is shown in the following table:

Gas Station Project Construction Process Flow Chart

Serial No. Project Process Responsible for the unit to obtain the approval of the document name Remarks (sent to the unit responsible for the paperwork < /p>

1 Construction of the gas station, the construction of the gas station, the gas station, the gas station, the gas station, the gas station, the gas station, the gas station, the gas station, the gas station and the gas station.

1 Construction Project Investment Review Investment or Construction Unit Construction Project Establishment Approval Project Application Approval (Feasibility Study)

2 Planning Opinion Municipal Planning Bureau Planning Opinion Notification Request for Investment Submission

3 EIA Impact Assessment Report Sheet EIA Qualification Unit Construction Project Environmental Impact Assessment Report Sheet Project Establishment Approval

4 Geotechnical Exploration Exploration Qualification Unit Geotechnical Exploration Report General Layout Plan

5 Actual Topographic Map Survey and Mapping Qualification Unit Actual Topographic Map (including CD-ROM) Investment Unit's Power of Attorney

6 Construction Drawing Design **Engineering Company Limited Full set of Construction Drawings

Geotechnical Exploration Report Actual Topographic Map Investment Unit's Power of Attorney

7 Pre-examination of Land Use for the Construction Project Land Use Pre-examination Opinion of the Land and Resources Bureau Application Report Construction Project Establishment Approval Feasibility Study Report Actual Topographic Map