1), pull the mold to the front of the corresponding machine and put it firmly screwed on the corresponding ring and confirm the thimble.
2) Lift the mold with a smooth carriage and slowly put it into the machine to align the machine and the positioning ring of the mold.
3) Slowly close the mold and tighten the mold.
4), use the pressure plate to tie the mold tightly and slowly release the crane and remove the crane, again take down the lift palladium.
5), start the high pressure and again lock the screws and the injection nozzle.
6), first check the mold for any abnormalities or to open the mold before the need for the equipment, after confirming the good and slow open the mold.
7), after opening the mold again to check whether the mold is abnormal.
8), find the relevant personnel to receive special auxiliary equipment and debugging.
9), according to the requirements of auxiliary equipment such as: water, strong pull, hot runner, etc. and test these auxiliary equipment is normal.
10), ready to start.