How to put molybdenum wire on wire cutting

Installation steps for WEDM molybdenum wire:

The operator stands behind the wire cylinder. Adjust the left and right bumpers to be placed at the maximum position of the stroke respectively before the machine is turned on. Screw the molybdenum wire disk onto the upper wire wheel with the end of the molybdenum wire secured to the screw on the wire cylinder.

After tightening, manually rotate the silk cylinder counterclockwise, so that the molybdenum wire winding 4 to 5 turns. Then turn on the silk cylinder operation switch, silk cylinder rotation, silk cylinder slider whole part to the left, the molybdenum wire evenly wound on the silk cylinder, according to the required number of installed wire, stop the rotation of the silk cylinder.

After wrapping on the silk cylinder, the other end of the molybdenum wire will be wrapped from the lower wire discharge wheel - conductive block - lower guide wheel - upper guide wheel - jewel stopper - conductive block (2pcs) - upper wire discharge wheel -Broken wire protection -Wire reel. After mounting, manually rotate the reel clockwise so that the molybdenum wire rotates and winds 4 to 5 times.

Press the right bumping block onto the proximity sensor, then press the silk cylinder running switch to move the silk cylinder to the left, and when it is close to the end of the silk cylinder, turn off the silk cylinder running switch to stop the rotation of the silk cylinder, and then press the left limit bumping block onto the left proximity sensor.

Take out the tightening wheel from the toolbox, pull the molybdenum wire on the silk cylinder, turn on the running switch, and the silk cylinder slider moves to the right as a whole. Tighten the silk process, the hand appropriate use of uniform strength tension, eliminate loose gap. When approaching the end of the silk cylinder, turn off the silk cylinder running switch, re-fix the molybdenum wire.