Tower crane emergency plan

Tower Crane Emergency Plan

Tower Crane Emergency Plan

I. Policy and Principles of Emergency Plan

Better adapt to the requirements of the law and economic activities; provide a better and safer environment for the work of the enterprise's employees and the surrounding residents of the construction site; ensure that all kinds of emergency resources are in a good state of readiness; and guide the emergency operations in an orderly manner according to the plan; Prevent the emergency rescue from being delayed due to poor organization of the emergency action or the disorder and confusion of the rescue work on site; effectively avoid or reduce casualties and property losses; help to achieve rapid, orderly and efficient emergency response; fully embodies the "emergency spirit" of emergency rescue. Adhere to the policy of "safety first, prevention first", "prioritize the protection of personnel safety, environmental protection", and implement the principle of "constant preparedness, unified command, efficient coordination, and continuous improvement". The principle.

Two, emergency planning

(a) Project Overview

This project is located in Shenzhen City, Liantang, the west side of the first road, the terrain is low in the north and south of the state of high, the plot of land on the south side of the east and west side of the city has been built in the residential area, the north can be seen in the mountain scenery. No.1 Road extends to Xianhu Botanical Garden. The project includes B1, B2 two tower residential buildings and semi-open underground parking garage. The project ±0.00 corresponds to the absolute elevation of the Yellow Sea Elevation 43.0 m; the building area is 6500 m2 The structure type is frame structure, and the seismic intensity is 6 degrees. It consists of two twelve-story residential buildings, with the garage on the first underground floor and one~twelve-story residential buildings.

(II), emergency plan workflow

According to the characteristics of the project and the actual situation of the construction process, carefully organized the identification and evaluation of hazardous sources and environmental factors, specially formulated for this project in the event of an emergency or an accident emergency measures, to carry out education on emergency response knowledge and emergency response drills, to improve the emergency response capability of the site operators, to reduce the damage caused by the emergencies and adverse environmental impact.

(3) major accidents (hazards) development process and analysis tower crane operation suddenly safety limit device out of control, impact on guardrail and adjacent tower crane or falling objects, or violation of safety regulations for operation, resulting in major accidents (such as tipping, broken arm); operation of electrical equipment failure or serious leakage of the line; other operations may occur in the event of major accidents (fall from height, lifting injuries, electrocution, etc.) The resulting casualties, property damage, and environmental damage.

(D) risk analysis and prevention of emergencies

In order to ensure normal construction, prevention of tower cranes in the use of the process of emergencies as well as some unforeseen, irresistible events, beforehand, there are sufficient technical measures to prepare, the reserve of emergency supplies, to minimize injuries and deaths, national property and economic losses, must be carried out to analyze the risk and take effective Preventive measures.

1, contingencies, emergencies and risk analysis

According to the characteristics of the project, in the identification, analysis and evaluation of the tower crane in the use of risk factors and risk based on the tower crane in the use of the process of determining the major risk factors are tower crane operation in a sudden loss of control of the safety limiting device, the occurrence of the impact of the guardrail and the neighboring cranes or falling objects, or violation of the safety regulations operation, resulting in major accidents (eg. Failure of electrical equipment or serious leakage of electricity in the line during operation. In the site has been taken on the basis of mechanical and electrical management, safety management of a variety of precautions, but also need to develop the tower crane tipping emergency program, as follows: assuming that the tower crane foundation collapse may be tipping; assuming that the tower crane torque limit failure, the crane driver violates the rules of operation of the crane is seriously overloaded lifting, may cause the tower crane tipping.

2, contingencies and risk prevention measures

From the analysis of the above risk situation, if the corresponding effective preventive measures are not taken, not only to the construction of the project has a great impact, but also a threat to the safety of construction workers.

f tower crane operation and use should be in accordance with the following provisions:

① tower crane before the operation, should check the metal structure, connecting bolts and wire rope wear and tear; before power supply, the controller handle should be in the zero position, no-load operation, test the institutions and safety devices and confirm normal.

