And specifically depends on the project is in what place, under which fire brigade, some fire departments require directly with the relevant stamped information drawings to the fire service center to do. In Xi'an, you can consult the Xi'an Du'an electronic fire design, audit, declaration, filing, installation, decoration, design, renovation, testing, acceptance procedures, opening permits, safety inspections, maintenance and other fire remodeling and construction projects is a one-stop service. The following is the relevant procedures to declare the process.
One, online filing: fill out the form on the fire network to declare, if the draw 5 working days to send the information to the fire department to check;
1, online review of the draw; the preparation of all the relevant design information, decorative design drawings, fire water supply, automatic fire extinguishing system, automatic fire alarm system, fire power supply system, smoke evacuation system, emergency lighting and evacuation instructions system and other relevant Fire system design drawings, designed by the formal qualification unit and provide stamped documents; while providing business license and certificate of qualification; to obtain permission to renovate the letter issued by the fire department;
2, the online report is not sampled: direct construction, must be accepted (must be perfected online declaration of the sampled information, ready for acceptance one by one to check);
Two, renovation permits; to obtain permission to renovate the letter issued by the fire department Permit to renovate the letter;
Three, sent for inspection;
1, material samples, fire decoration process used in the construction materials, take samples sent for inspection; general fire acceptance inspection of the most sampling of various types of fireproof paint, fire doors, emergency lights evacuation signs and fire extinguishers, decorative decorative and carpet, etc.;
2, the preparation of material information, samples of materials related to the certificate of conformity Copies, submit the fire product inspection report of the statutory inspection agency, and fire product production license or in our province sales and use of the record certificate;
3, to prepare the corporate information;
Four, acceptance; fire project is done, you have to apply for acceptance; online declaration of the draw, there are 2 options:
1, the fire department staff to come to the site acceptance; according to the The actual situation, there may not be on-site acceptance, according to the project specificity decision;
2, acceptance is not drawn, you must provide all the above relevant fire design information, and graphics and the actual construction of the same;
fifth, open for business inspection; the fire brigade will be sent to the scene to see whether the information you presented with the match, whether it is in line with the norms, to get a certificate of conformity can only be opened for business;
Sixth, late training; staff door-to-door fire prevention knowledge, explain the use of fire equipment, escape and other fire emergency rescue drills to implement the program, the popularization of relevant fire prevention knowledge, to master the emergency rescue procedures and fire equipment operation and use, to improve the emergency response capabilities of the site management staff.
1, fire drills
2, training photos for the record
3, trained personnel registration