Installation of the pull-rope switch. First, the pull-rope switch should be installed on both sides of the conveyor where there are maintenance channels. The installation location should ensure that maintenance personnel can easily operate in an emergency.
Second, fix the pull rope switch on the rack.
Third, the distance between the two switches on each side is about 50m, and they are connected by a steel wire rope with a diameter of Φ4. The tightness should be kept moderate.
Fourth, in order to reduce the influence of the weight of the wire rope on the switch startup, a support ring should be installed on the frame every 3m to support the wire rope.
Fifth, the other end of the wire rope is tied to the tension spring and fixed with a rope buckle. Without affecting normal use, use a tensioner to tighten the pull ropes on both sides to ensure that both sides Tension balance.