② tower crane operation is strictly prohibited overloading, diagonal pull and lifting buried in the ground and other unknown weight objects;

③ lifting bulk objects, should be made of special cages or containers, and should be guaranteed that the material will not fall off in the process of lifting. The cage or container should be tested according to twice the load of the permissible carrying capacity before use, and should be inspected regularly during use;

④When lifting long materials such as multiple steel pipes and reinforcement bars, it is necessary to make sure that the slings are securely tied to prevent the slings from slipping and the materials from falling out during the lifting process;

5The distance between any part of the tower crane (including the lifting objects) should not be less than 2m between two or more tower cranes. When the requirements can not be met, measures should be taken to adjust the working height of adjacent tower cranes, add travel limit, slewing limit device, and other measures, and formulate the operating procedures for cross operation;

⑥ cables hanging vertically along the tower should be suspended using a reliable device that is not stretched and abraded by the weight of the cables;

1) the completion of the operation, the lifting arm should be turned to the downwind direction, and should be released to swing Brake, lifting trolley and counterweight should be placed in a non-working state.

g In order to prevent accidents, the tower crane must be installed and dismantled by qualified professional team, the tower crane driver must be licensed, after installation by the Technical Supervision Bureau of Special Equipment Safety Inspection Center or the Construction Management Bureau of the Safety Supervision Station acceptance before being put into use.

h tower crane driver operation, must be strictly in accordance with the operating procedures, are not allowed to work against the rules, the strict implementation of the "ten do not hang", before the operation must have a safety and technical briefing records, and fulfill the signature in the sequel.

(5), laws and regulations

"Construction tower crane safety operation technical regulations", "on the provisions of the administrative responsibility for large-scale safety accidents," Article 7, Article 31; "production safety law" Article 30, Article 68; "construction safety regulations", "safety license regulations".

Two, emergency preparedness

1, institutions and responsibilities

Once a tower crane use in the process of safety accidents, the project leader and the person in charge of the relevant departments must immediately rushed to the scene, organization and command of the emergency response, the establishment of on-site emergency response leadership group.

Project emergency leadership group and its composition

Group leader:

Deputy leader:

Subordinate:

Communication and liaison group leader:

Technical support group leader:

Rescue and repair group leader:

Medical rescue group leader:

Logistics group leader:

Logistics group leader:

Responsibilities and division of labor of the emergency organization

Responsibilities of the team leader:

1) Decide whether there is or may be a major emergency, request help from emergency services and implement off-site contingency plans, and carry out direct control in places unaffected by the accident;

2) Review and assess the direction in which the accident (incident) may develop, and determine the likely course of its development process;

3) directing the partial shutdown of the facility and, in conjunction with key members of the Leadership Team, directing the evacuation of personnel from the site and ensuring that adequate attention is given to any injuries;

4) contacting off-site emergency response agencies and arranging for the handling of emergencies;

5) exercising traffic control within the site (facility) and assisting off-site emergency response agencies to carry out service work;

6) control the recovery of the affected site after the end of the emergency and organize the participation of personnel in the analysis and treatment of the accident.

Duties of the Deputy Team Leader (i.e., Site Manager):

1) Assessing the magnitude and development of the incident and establishing emergency response steps to ensure the safety of employees and minimize damage to facilities and property;

2) If necessary, participating directly in ambulance activities prior to the arrival of rescue services;

3) Arranging for the search of injured persons and the evacuation of non-essential personnel to a concentrated

4) Establish communication with the Emergency Response Center to provide advice and information to the emergency services.

Responsibilities of the Communication and Liaison Team:

1) Ensure smooth communication with the top management and the outside world, and rapid feedback of internal and external information;

2) Maintain the communication facilities and equipments in good condition.

3)Responsible for the records and organization of the emergency response process and external liaison.

Technical Support Group Responsibilities:

1) Propose rescue and repair and avoid the expansion of the accident temporary emergency programs and measures.

