What information is required for completion acceptance filing of construction projects in Chongqing?

The application materials submitted by the applicant should be provided in complete sets classified by department.

(1) Materials required by the urban and rural construction authorities

1. 1 copy of "Application for Registration of Construction Project Completion Acceptance" (original);

2. 1 copy of "Construction Project Completion Acceptance Letter" (original);

3. 1 "Construction Drawing Design Document Review Report" (copy);

4. "Construction Project "Archives Acceptance Opinion" and 1 copy of the "Archives Handover" (original will be presented and a copy will be accepted);

5. 1 "Project Completion Report" issued by the construction unit (original);

6. 1 "Project Quality Evaluation Report" issued by the supervision unit (original);

7. 1 "Survey Document Quality Inspection Report" issued by the survey unit (original);

8. One copy of "Design Document Quality Inspection Report" issued by the design unit (original);

9. One copy of "Project Quality Warranty" issued by the construction unit (copy);

p>

10. 1 copy of the certificate (original) provided by the construction unit that the construction unit has paid for the project in accordance with the contract;

11. 1 copy of the "Building Energy Efficiency Evaluation and Labeling Comprehensive Evaluation Form" (original) )

12. One copy of the "Chongqing Real Estate Development and Construction Project Manual" approved by the real estate development administrative department (original);

13. The commercial housing project should provide the "Use of New Commercial Housing" 1 copy of Instructions and Quality Assurance Letter (copy);

14. Municipal infrastructure projects should also provide 1 copy of relevant quality inspection and functional test information

(copy).

15. 1 CD of 1:500 measured topographic map of the completed construction project measured and drawn by a surveying and mapping unit with corresponding qualifications;

Municipal pipeline projects submitted to the municipal surveying and mapping product quality supervision station for acceptance 1 CD of qualified pipeline as-built drawings and surveying and mapping data.

(2) Materials required by the urban planning department

1. Application form for construction project planning completion acceptance certificate (parallel acceptance project) 1 copy (original);

2. One copy (original) of the completed drawing of the construction project (for the construction project, only the completed floor plans, elevations, sections and the completed general plan are submitted);

3. Prepared by a surveying and mapping unit with corresponding qualifications 2 copies of the house completion measurement report (including electronic documents) (original);

4. 1:500 completed measured topographic map of the construction project measured and drawn by a surveying and mapping unit with corresponding qualifications (with inspection line receipt attached, including Electronic documents) 2 copies (original);

5. For municipal pipeline projects, submit 2 copies (original) of pipeline completion drawings and surveying and mapping data (including electronic documents) that have passed the acceptance of the Municipal Surveying and Mapping Product Quality Supervision Station.

(3) Materials required by the public security and fire department (one copy each)

1. Information required for civil engineering acceptance declaration

⑴ Construction project fire acceptance declaration form ;

⑵Construction project preliminary design review opinion letter (copy);

⑶Project completion acceptance report;

⑷Construction permit issued by the construction administrative department Certificate (copy);

⑸ Fire protection product list and quality certification documents;

⑹ Fire protection facilities and electrical fire protection technology testing certification documents;

⑺ The legal identity certificate and qualification level certification document (copy) of the fire protection facility construction, project supervision, and testing unit should be marked "This document is verified to be correct with the original" and stamped with the official seal of the unit;

⑻ Yes Certification documents and factory certificates that building components and building materials required for fire protection performance meet national standards or industry standards;

⑼Complete drawings related to fire protection acceptance (general plan, standard floor plan and non-standard floor plan , elevations, sections, plans and system diagrams of various fire protection facilities) and concealed engineering records;

⑽ Other materials required to be provided by law.

2. Fire protection acceptance stage of decoration project

⑴ Construction project fire protection acceptance declaration form;

⑵ Construction project decoration design review opinion letter (copy);

⑶ Letter of acceptance of fire protection for the main building (copy);

⑷ Project completion acceptance report;

⑸ List of fire protection products and quality certification documents;

⑹ Documents proving that the electrical fire protection technology has passed the test. If there are modern fire protection facilities, the documents that have passed the test of the fire protection facilities should be provided;

⑺The legal identity of the fire protection facility construction, project supervision, and testing units Certificates and qualification level certification documents (photocopies) should be marked "This document is verified to be correct with the original" and stamped with the official seal of the unit;

⑻ Building components, building materials, and interior decoration with fire protection performance requirements Documents proving that decorative materials comply with national standards or industry standards, factory certificates and witness inspection reports;

⑼Complete drawings related to fire protection acceptance (plans for each floor of the decoration, plans for various fire protection facilities and system diagrams) and concealed project records;

⑽Other materials required by law.

(4) Materials required by the environmental protection department

1. Environmental protection pre-acceptance (trial production):

(1) Environmental protection pre-acceptance of Chongqing construction projects ( Trial production) application form 3 copies (original).

2. Environmental protection acceptance:

(1) 5 copies (original) of the environmental protection acceptance application form for completion of the construction project (divided into 4 forms according to the specific conditions of the construction project);

① Application form for environmental protection acceptance and pollutant discharge upon completion of construction projects (applicable to construction projects focusing on pollutant discharge);

② Application registration card for environmental protection acceptance upon completion of construction projects (Applicable to construction projects that mainly focus on ecological impact and fill out the environmental impact registration form);

③ Application form for environmental protection acceptance of completed construction projects (applicable to construction projects that mainly focus on ecological impact and prepare an environmental impact report form) Construction projects);

④ Application report for environmental protection acceptance of completed construction projects (applicable to construction projects that focus on ecological impact and prepare environmental impact reports).

(2) Two copies (original) of the completed environmental protection acceptance monitoring report or acceptance investigation report of the construction project prepared by a qualified monitoring agency or environmental assessment agency (for construction projects that fill in the completed environmental protection acceptance application registration card, The applicant does not provide this application material).

Remarks: For projects that have passed the acceptance of co-organized items, the construction unit must provide the urban and rural construction department with an approval document or a permission document issued by the planning, fire protection, and environmental protection departments (present the original, and receive a copy)

p>

Basis for establishment:

"Regulations on Quality Management of Construction Projects", "Pilot Plan for the Reform of Administrative Approval System in the Construction Field of Chongqing" (Municipal Government Order No. 190), "Fire Protection Supervision and Management of Construction Projects" Regulations", "Chongqing Trial Measures for Parallel Approval of Construction Project Acceptance Links" and "Regulations on the Management of Completion Acceptance Recording of Housing Construction Projects and Municipal Infrastructure Projects", etc.

Reference materials: /webzw/F_News/ShowNews.aspx?id=91