Tendering flow chart

Tendering agent (signing agency agreement) Bidder

Publishing pre-qualification notice/tender notice

Pre-qualification

↓↓

Determine the list of bidders ----------------------- Confirmation of bidding Intention

Preparation of tender documents

*Submission for approval

↓ ↓

Offering of tender documents ----------------------- Purchase of tender documents

Study of tender documents

↓ ↓

Organization of site visits ( If necessary) ----------------------- Participate in the site visit

↓ ↓

Questioning questions

Pre-bid Q&A ↓

Participate in the pre-bid meeting

↓ ↓

Send Q&A documents ----------------------- Determine the tender Strategy

↓ ↓

Random selection to determine the evaluation of experts ----------------------- Preparation of tender documents

↓ ↓

Acceptance of tenders (including qualification documents) ----------------------- Submission of tender documents

↓ ↓

Public opening of bids ----------------------- Participation in the bid opening meeting

Review of bids

↓ ↓

Clarification of questions ----------------------- Answers to questions

Evaluation of bids comparisons

Bid evaluation report

Finalizing bids

↓ ↓

Issuing notice of award ------------------------ Preparing a performance bond

↓ ↓

Negotiating a contract ------------------------ Negotiating a contract

↓ ↓

Notify unsuccessful bidders Report bidding summary information