Purpose:
In order to ensure the normal life of the owners, the working order and the safety of life and property, and to ensure the normal operation of the equipment, so that the buildings and facilities and equipment are not damaged during the summer safety and flood control.
Scope of application:
Scope of jurisdiction
Supervision and implementation:
Safety and Environment Department
Flood emergency procedures:
I. Flood control organization procedures
Second, the flood engineering department flood control measures
1, the establishment of a special storage library for flood control equipment, storage of flood control equipment, mainly should be drainage pumps, drainage hoses, waterproof distribution boxes, woven bags, sand, shovels, etc.;
2, before the flood season, the Department of Safety and Environment Supervisor, foreman, should be carefully inspected.
(1) whether the roof platform drains are unobstructed, and at the same time will be the roof of the garbage clean;
(2) check the underground puddles of sewage pumps are sensitive and effective, and will be controlled to open in the "automatic" position;
(3) check the size of the area inside and outside the rainwater wells, sewage wells, rainwater pipes, and remove the accumulation of materials. Whether there are accumulations, and to remove, to ensure smooth drainage;
(4) maintenance team to check the distribution room, control room and other important rooms whether there is a leakage of rain, if any should be dealt with in a timely manner.
(5) Safety and Environment Department supervisor, foreman, focus on checking the rainwater outlets, drainpipes, underground garages, sewage pumps, around the elevator pits and previous recorded problem points.
(6) At the same time to strengthen the electrical equipment, facilities, including lightning nets (pins), cable trench inspection, inspection, found that the problem is resolved in a timely manner.
Third, the risk of handling procedures
1, if the rainwater into the underground garage, safety and environment department supervisor, foreman, should promptly notify the engineers to start the sewage pump drainage, and timely notification of the owner, the organization of the evacuation of vehicles out of the garage, parked in the safe place. At night and on double holidays, the manager of the Department of Safety and Environment, on the one hand, the organization of the personnel to rescue, on the one hand, immediately notify the Department of Safety and Environment, other members of the flood control team;
2, cell safety and environment department of all personnel by the manager of the Department of Safety and Environment command, part of the personnel to maintain order, part of the personnel to remove the danger, rescue equipment;
3, the community cleaners to remove the water from all places;< /p>
3, the community cleaner
4, after the occurrence of dangerous situations, the company office to carry out a comprehensive inspection, statistics on the damage caused by the flood and material consumption, and timely replenishment of flood control materials, make good preparations for the next flood control;
5, each cell supervisor is responsible for the incident handling process detailed records to the company's leadership to make a report.
The property company's emergency plan for big stormy days 2
According to the property group company issued a notice and requirements, in order to do a good job of the company and the project flood prevention work, to protect the company and the owners of the property and personal safety, especially the development of the emergency plan.
First, the organization and responsibilities
(a), the establishment of the flood control leading group
Group leader:
Deputy leader:
Members:
Responsibilities: responsible for property management company and the project drainage facilities and equipment inspection and maintenance work, to ensure that the drainage system is intact and effective; to strengthen the inspection of various projects, and timely find leaks, to avoid the leakage of rain, to avoid the leakage of rain. Leakage points, to avoid the occurrence of short circuits and equipment damage caused by rain leakage, especially the high distribution room of each project, must ensure normal power supply; responsible for the overhaul of the lightning facilities and equipment of each project, is responsible for the reserve of the necessary flood control, disaster relief materials; once the flood disaster, in accordance with the flood relief plan to organize the maintenance and rescue work.
(b), under the command of the flood control leadership group set up four working groups
1, the establishment of the flood control rescue group
Group leader: Members:
Responsibilities: under the command of the leading group of flood control flood control rescue work, the project manager to organize the rescue of the management of the region to carry out a comprehensive examination to determine the causes of accidents in the area of waterlogging, the development of local emergency response measures. The organization will deal with the situation.
2, the establishment of equipment security group
Group leader: Member:
Responsibility: under the command of the flood control leadership group to carry out flood rescue (drainage with pumps) work. The project according to the actual situation of the project, the rational organization of the use of drainage pumps and other equipment on the serious areas of water drainage, to ensure that the management of the region normal.
