Completion Acceptance Report Sample
A completion report
(a) Overview
Project name, project location, construction basis, construction scale, standards and main content, participating units, the main project and the construction process of the important construction facilities.
(B) project construction management
1. Project unit organization and work. Project management system of the project unit, the higher authorities, quality supervision agencies and local governments and other institutions serving the construction of the project set up and work briefly.
2. Bidding management: survey, design, supervision, construction, materials and equipment bidding, the qualifications of the winning unit, the main tasks undertaken.
3. Design change management: the implementation of major technical issues, the handling of design changes.
4. Safety and quality management: safety and quality management system, safety and quality control measures, accident results, civilized construction.
5. Investment management: investment sources, investment control measures, approved budget estimates and the actual implementation of the situation, the annual plan and completion of the situation, budget adjustments.
6. Progress management: the main project node plan control objectives and actual implementation, progress control measures.
7. Contract management: the performance of the contracting unit, the contract price settlement method and the handling of special issues, to the completion of the project there is no arrears in payment, etc.
8.
8. Compensation for land acquisition and resettlement: whether land acquisition and resettlement can meet the requirements of the construction progress, whether there is any violation of the policy, the approved land acquisition and the actual land acquisition, land acquisition procedures, land acquisition and resettlement costs of the use of land, etc.
9.
9. Innovative achievements: technical innovation (new structure, new materials, new technology, new equipment, etc.), management innovation and other achievements in the process of project construction.
10. Integrity construction: integrity measures and the implementation of integrity contracts.
11. Other: information management and other situations that need to be explained.
(C) successive acceptance
Successive delivery and acceptance, stage acceptance, special acceptance and other conclusions and acceptance of the remaining issues to deal with the situation.
(D) the final accounts of the completion of the audit
The final accounts of the completion of the audit and audit conclusions.
(E) engineering trial operation
Engineering observation and analysis results, engineering trial use and benefit performance.
(F) Project construction management experience and recommendations
Combined with the characteristics of the project and the management process, summarize the lessons learned from project management, experience revelation, the future construction, maintenance and operation of the management of the proposal.
Second, the design work report
(a) Overview
Briefly describe the scope of the design, the main content and features, and contract performance.
(b) design quality management
Mainly reflect the project design management organization and the main technical staff; quality management system; design management measures (including the use of mandatory provisions of engineering and construction standards, design quality, schedule assurance measures, etc.).
(C) design changes
Reflects the main design changes in the project, the reasons, content, the amount of work, investment, the impact of the schedule.
(D) design services
Briefly describe the design briefings, on-site services and other aspects.
(v) Design evaluation, experience and recommendations
Evaluation of the effect of engineering design, innovative effects, experience and recommendations.
Third, construction work report
(a) Overview
Briefly describe the scope of construction, content and contract fulfillment, etc..
(ii) Project management
Project management organization set up and the main technical personnel, equipment, safety, quality management system, construction management measures (including construction period, construction period navigation, environmental protection, fire and other measures to ensure).
(C) construction
construction organization (including construction preparation, input equipment and personnel, the total progress and phased construction schedule, etc.), the main unit construction measures, the completion of the main works, the project progress control, the project ahead of or delay in the completion of the reasons for the handling of major technical issues.
(D) construction process
Zhongguo recommended lawyers:
Xie Xu Zhejiang Hangzhou 13116752875 now serves as a number of real estate companies, real estate agents, property companies, construction companies, and special legal adviser. He specializes in corporate, real estate, finance and securities, intellectual property and other legal services.
Xu Weihua Shanghai 13671800608 "engaged in trial work for sixteen years, many years in charge of the trial committee affairs, for thousands of civil and criminal cases, has accumulated a wealth of judicial experience, writing a certain amount of jurisprudence, there are two in the Provincial High Court won awards in the "China Civil and Commercial Law Network" published a paper with a high level of theoretical expertise in jurisprudence; on the Contract Law, Guarantee Law, the Company Law, the Law of the People's Republic of China, the Law of the People's Republic of China and the Law of the People's Republic of China. The Law of Contract, Guarantee Law, Company Law and Property Law have certain research, writing and publishing papers. On the real estate business, corporate law, criminal defense has a certain specialization, successful representation of dozens of litigation and non-litigation cases, litigation cases all win rate of more than 90%, for a number of joint-stock companies and limited liability companies to provide quality legal services, achieved good results, and get the customer affirmation.
