An EIA report process (Maoming City, for example)
1, application
The applicant to the Municipal Administrative Service Center Environmental Protection Bureau window to apply for the submission of application materials
2, acceptance
receiving acceptance of the personnel to verify the application materials, and to make a decision on the spot acceptance. Applicant materials do not meet the requirements but can be corrected on the spot, returned to the spot after correction to be accepted.
3, review
After acceptance of the review of the material review staff, to make a review of the conclusions; decision makers in the completion of all the review process to make a decision on the review
4, get the results
Applicants according to the agreed way to the Municipal Administrative Service Center, Environmental Protection Bureau window to pick up the results of the self or by mail
Two, the approval of the contents of the
1. Whether it complies with laws and regulations related to environmental protection. If the project involves nature reserves, scenic spots, domestic drinking water source protection zones and other areas that need special protection according to the law, whether the consent of the people's government of the corresponding level or the competent department is obtained
2. Whether the project's site selection, routing, and layout are in line with the regional, watershed, and urban master plans, and whether it is in line with the environmental and ecological functional zoning
3. Whether it is in line with the national industrial policy And clean production requirements
4, the project is located in the area of environmental quality can meet the corresponding environmental functional zoning standards
5, the proposed pollution prevention and control measures can ensure that pollutant emissions meet national and local emission standards, to meet the total control requirements
6, the proposed ecological protection measures can effectively prevent and control ecological damage
Expanded Information:
Environmental Impact Report
1, the overall layout structure of the environmental impact report should be in line with the "Regulations on the Protection and Management of Construction Projects" (promulgated on November 29, 1998), that is, the requirements of the "Executive Summary of the Environmental Impact Report on Construction Projects". Comprehensive, focused and practical
2, reliable basic data
Basic data is the basis of evaluation, basic data must be reliable, different data on the same parameters should be verified when the data appear different.
3, the prediction model and parameter selection is reasonable
Environmental impact assessment prediction model have certain conditions of applicability, choose the model of the derivation (summarization) conditions and evaluation of the environmental conditions are similar (the same) model. Selection of summarized parameters when the environmental conditions and evaluation of environmental conditions similar (the same) parameters.
4, the conclusion of a clear point of view, objective and credible
Conclusion must be the feasibility of the construction project, the reasonableness of the site to make a clear answer, can not be ambiguous, the conclusion must be based on the report of the objective argumentation, can not be emotionally charged
5, the language is fluent, clear and concise text, the length of the report should not be too long, all with a comprehensive, concluding Charts should be put in the body of the report, the charts of reference value should be put in the report, in order to reduce the length
6, environmental impact report should be evaluated in the certificate of qualification, the report of the signature, the report compiler according to the chief administrative officer, the chief technical officer, the technical reviewer, the chief project manager
Maoming Municipal People's Government - Construction Project Environmental Impact Assessment Document Approval
Baidu Encyclopedia - EIA Approval
Baidu Encyclopedia - EIA Report