2) Guiding the rescue and repair team to implement emergency programs and measures.

3) Fix the defects of the emergency program and measures in the implementation.

4) Drawing the plan of the accident site, marking the key areas, and providing accurate emergency rescue information to external rescue organizations.

Duties of the defense team:

1)Protect the property of the victims.

2) Setting up accident site cordons and posts to maintain the normal operation of rescue and relief within the site.

3)Maintaining the smoothness of the rescue and relief channels, and guiding the entry of rescue and relief personnel and vehicles. 4)After the rescue and relief, closing the accident site until receiving a clear lifting instruction.

Response of the rescue and repair team:

1) Implementation of rescue and repair of emergency programs and measures, and constantly improve.

2) Finding victims and moving them to safety.

3) Take great care to avoid accidental injuries when carrying out emergency repairs or rescuing when the accident is likely to expand.

4)Report directly to the highest level of management and review and evaluate the results after the emergency repair or rescue is completed.

Medical treatment team:

1)Before the arrival of external rescue agencies, the necessary rescue of the victim (such as artificial respiration, bandage to stop bleeding, prevent contamination of the injured area, etc.).

2) Prioritize severe victims to external rescue agencies.

3)Assist external rescue agencies in transferring victims to medical facilities and designate personnel to care for victims.

Duties of the Logistics Support Group:

1)To guarantee the supply of protective and rescue supplies and living materials necessary for the personnel of each group in the system.

2)Provide qualified substances and equipment for emergency repair or rescue.

2, emergency resources

Emergency resources preparation is an important guarantee of emergency rescue work, the project department should be based on the nature of potential accidents and the consequences of the analysis, equipped with fire fighting means, rescue machinery and equipment, transportation, medical equipment and medicines, and life support materials needed in emergency rescue.

Emergency supplies are mainly:

1, oxygen cylinders, acetylene bottles, a set of gas cutting equipment

2, 1 first aid kit;

3, 3 flashlights (tower crane, electrician, manager of each 1);

4, 6 walkie-talkies.

3, education, training

In order to comprehensively improve the emergency response capability, the project department should rescue personnel to carry out the necessary rescue knowledge education, to develop the appropriate provisions, including emergency content, planning, organization and preparation, evaluation of the effect.

4, mutual agreement

The project department should establish a formal mutual agreement with local hospitals and hotels beforehand, so as to get the assistance of external rescue forces and resources in time after the accident.

Three, emergency response

Construction process of the construction site or resident in the occurrence of unforeseen dangers that require emergency rescue treatment, should be quickly reported level by level, in the order of the site, the office, the leading group of rescue, the higher authorities. The safety and quality department of the project department collects, records and organizes the emergency information and transmits it to the group in time, and the leader or deputy leader of the group presides over the meeting of emergency treatment, coordinates, dispatches and unifies the command of all the vehicles, equipments, personnel, materials, etc. to carry out the emergency rescue and report to the higher authorities. Accident handling according to the size of the accident to determine the situation, if the accident is particularly small, according to the instructions of the higher level can be directly by the construction unit to deal with their own. If the accident is large or the construction unit can not deal with the construction unit to the construction unit to the competent departments for instructions, requesting the start of the construction unit's rescue plan, the construction unit's rescue plan can not be dealt with, then the construction unit's safety management to the Construction Authority Safety Supervisory Bureau or the government department to request the start of the upper level of the rescue plan.

(1) duty phone: the project department to implement day and night duty system, the project department duty time is as follows:

7:30 ~ 20:30; 20:30 ~ 7:30

(2) emergency occurs, the scene should be a good alert and evacuation, protect the scene, rescue the injured and property in a timely manner, and by the highest level at the scene of the project department in charge of command. Within three minutes of the telephone notification to the duty officer, mainly explaining the nature of the emergency, location, time of occurrence, casualties, whether the need to send an ambulance, fire engines or police support to the scene to implement rescue, such as the need to call 120, 110 and other direct calls for help.