3, logistics group Group Leader: Members:
Responsibilities: Under the command of the flood control leadership group for emergency communications, statistics, logistics. In the event of flooding, do a good job in the company's internal information transfer and logistical support work, after the flood, statistics and summarize the losses caused by flooding.
4, emergency rescue team leader: Members:
Responsibilities: Under the command of the leading group of flood control flood assistance work. When a project occurs in a major risk, the timely deployment of rescue.
Second, flood control materials:
rain shoes, raincoats, shovels, woven bags, flashlights, wire, drainage pumps, bracketed disks, etc., and set up a special person in charge of ensuring that the flood control materials are available 24 hours.
Third, the project manager for the regional flood control responsible person; strengthen the flood control awareness training, the key parts to check in place, found that the risk of timely reporting to the department or the company leadership, and take active measures to avoid the expansion of the risk.
Fourth, during the flood control period, all flood control must keep the communication tools 24 hours
Fifth, in case of moderate rain above the rain, the project manager must be on duty; in case of heavy to heavy rain rain, the implementation of the full duty system.
Sixth, when the office duty to receive flood control notice, should promptly notify the duty leader and all the flood control.
VII, the project duty received the owner's help information, should promptly notify the duty leader and the project, the main members of the flood control quickly to the scene to check the situation, timely disposal; when encountered in the management of the area of a large area of water, should be quickly organized to rush to the scene, mobilizing pumps and other related equipment for dredging, drainage, and at the same time reported to the leadership of the company.
VIII, usually, the office staff and customer service projects should pay close attention to the weather changes, and timely notification of the relevant weather anomalies, while doing a good job during the flood control duty signature, and major flood records.
IX, flood control materials should be strengthened management, the end of the flood season to the warehouse for safekeeping, in order to prepare for the later renewal.
The big stormy days property company emergency plan 3
First, the purpose:
In order to establish and improve the property management in the sudden public **** events in the early warning and emergency response system, to ensure that the property company in case of major floods can be efficient and orderly flood rescue and relief work, according to the requirements of the competent authorities and the company's leadership, in order to the rescue and relief work. According to the requirements of the higher authorities and the leadership of the company, in order to put the rescue and relief work into practice, to ensure the safety of this year's flood, combined with the actual situation of our company, the development of this plan.
Second, the guiding ideology
Conscientiously implement the national, municipal and county flood control work conference, adhere to the scientific concept of development and people-oriented thinking, active defense against floods, in order to build a harmonious society, the implementation of the "safety first, preventive measures, constant preparedness, and all-out emergency relief "The work of the policy; unified leadership, careful deployment, coordinated action, hierarchical management, a clear division of labor, scientific scheduling, to further strengthen the responsibility of flood control, effectively grasp the various aspects of flood control work, improve, implement the flood control plan, strengthen flood monitoring and early warning forecasts, improve flood prevention and flood control integrated capacity, to minimize the loss of floods to the tenants and the company.
These are the most common problems in the world.
Third, the main task
1, the implementation of accountability. Conscientiously implement the project manager responsibility system as the main content of the flood control responsibility system, improve the rules and regulations, clear work responsibilities, responsibility to implement.
2, the organization to develop and implement emergency plans for flood control. Combined with the actual situation of each department, each project, fully foresee the problems that may occur, scientific and rational development of flood prevention, flood control work emergency plan.
3, each department, each project to the implementation of flood control materials in place, to achieve adequate flood control materials, to do point, location, by the person responsible for the management.
4, the projects to do 24-hour duty, and a leader on duty, the implementation of the project manager responsibility system. Ensure that the information is smooth, and properly respond to emergencies.
Fourth, the leadership of the command and rescue and relief agencies
1, the establishment of the flood control work group
Commander: xxx
Deputy Commander: xx, xx, xxx
Members: xx and so on
2, the establishment of the company's flood control and flood rescue commando
each Project to form their own rescue commando team, the captain of the project manager (or order maintenance supervisor) as respectively.
