Where is the site of Huaneng Yingcheng Cogeneration Plant?

Huaneng Yingcheng Cogeneration (Phase I) Desulfurization Project

Location: Yingcheng City, Hubei Province

Project nature: New construction

Total investment: 10,000,000 Yuan

Construction period: 2010-2011

Supervisory unit: Central China Branch of China Huaneng Corporation

Major equipments : Desulfurization equipment, dust removal equipment, mist eliminator, equipment for desulfurization sludge dewatering system, equipment for desulfurization wastewater treatment system, absorption tower, agitator.

Main products: Flue gas desulphurization of a 350,000 kW supercritical coal-fired unit.

Project Introduction

The project is located in Yingcheng City, Hubei Province, and is a supporting facility for Huaneng Yingcheng Cogeneration Project, which provides flue gas desulphurization treatment for a 350,000-kilowatt supercritical coal-fired unit.

The total investment of the project is 100 million yuan.