1. After the equipment arrives at the site, the user shall conduct acceptance according to the delivery list.
2. Place the washing tank on the basis of pre-poured concrete first, and find the level according to the channel steel frame, with a four-point error within 2mm.
3. Install the vibrating screen. When four supporting beams are installed with spring bearing seats, the spacing should be basically equal, the upper and lower surfaces of the bearings should be parallel, the rubber springs should be perpendicular to the ground plane, tighten the clamping bolts and connect the motor wires.
4. Install the vacuum high-pressure pump; Place the vacuum high-pressure pump on the base, which should be flush with the ground and padded. The front end of the pump is equipped with a valve, a water inlet pipe and a cleaning tank. The outlet pipe should be aligned, welded firmly and without water leakage. Tighten bolts after secondary grouting of anchor bolts. The motor should be connected to the power cord to test the rotation direction, which should be consistent with the direction of the vacuum high-pressure pump, and then butt-jointed with the flange. After alignment, tighten the motor anchor bolt. This pump can't run at no load.
5. High-pressure separator: install the high-pressure separator on the channel steel bracket of the reflux box, connect the reflux elbow with the water outlet, insert the lower end of the elbow into the reflux box and weld it firmly with the upper cover plate, recover the fine sand into the discharge box at the front end of the high-pressure separator, and install bolts and tighten them. Install 76mm feeding hose, and connect the lower end with the pump outlet pipe and fasten it with iron wire.
6. Install the overflow hose and put it into the sink according to the site conditions.