Overview of Guangzhou LiKeng Waste Incineration Plant

Enterprise name: Guangzhou LiKeng Domestic Waste Incineration Power Plant

Enterprise nature: Municipal environmental protection project

Construction unit: Guangzhou Municipal Bureau of Municipal Facilities and Environmental Hygiene

Plant site: Yongxing Village, Taihe Town, Baiyun District, Guangzhou City

Preoccupied area: 101778 square meters

Building area: 23997 square meters

Greening rate of the plant: 53%

Daily processing capacity (into the furnace): 1,040 tons/day

Annual processing capacity (into the furnace): 346,660 tons/year

Boiler evaporation capacity: 48 tons/hour

Steam parameter: 6.5MPa, 450℃

Installed capacity of generating set: 22 MW ( 22,000 kilowatts)

Power generation efficiency (thermal efficiency of the whole plant): 24%

Annual power generation: 158 million kWh/year

Annual power consumption of the plant: 32 million kWh/year

Annual feed-in tariffs: 126 million kWh/year

Quantity of the production line: two sets of incinerators and waste heat boilers, and one set of turbine-generator set, which is the so-called "two furnaces and one machine"

Service life: 30 years