Fifth, the main responsibilities
1, the leading group of flood control responsibilities
(1) quickly receive and convey the flood control department and the higher leadership on the flood control and flood relief instructions.
(2) deployment and command implementation of flood control and flood relief operations. The emergence of dangerous situations, the rescue commando by the flood control work leading group command.
(3) grasp the basic situation of each unit of flood control and flood prevention work, understand the flood situation and timely report.
(4) the implementation of other tasks assigned by the superiors.
2, flood rescue commando duties
(1) receive and report flood relief.
(2) directly involved in flood control and disaster relief operations.
(3) Coordinate the resettlement and transit of affected households.
(4) Perform other tasks assigned by the company's flood control work leading group.
Sixth, the preparatory work (each project in conjunction with the actual situation with reference to the implementation)
1. In advance of the inspection and dredging of the ground and roof drains, cleaning septic tanks and sewage wells, checking the drainage mains and the municipal pipeline network interface, to ensure that the smooth.
2. Check the sewage pumps to ensure that the sewage pumps in important locations (generator room, pump room, power distribution room) and other locations can run automatically.
3. Overhaul standby generators and control lines to ensure the safety and reliability of emergency power.
4. Check the integrity of the flashlight, check the equipment room emergency lighting.
5. Check the cell lightning protection system.
6. Check the facade, notify residents, organize balconies, roof gardens, clean up overhead shelves, canopies.
7. Trimming of large trees in the neighborhood with dead branches and serious insect damage.
8. Determine the evacuation routes and locations of vehicles and people in emergency situations.
9. The project fixed people, regularly watching the local weather forecast every day, and report important information to the project leader in a timely manner.
VII. Project key locations and equipment and facilities (each project combined with the actual situation with reference to the implementation)
1. equipment room, and below the level of the community elevation of the equipment and facilities for the focus of the monitoring (basement, elevator shafts).
2. Office computers and monitoring mainframe, gate equipment and other public **** electricity equipment.
Eighth, material preparation (each project in conjunction with the actual situation with reference to the implementation)
1, the preparation of spare pumps, buckets, brooms, towels.
2, prepare the necessary rain gear such as umbrellas, rain shoes, raincoats.
3, emergency lighting such as: flashlights, emergency lights.
4, emergency communications such as: walkie-talkies.
5, medical care: tourniquet, anti-inflammatory drugs, iodine, band-aid.
6, rescue tools and materials such as safety belts, safety ropes, shovels.
7, prepare the necessary funds.
8, emergency protection vehicles.
Nine, after the emergence of flood emergency measures
1, ordinary flood emergency
(1) to strengthen the communication with the county flood control department, strengthen the flood monitoring and forecasting.
(2) According to the actual situation of our units, flood control requirements for each department and project, and organized evacuation of households.
(3) Take measures to guarantee the smooth contact of the flood control system.
(4) Supervise the preparations for rescue and relief work and check the implementation.
(5) Based on the flood control department's flood trend judgment, strengthen the publicity and education on flood control to households, quell rumors, stabilize people's minds, and maintain normal production and living order.
2, major flood emergency
(1) After receiving the notice of major flood emergency from the higher leadership, the flood involved in the flood relief team of the project quickly focused on how to quickly put into the work of flood control and rescue.
(2) Organize forces to do a good job of evacuation and resettlement of households, and take favorable measures to try to protect the basic living conditions of households.
(3) Organize the relevant personnel to maintain public **** order, to prevent people from taking advantage of the opportunity to make trouble.
(4) Understand the situation of the disaster, do a good job of publicity, quell rumors and misinformation, and maintain social stability.
The specific 'emergency measures refer to the above process, combined with the actual situation of the project, in accordance with the project's flood emergency work program implementation.
