Enterprise name: Guangzhou LiKeng Domestic Waste Incineration Power Plant
Enterprise nature: Municipal environmental protection project
Construction unit: Guangzhou Municipal Bureau of Municipal Facilities and Environmental Hygiene
Plant site: Yongxing Village, Taihe Town, Baiyun District, Guangzhou City
Preoccupied area: 101778 square meters
Building area: 23997 square meters
Greening rate of the plant: 53%
Daily processing capacity (into the furnace): 1,040 tons/day
Annual processing capacity (into the furnace): 346,660 tons/year
Boiler evaporation capacity: 48 tons/hour
Steam parameter: 6.5MPa, 450℃
Installed capacity of generating set: 22 MW ( 22,000 kilowatts)
Power generation efficiency (thermal efficiency of the whole plant): 24%
Annual power generation: 158 million kWh/year
Annual power consumption of the plant: 32 million kWh/year
Annual feed-in tariffs: 126 million kWh/year
Quantity of the production line: two sets of incinerators and waste heat boilers, and one set of turbine-generator set, which is the so-called "two furnaces and one machine"
Service life: 30 years