Equipment into the field to open acceptance, as a general contractor needs to prepare what, in addition to open acceptance organized by who shall notify which people?

Equipment into the field, should be constructed by the construction unit, construction units, supervision units, supply units **** with the unpacking inspection, and fill out the "equipment unpacking inspection record".

One, the main content of the equipment unboxing inspection: the origin of the equipment, varieties, specifications, appearance, quantity, accessories, marking and quality information, relevant technical documents.

Two, the equipment should have the quality of the following information:

1, all types of equipment should have a quality certificate, its date of production, specifications, manufacturers and other content should be consistent with the actual field of equipment.

2, for national and local specific equipment, there should be a corresponding qualification level testing unit test report.

3, the main equipment, appliances should be installed instructions.

4, finished compensator should be pre-stretching instructions.

5, imported equipment should be commercially available certificate (National Certification Committee announced the mandatory certification [CCC certification] products, except) and the Chinese version of the quality of the documents, performance test reports and the Chinese version of the installation, use, maintenance and testing requirements and other technical documents.

Three, the equipment should be well-packed when entering the field, no surface scratches and external impact damage. Should be in accordance with the relevant standards and the requirements of the procurement contract for all equipment origin, specifications, models, quantities, accessories and other items for testing, and meet the requirements before acceptance.

Four, pumps, heat exchangers, tanks and other equipment should be printed on metal materials, nameplates, nameplate labeling content should be accurate, clear handwriting.

Fifth, there are objections to the equipment should be tested by the appropriate qualification level testing unit to carry out sample testing, and issue a test report.

Extended information:

< p>The main contents of the unpacking and acceptance:

1, equipment name, number, specification model, manufacturer's name, packing list number, the number of pieces received truthfully.

2, inspection records: fill in the packaging is good; random documents are complete; spare parts and accessories are complete. Appearance refers to the appearance of the equipment is good; test whether the situation is in line with the provisions.

3, test results: fill in the actual whether there are missing parts and damage.

4, the conclusion: should be based on the actual test, fill in whether to meet the design requirements and the use of the requirements and measures that must be taken.

5, the signatures of all parties should be complete and stamped, the supply unit is not on site, supervision (construction) unit can also be recognized.

On-site unpacking inspection notes:

Should be counted against the packing list piece by piece, and make a good record, such as damage, corrosion, parts shortages and other issues, should be photographed or other methods to make a good record, as a supplier and the relevant departments of the basis for negotiating a claim, and pay attention to the claim period specified in the procurement contract for the equipment. Also note that after the equipment out of the box inspection, such as can not immediately start the installation, should be repackaged, and do a good job of rust and moisture.