X. Information summary and report
Project flood control headquarters according to their respective division of responsibilities, responsible for collecting, organizing and studying the analysis of the flood control information may occur in the jurisdiction of the summary, in accordance with the principle of early discovery, early reporting, early disposal, and quickly report the situation to the company's competent leadership. For all kinds of flood control emergencies and may lead to a variety of hidden dangers, any individual has the right and obligation to report to the company's office, and the right to the relevant departments of the work of negligence and mishandling of the behavior of the report, flood control information reporting and processing follow the principles of:
1, the important information is reported immediately, due to objective reasons it is difficult to accurately grasp the information, it should be reported in a timely manner to report on the basic situation, and at the same time Grasp the situation, and then make up the details of the report.
2, general information according to sub-project management authority, reported to the person in charge of flood control projects.
3, the company's flood control work group received a major flood, industrial, risk, disaster report, should be reported immediately.
XI, other
When faced with a major, emergency, emergencies or situations involving the normal work of the residents, business, life order, with the customer service center of the project near the verbal notification of the customer and do a good job of customer appeasement and explanation of the work.
big storms and rainy days property company emergency plan 4According to the "Chinese People's **** and the State Flood Control Law" and the so-and-so group holding limited liability company, the district, the street and other relevant departments of the higher level on the specific needs of flood control requirements, combined with the actual situation of my business, in order to ensure that the measures are put in place, so that the flood season the work of all the work goes smoothly, the preparation of the enterprise flood control rescue emergency plan ". Specifically as follows:
First, the guiding ideology
Based on the principle of "solidarity and cooperation and local interests are subordinate to the overall interests", the scientific attitude to seriously analyze the actual situation, based on the prevention of floods to cope with sudden disaster weather, and do a good job in flood control and drainage of the preparatory work, take effective measures to avoid the rain and floods, and take effective measures to avoid the floods. Preparation, take effective measures to avoid rain leakage, backflow, flooding and other phenomena during the rainy season, to avoid and reduce economic losses, to protect the normal operation of the flood season production and operation, the preparation of operational flood control plan, to ensure the safety of life and property of enterprises and employees.
Second, the flood control work command system
Flood control work is strictly enforced under the leadership of the chief executive hierarchical system of responsibility, layer by layer to solidify the responsibility of the workshop departments during the flood control period, a hand in person, and at the same time, in order to make the flood control of the command of the work of the order of the enterprise set up a flood control work command. The members are as follows:
General Commander: Secretary of the Party Committee of the Group, General Manager Deputy General Commander: Deputy Secretary of the Party Committee of the Group, Chairman of the Labor Union
Members: the enterprise's leaders in charge of the various departments of the Ministry.
Contact: xxx
Duty phone:
Enterprise Office:
Integrated Department:
Night duty:
Duty room:
Third, the formation of emergency rescue and emergency response team
In the flood season, in order to prevent the impact of disasters and accidents on production and operation, we in accordance with the so-and-so group, we will be able to provide the best service. In the flood season, in order to prevent disasters and accidents on the production and operation, we in accordance with the so-and-so group (holding) limited liability company, the district, the street flood control command needs requirements, the formation of the security team and the fire department based emergency rescue detachment, emergency rescue detachment to obey the enterprise flood control work command leadership, in the flood emergency at any time to enter the flood control rescue battle is responsible for the disposal of the emergency situation.
Four, build flood rescue team
1, in order to do a good job of flood prevention, discharge of waterlogging preparations, we are in accordance with the higher level of the flood control command requirements, the formation of the militia and young workers as the main two hundred rescue team, the emergence of a major flood will be subject to the unified mobilization of the District Flood Control Command, ready to go up the dike to fight against floods and rescue. Preparation.
2, in the flood control period, in order to do a good job of the enterprise internal rescue and drainage work, by the enterprise workers to form a 100 people of the rescue team, all the rescue work by the unified mobilization of the Enterprise Flood Control Command.
Fifth, do a good job of flood prevention and anti-rain leakage and anti-inversion of the preparation
In order to safely through the flood, to ensure that the enterprise property is not lost, in the forecast of heavy rain and rainstorms, the workshop, the department should be strengthened to ensure that the flood control force in the staff shall not be less than two people. At the same time, in order to ensure the safety of the production workshops of the enterprises owned by the enterprise's plants, warehouses and the key needs of the security of the flood season, in particular, to eliminate a variety of bacteria through the underground drainage of food infections, the workshop, the department should do a good job of pre-flood leakage prevention and underground drainage pipe inspection in the plant, the warehouse parts of the anti-pouring inspection work, found that the problem in a timely manner to find the competent authorities to solve the problem of the low-lying parts of the terrain should be taken to prevent the pouring of water. Measures to ensure the safety of the flood, do not leak in the middle, small rain, heavy rain does not back up, to ensure that the production and operation of normal.
