What are the specific contents of the construction organization design plan for a sewage treatment plant in Henan? Zhongda Consulting will answer it for you below.
Chapter 1 Construction Organization Design Preparation Instructions
Section 1 Preparation Guiding Ideas
Thanks to a company in Henan Province for inviting our company to participate in a certain sewage treatment plant in a certain city Bidding for Project Section II. We will take "providing the best quality services to the construction units" as our basic guiding ideology, invest in our company's best backbone construction team, and aim to build high-quality projects that satisfy the construction units most with the best work quality and create a green The construction environment, with strict cost management, uses new technologies and new processes that are most suitable for this project to improve quality, minimize the consumption of materials, and ensure that every investment by the construction unit can obtain a satisfactory return.
"Construction Organization Design of a Sewage Treatment Plant Project in a City" is one of our company's bidding documents for a sewage treatment plant project in XX City. This is a programmed programmatic document compiled by our company on the basis of carefully reading relevant documents, being familiar with the drawings, understanding the design intentions and conducting on-site inspections on project quality, cost, construction period and other aspects. We strive to fulfill every commitment we make to the construction unit in the "Construction Organization Design", hoping to win the trust of the construction unit with an economically reasonable, technologically advanced, practical construction plan and a rigorous and pragmatic work style.
In the process of writing this "Construction Organization Design", we strive to use a shorter length and within a shorter time to let experts know the key points and difficulties expressed in this "Construction Organization Design"; The precise and concise language and detailed illustrations fully display the key information that is difficult to express in ordinary engineering language for engineering experts. The general information is briefly explained for each expert to choose from. In addition, our company cherishes this precious opportunity given to us by the construction unit. If our company is lucky enough to win the bid, we will follow the principles determined in this "Construction Organization Design", follow our company's technical management regulations and quality system documents, and explain the design in detail. After the drawings are reviewed, a detailed special project construction plan and operation instructions will be prepared to provide complete technical documents for the work to guide the construction and ensure high-quality, high-speed, and safe completion of the construction of the project, and provide the construction order
Submit a satisfactory project.
Section 2 Preparation Basis
1. Bidding documents for this project
2. Company Quality System Assurance Manual (Third Edition)
3. Company quality system procedure documents (third edition)
4. Construction process standards for construction and installation sub-projects (DBJ01-26-96)
5. Earthmoving and blasting projects Construction and acceptance specifications (GBJ201-83)
6. Foundation and foundation engineering construction and acceptance specifications (GBJ202-83)
7. Underground engineering waterproofing construction and acceptance specifications (GB50205- 95)
9. Specifications for construction and acceptance of building ground projects (GB50209-95)
10. Specifications for construction and acceptance of roof projects (GB50207-94)
11. Specifications for construction and acceptance of building decoration projects (JGJ73-91)
12. Specifications for engineering measurement (GB50026-93)
More about engineering/service/purchasing tender documents Write and produce to improve the bid winning rate. You can click on the official website customer service at the bottom for free consultation: /#/?source=bdzd