Completion Acceptance Report Sample
Name of Unit Project:
Name of Construction Unit:
Completion Acceptance Time: Month of Year
Completion Acceptance Report of Construction Project
Name of Unit Project
Improvement of Facilities Along the Longjiang River of Hechi City -- One Bridge To Six Bridges Lighting Improvement Project
Construction area
Total length in meters
Structure type and number of floors
Name of survey unit
Name of design unit
Guangxi Hualan Design (Group) Co.
Name of construction unit
Name of supervising unit
Hechi City Jianyu Engineering Construction Supervision Co.
Commencement of construction
January
Completion date
January
Construction cost
Yuan
Completion acceptance procedures:
1, the construction unit to preside over the acceptance meeting.
2, construction, design, construction, supervision units to introduce the performance of the project contract and the implementation of laws, regulations and mandatory standards for engineering construction in all aspects of construction. Invite the Urban Council, Street Lighting Department and other units to participate
3, review the construction, survey, design, construction, supervision units of engineering information.
4, acceptance of the group field check the quality of the project.
5, professional acceptance group comments, acceptance group to form the project completion acceptance opinion and sign.
I organized the organization on the date of the survey, design, supervision, construction, and other relevant persons in charge of the acceptance group, the construction contract for the construction of the project for the completion of the acceptance of the project.
Completion acceptance content:
1, by the completion of the acceptance team leader presided over the completion of the acceptance.
2, construction, construction, supervision, design, survey units were reported on the project construction quality status, contract performance and implementation of national laws, regulations and mandatory standards for engineering construction.
3, the acceptance group is divided into three parts of the inspection and acceptance.
(1) Check the quality of the project entity.
(2) Check the completion information provided by all parties involved in the construction of the project.
(3) Summarize and discuss the completion of the acceptance, and listen to the quality supervision agency on the quality supervision of the project.
(4) Formation of completion acceptance opinions, fill out the "construction project completion acceptance record form" and "construction project completion acceptance report", acceptance of the team personnel were signed, construction unit seal.
Completion acceptance organization:
(a) the establishment of the construction unit project leader Tang Bin for the leader, presided over the acceptance meeting; the project leader of the participating units and experts involved in the acceptance of the acceptance group, in accordance with the acceptance procedures for acceptance.
(b) the construction unit to introduce the construction;
(c) supervision unit to introduce the supervision;
(d) the acceptance of the professional group to verify the quality assurance information, and check the site;
(e) the acceptance of the professional group to summarize the statement, the construction unit to make a good record of the
Completion of the acceptance criteria:
completion acceptance standards:
completion of acceptance standards for the national and Guangxi Province mandatory standards, the current acceptance criteria for the national and Guangxi Province mandatory standards, the current acceptance standards, the current acceptance criteria for the national and Guangxi Province mandatory standards, the current acceptance criteria for the construction unit and Guangxi Province mandatory standards. And Guangxi Province, the mandatory standards, the current quality inspection and evaluation standards, construction acceptance norms, the design documents reviewed and approved by the relevant laws, regulations, rules and normative documents.
Evaluation of the survey unit:
Participate in the foundation groove inspection; participate in the foundation and related important parts of the project quality acceptance; participate in the project completion acceptance; participate in the project quality problems; issued engineering survey quality inspection report;
Evaluation of the design unit:
Participate in the foundation, the main body structure and related important parts of the project quality acceptance;
Participate in the project quality acceptance;
Participate in the project quality acceptance;
Participate in the project quality acceptance;
Participate in the project quality inspection and acceptance of the main body structure and related important parts of the project.