Six, do a good job of preparing flood control materials
In order to do a good job of this year's flood control, rescue, drainage and other work, to be prepared, the relevant departments to do a good job of flood control facilities, flood control tools, drainage pipes, flood control soil, flood control gates, waterproof plug, communication lines, duty vehicles and other types of materials, management, repair, maintenance and other items of work. Work, so that it is in a good state of readiness. At present, my enterprise has flood control tools: 50 shovels, 50 stretcher, 3 drainage pumps, 18 baskets.
Seven, strict flood control duty system
To ensure safe flooding, in the flood season arrangements for business leaders and managers of flood control duty. The key parts of the need to set up a person on duty system, workshop and relevant departmental leadership on duty system, especially in the event of moderate to heavy rain, the key parts must have workshop departmental leadership on duty, in order to find a timely solution to the problem.
VIII. Flood control work in various departments
In the flood control work, the implementation of the "who leads, who is responsible for", "who is on duty, who is responsible for" the principle of establishing a global concept. Do a good job in the preparation of flood prevention. To this end, the development of the relevant duties:
In the flood season, actively organize and arrange production and do a good job of preventing leakage of rain and sewage backflow of the work, timely grasp of the changes in the weather during the flood season, combined with the production of practical assistance in organizing the drainage, rescue. In the event of rain forecast or sudden rain at night, each workshop, the main departments need to lead the leadership and flood control focus on departmental leadership must be immediately on duty to inspect the workshop, departmental leakage of water and obey the corporate arrangements.
big storm rain day property company emergency plan 5In order to effectively defend against catastrophic floods, standardize the flood control procedures, effectively safeguard people's lives and property safety, and minimize disaster losses, according to the "Chinese People's Republic of China *** and the State Flood Control Law" and "Chinese People's Republic of China *** and the State Flood Control Regulations" regulations, combined with the actual situation of flood control work in the project, the development of this plan.
I. Flood control and flood emergency rescue organization
1, the accident site commander by the project manager manager xx;
2, the casualty rescue group by the deputy manager xx as team leader, the construction team of the various shifts were drawn from the composition of the operating personnel;
3, material rescue group by the construction team leader xx As the leader of the group, the construction team of each shift were drawn from the construction personnel;
4, the defense and guidance group by the logistics personnel and construction team of each shift were drawn from the construction personnel;
5, the rescue materials supply group by the materials responsible for Zeng Dehe as the leader of the group, the construction team of each shift were drawn from the construction personnel;
6, the logistical supply group by the project department office personnel
7, the site of temporary medical group by the site medical personnel and construction teams were drawn from each team composed of personnel;
8, the daily office of the leading group of flood control emergency rescue for the project office.
Second, the project manager's emergency organizational functions and responsibilities
1, the accident site commander-in-chief's functions and responsibilities:
a, the command and coordination of all accident site operations;
b, on-site accident assessment;
c, to ensure that on-site personnel and the public emergency response to action implementation;
d, control of emergencies;
e, on-site command of emergency operations;
f, make a good emergency rescue treatment of on-site command after the conversion of the transfer of authority and emergency rescue treatment assistance;
g, make a good job of firefighting, medical care, traffic control, rescue and relief of various public **** rescue department contact work.
2, the functions and duties of the injured rescue group:
a, guide the site operators from the safe channel evacuation;
b, rescue of injured people to the safety zone.
3. Functions and duties of the material rescue group:
a. Rescue and transport materials in the field that can be transferred;
b. Transfer items that may cause new sources of danger to the safe zone.
