Cost engineer "installation engineering measurement" high-frequency test point practice

Introduction of installation engineering measurement is a chapter in the "installation engineering", and "installation engineering" is one of the subjects of the cost engineer examination, which belongs to the "construction engineering technology and measurement" of the sub-specialty, but also to apply for the first level of cost engineers and second level of cost engineers need to be examined in the subject, of course, this subject involves a lot of points of view, which includes the installation of construction technology, the measurement of the installation project, the installation of engineering materials, etc. No matter which one of the knowledge points need us to study after the corresponding exercises to consolidate knowledge. Engineering materials and so on, either one of the knowledge points we need to learn the basics of the corresponding practice, to consolidate the purpose of the knowledge points, today to bring you the cost engineers, "installation engineering measurement" high-frequency test practice questions, the following we come together to practice a little.

1, according to the "general installation engineering quantity calculation specification" GB50856 - 2013 provisions, belonging to the safety and civilization construction and other measures of the project are ( ).

A. Increase in construction in a health-hazardous environment

B. Environmental protection

C. Increase in non-night construction

D. Increase in high-rise construction

Reference Answer: B,C,D

Reference Analysis: This question is about the content of the list of measures. Safety and civilization construction and other measures include: safety and civilization construction (including environmental protection, civilization construction, safety construction, temporary facilities), night construction increase, non-night construction increase, secondary handling, winter and rainy season construction increase, protection of completed works and equipment, high-rise construction increase.

2, according to the "general installation engineering quantity calculation specification" GB50856 - 2013 provisions, temporary facilities belong to the safety and civilization construction and other measures project, its project content includes ( ).

A. Construction site brick, concrete blocks and other enclosures of the installation, maintenance, demolition

B. Underground (dark) room and other parts of the construction of the lighting equipment used in the installation and maintenance

C. Completed works and equipment covering, wrapping, closure, isolation and other protective measures

D. Other temporary facilities of the erection, maintenance, dismantling

Reference Answer: A,D

Reference Analysis: This question is about the list of measures. Temporary facilities: construction site using color, shaped steel plate, brick, concrete blocks and other fences of the installation, maintenance, demolition; construction site temporary buildings, structures, erection, maintenance, demolition, such as temporary dormitories, offices, canteens, kitchens, toilets, clinics, temporary cultural and welfare rooms, temporary warehouses, processing yards, mixing platforms, temporary improvised water towers, pools, etc.; construction site temporary facilities of the erection, Maintenance, demolition, such as temporary water pipelines, temporary power supply lines, small temporary facilities; construction site within the scope of the temporary simple road paving, temporary drainage ditches, drainage facilities, masonry, maintenance, demolition; other temporary facilities, maintenance, demolition.

3, in accordance with the "General Installation Engineering Quantity Calculation Standards" GB50856 - 2013 provisions, measures the list of items can be listed as "engineering system testing, inspection" project is to be built in the project ( ).

A. Design pressure greater than 10MPa pipe laying

B. Volume greater than or equal to 50m3 spherical tank fabrication and installation

C. Medium-pressure shell-and-tube waste heat boiler fabrication and installation

D. Low-pressure glass-lined pressure vessel fabrication and installation

Reference answer: A,B,C

Test difficulty: Statistics: the number of questions. >Test Difficulty: Statistics: This question *** has been answered 165 times , correct rate 50% , easy to wrong items are A,B .

Reference Analysis: This question is about construction measure items and their measurement. When the proposed project has three types of container production, installation, there are more than 10MPa high-pressure pipeline laying, measures the list of items can be listed as "engineering system testing, inspection". Options B, C belongs to the three types of pressure vessels of the standard; Option D is correctly described as "medium-pressure glass-lined pressure vessel production and installation".

4, according to the "general installation engineering quantity calculation specification" GB50856 - 2013 provisions, the following items belong to the safety and civilization of construction and other measures of the project ( ).

A. Protection of completed works and equipment

B. Protection of harmful compounds

C. Protection of high concentration of oxygen

D. Increase in high-rise construction

Reference Answer: A,D

Reference Analysis: This question is about the list of measure items. Option BC belongs to the specialized measure items.

5, according to the "general installation engineering quantity calculation specification" GB50856 - 2013 provisions, scaffolding erection and dismantling measures project includes the work content ( ).

A. On-site and off-site handling of related materials

B. Erection and dismantling of scaffolding

C. Erection and exceeding of the perimeter netting

D. Stacking of materials after dismantling of the scaffolding

Reference Answer: A,B,D

Reference Analysis: This question is about the list of measure items. Scaffolding erection and dismantling: on-site and off-site material handling; erection and dismantling of scaffolding; stacking of materials after dismantling scaffolding.

The above is the cost engineers "installation engineering measurement" high-frequency test practice questions, I hope you can eat each topic, to ensure that the next time you encounter the same type of questions can be done, as for the preparation of the examination in 2021 candidates, the first thing you need to know is the first level of cost engineers need to enroll in what conditions they are in line with the words and then prepare for the exam is not too late oh!