(3) The duty officer must report the situation to the leader and deputy leader of the emergency leadership team within 2 minutes after receiving the emergency report. The team leader to organize a discussion in the shortest possible time after the issuance of instructions on how to carry out on-site treatment. Assign personnel and vehicles to the scene to rescue, guard, evacuate and protect the scene. By the project department safety and quality department in the name of the team within 30 minutes to call the upper level of the relevant departments to report.

(4) in the event of an emergency, all employees should be special, urgent, active and positive to the emergency treatment. All kinds of equipment, vehicles, equipment, materials, etc. should be unified deployment, all kinds of personnel must resolutely and unconditionally obey the group leader or deputy leader of the orders and arrangements, shall not be delayed, shirking, hindering the handling of emergencies.

Four, tower crane tipping contingency plan

1, alarm and notification: in case of accidental tower crane tipping, the project management personnel at the scene should immediately use the walkie-talkie to the project manager Bi Chunjie report the danger.

Bi Chunjie immediately summoned the construction team leader Lu Wenchong, labor captain Cai Jianshi, rescue command group other members, rescue, rescue, protection group members carrying their own rescue tools, rushed to the scene of the accident.

2, command and control:

3, rescue group arrived at the scene of the accident, under the command of Lu Wenchong divided into work.

① First rescue group and the manager to identify the danger: to determine whether there is still a source of danger. Such as touching off the high and low voltage wires are electrified; tower crane components, whether other components continue to collapse danger; casualties; agreed rescue program, project manager Wang Dezhong to the company leadership report approved.

② protection group is responsible for the accident site near the operating personnel evacuated to a safe area, and guard against idlers close to the external attention to polite language.

③ site duty electrician is responsible for cutting off the power supply of the dangerous low-voltage electrical lines. If at night, connect to the lighting;

③ rescue group in the exclusion of the continued collapse or electrocution risk, immediately rescue the injured: contact the ambulance, the side of the timely bleeding and bandaging, with a stretcher will be carried to the car to the injured to the hospital.

④ Tipping deformation of the tower crane disassembly, repair work should be asked to tower crane manufacturers to come under the guidance of people.

⑤ tower crane accident emergency rescue is completed, the project manager Wang Dezhong immediately called Peng Guizian, Yang Zeping, Wang Xiaobo and tower crane driver group of all comrades to investigate the accident, to find out the cause of the accident, the person responsible for as well as the development of corrective measures to prevent the recurrence of similar.

6 Review and revise the effectiveness of the emergency plan.

4, communication

The project department must be 110, 120, the project department emergency leadership group members of the cell phone number, the enterprise emergency leadership organization members of the cell phone number, the local safety supervision department telephone number, express in the site in a prominent position. Site rescue command and safety personnel should be familiar with these numbers.

5, alert and security

Safety and security team in the accident site around the establishment of the alert area to implement traffic control, maintenance of law and order on site.

6, crowd evacuation and resettlement

Evacue the work of the people should be orderly and obedient to the commanding officer's guidance requirements for evacuation, so as not to panic, do not confuse, crowded, to reduce casualties.

7, public **** relationship

Project Department of Safety and Quality Department for the accident information collection and dissemination of the organization, including: Safety and Quality Department will then play the role of the media of the project department, the handling of accidents, control, progress, escalation of the situation of information collection, and the severity of the accident situation to delete, targeted regular and irregular to the outside world and the internal truthful report to the internal report. The internal report is mainly to the project department internal work area, group company report, etc. The external report is mainly to the owner, supervision, design and other units of the report.

V. Site restoration

Fully identify the dangers that exist in the restoration process, when the safety hazards are completely removed, before resuming normal working conditions.

Sixth, plan management and review and improvement

The company and the project department of the emergency plan at least once a year for review, for the construction of the changes and the flaws exposed in the plan, constantly updated and improved and improved emergency plan.

The company and the project department will review the emergency plan at least once a year.