4, the functions and duties of the defense and evacuation group:
a, effective isolation of the site inside and outside the work and maintenance of the site emergency rescue channel open work;
b, evacuation of residents outside the site to withdraw from the danger zone.
5, the functions and duties of the rescue supplies group:
a, rapid deployment of rescue supplies and equipment to the accident site;
b, provide and check the equipment and safety of the rescue personnel equipped;
c, the timely provision of follow-up rescue supplies.
6, the functions and duties of the logistics supply group:
a, rapid organization of logistics must be supplied;
b, timely delivery of logistics supplies to the hands of emergency personnel.
7, the site of the temporary medical team's functions and responsibilities:
a, the injured person for simple rescue and bandaging work;
b, timely transfer of seriously injured people to the medical institutions for medical treatment.
Three, scheduling duty
The project set up the corresponding flood accident emergency rescue leading group office, in the flood season to arrange for personnel on duty 24 hours a day, duty phone
In the danger of the first time in a timely manner to report to the general director of the emergency rescue, and at the same time reported to the leadership of the corporate headquarters.
Fourth, emergency preparedness
1, the project office under the leadership of the flood emergency rescue leading group, is responsible for organizing the construction team to develop the appropriate emergency plan, do a good job.
2, the office is responsible for doing a good job of collecting, tracking and transmitting weather forecast information, and urging all departments to implement the flood season duty personnel, and make records.
3, received by the project team construction teams in accordance with the location of the relevant emergency alarm issued notice, the project department flood emergency rescue leading group of all personnel should immediately convene a meeting, and organized to make good preparations for disasters, and urged to do a good job of the emergency measures, site site should be strengthened to patrol the inspection, equipped with emergency equipment and materials.
4, the Office of the construction team to organize the construction team to develop the emergency plan measures to deal with flooding accidents.
5, the construction team of each team according to the flood control area to do emergency measures, so that the construction site of the drainage system unimpeded, reinforce the temporary power lines, to ensure smooth communication.
6, dangerous goods should be stored in a clear sign to prevent the flood will be stirred up, mixed, loss, resulting in accidents, need to develop appropriate emergency measures.
7, the project department flood emergency rescue leading group to organize the implementation of the emergency plan and inspection, the office to supervise the departments to do a good job checking and recording.
V. Emergency response
1, the project office is responsible for contacting the flood emergency response related matters, and organizing the construction team to implement the emergency response plan.
2, the construction team should actively cooperate with the office work, and according to the development of the emergency response plan implementation.
3, when a serious accidental flood control situation occurs, the leading group of flood emergency rescue should immediately report to the relevant government departments for assistance and guidance, and timely report to the corporate leadership, while all emergency personnel should be organized according to the characteristics of the disaster and accident situation, the implementation of effective emergency response measures, and strive for a short period of time, and strive to minimize the loss of, and disadvantages or elimination.
4. When a general accident occurs, each department will carry out the disposal of the incident according to the emergency measures, evacuate the personnel and heavy need materials in time, control and prevent the expansion of the incident, and strive to minimize the loss or adverse factors.
When it is confirmed that the flood prevention and flood control accidents, the person in charge of the site ordered to report to the duty room, organizing all on-site construction workers will be placed to protect the construction machinery, on-site construction workers by the team leader to lead the evacuation of all. Trapped construction workers can not evacuate, should choose a higher ground to avoid flooding, self-protection, waiting for the organization to rescue.
Six, the organization of rescue
1, the Ministry of the project organization construction team teams to count the personnel in a timely manner, to confirm that there is no trapped personnel, and assembled on standby, shall not go out privately;
2, the Ministry of the project organization rescue commando, by the construction team teams drawn from the composition of the strongest workers responsible for installing the stacking of sandbags, standardize the direction of the water flow
3, equipped with adequate lighting, life-saving equipment, organized by the project department of good health, high water workers to carry out search and rescue activities;
4, in the event of flooding, such as the equipment can not be evacuated to a safe location, the equipment should be in a power off, reinforced and properly protected to prevent equipment from causing unnecessary damage.
5, the hygienist to prepare, and depending on the flood situation in advance to contact the designated hospital.