Participate in the acceptance of the completion of the project;
Issue design modification changes, technical negotiation notice;
Participate in the handling of quality issues related to the project;
Issuance of quality inspection report on the design of the project;
Evaluation of the construction unit:
Qualification of the management personnel of the project management department, equipped with and in place, the main professional types of operations, qualifications, equipped with and in place. The qualification of project manager department management personnel, equipped and in place, the main professional trades operation qualification, equipped and in place in line with the requirements;
Subcontracting unit qualification in line with the requirements, and management of subcontracting units;
Construction organization design or construction program has been approved and implemented;
Construction site configuration of the construction operation of the technical procedures and the relevant national norms, standards;
According to the technical standards of the engineering and design of the construction drawings reviewed and approved document Implementation;
Processes, parts, unit project quality inspection and evaluation meets the requirements;
Timely rectification of quality problems and quality accidents;
Collected and organized a complete set of quality assurance information;
Evaluation of the supervision unit:
The qualifications of the personnel of the project supervision organization, equipped and in place to meet the requirements;
Supervision planning, supervision, supervision and management of the construction of the construction site and the construction of the project. Supervision planning, supervision and implementation details are prepared and approved according to regulations;
Review of materials, components, equipment before putting into use or installation;
Verification of the qualification of subcontracting units;
Implementation of the witness sampling system;
Implementation of the focus on the key parts, key processes of the implementation of the side supervision;
Issuance of the quality of the problem notification form and review of the results of the rectification of the problem;
Issuance of the quality of the problem notification form and review the quality of the problem rectification results;
Implementation of the quality of the project management system;
Implementation of the project management system;
Implementation of the quality of the project management system. Construction permit procedures;
Commissioned according to the provisions of the project supervision;
Organization of drawing review, design briefings, design changes;
Organization of the project quality acceptance;
Timely completion of the project acceptance of the record formalities;
Acceptance of the completion of the project: quality level: qualified
1. Completed the design and the contract content, Quality acceptance meets the requirements, agreed to acceptance.
2, according to the survey report for design, construction.
3, according to the requirements of the design documents to complete the construction, construction quality in line with the design requirements.
4, the quality of the project is in line with the mandatory standards for engineering construction, in line with the design and contract requirements. Self-assessment to achieve excellent grade.
5, the quality of the project meets the requirements of the design documents and mandatory standards for engineering construction, and reaches the excellent grade.
6, the project file information is basically complete.
Project completion acceptance conclusion:
The project has been constructed according to the design drawings and the scope of the construction contract, the quality of the project is in line with the requirements of the contract and the requirements of the design drawings and the relevant quality acceptance standards of the project, and the functions to meet the use of requirements. The acceptance group unanimously agreed that this project is rated as qualified. Agree to use.
Construction unit (official seal)
Project Manager:
Unit Manager:
Monthly
201X Equipment Acceptance Report Template
Xxxxxx unit xx October
I. Appearance Inspection
1. Equipment and external packaging to take photos and records, check whether the external packaging of the equipment is intact, there is no damage, soaking, moisture, deformation, etc., the surface of the outer box and the state of encapsulation to check;
2. Check the surface of the equipment and accessories there is no mutilation, corrosion, bruises, etc., focusing on the inspection of the rotor impeller there is no damage, the main components and the main working surfaces;
3. If found Packaging is damaged, equipment and accessories have damage, corrosion, signs of use, etc., should be recorded in detail, and focus on photographs and documents, and timely return to the supplier for replacement, claims procedures.
Second, the number of inspections
1. Quantity inspection should be based on the supply contract and packing list, check the host, accessories and other equipment specifications, models, configurations and quantities, and piece by piece inventory check;
2. Carefully check the completeness of the randomized data, such as instruction manuals, certificates of conformity of the product inspection, warranty, etc.;
3. Serial number and factory number, if necessary, you can check online;
4. Carefully make a good record of unpacking and counting, write down the location, time, participants, box number, product name, should be to the actual number of real, such as found in shortages, misdirection and other issues, we must promptly make a good record and retain the relevant materials.
Third, fill in the acceptance record sheet
1. Box acceptance is completed, found that any one does not meet the requirements of the contract documents, must be recognized by the supplier's representative (signature, seal).
2. Write a record sheet of equipment unboxing inspection, serial number and factory number, field photos as part of the equipment acceptance documents.
Equipment unpacking acceptance record sheet