1, commission a qualified EIA company. You take the project document from the NDRC as well as the feasibility study report to the EIA company, which will send someone to your processing site to conduct a site survey.
2, the EIA company to prepare the EIA report. When the EIA company prepares the EIA report, communicate with the EIA company in time to ensure the quality of your EIA.
3, the EPA commissioned review. After the report comes out, send it to the EPA, if it needs to be reviewed, after the review, some comments will be made, and the EIA preparation staff should be revised according to the review comments.
4, the EPA approval. You finished taking the modified report, hand over a local environmental protection bureau, the environmental protection bureau and publicity, after the publicity will give you an approval document, get approval documents, so that the EIA procedures are completed.