Central air-conditioning machine room safety management system

Central air conditioning machine room safety management system

In the real world, the system is increasingly important to people, the system is formed under certain historical conditions of decrees, rituals and other norms. So is it really difficult to draw up a system? The following is the central air conditioning machine room safety management system that I have organized for you, just for reference.

Central air conditioning machine room safety management system 1

In order to strengthen the management of the air conditioning system, to ensure the normal operation of the air conditioning system, to ensure the safe production of the mine, according to the "Coal Mine Safety Regulations" and the "main ventilator management specification" of the relevant provisions of the system, is hereby formulated.

1, the main ventilator room must hang "the main ventilator management system", "the main ventilator operating procedures", "driver job responsibility system", "cadres on duty inspection system", "equipment management system", "high-pressure cabinet operating procedures", "frequency converter operating procedures", the main ventilator distribution system diagram and other boards, the main ventilator equipment operation records and parameters, equipment maintenance and maintenance records, the duty officer handover Records, duty personnel handover records, cadres on duty inspection and other record sheets.

2, the Department of Electrical and Mechanical seriously organize operators to learn the pumping station management system, operating procedures, operating system operating procedures, so that operators are proficient, at least once a month training.

3, the main ventilator room must have a person on duty, do a good job of negative pressure, current, power, air volume, temperature and other parameters of the record work.

4, when the main ventilator failure and shutdown, the backup ventilator must be able to start within 10 minutes, and normal operation.

6, the strict implementation of the shift handover system, the shift must be the main ventilator, electrical equipment, testing instruments and the connection parts of the inspection, such as the discovery of problems with equipment can not work properly, immediately report to the dispatching room, and make a good record.

7, the main ventilator room must have a direct line to the mine scheduling office of the phone, must be installed alarm sensor, when the power failure phenomenon, immediately send an alarm signal.

8, the main ventilator room distribution room, frequency converter room and the nearby 10m range is strictly prohibited smoking and open fire, and must be set up "no fireworks" board.

9, the main ventilator room operators to standardize the operation, on time testing, recording parameters and operating conditions, reasonable adjustment of the operating state.

10, it is strictly prohibited to arbitrarily stop and open the main ventilator, you must ensure that the equipment is operating normally, such as emergencies need to stop when you must report to the dispatching room.

11, often check the main ventilator on the safety devices, measuring devices, electric butterfly valves, etc., and to ensure that it is flexible and reliable, to maintain cleanliness in the machine room.

12, the strict implementation of the registration system, non-machine room managers must be registered to enter.

13, air-conditioning plant room, the strict implementation of the site handover system, and to fulfill the signature procedures.

14, distribution duty room, must be equipped with adequate fire-fighting equipment, shall not be stored with the work of non-related equipment and materials.

Central air-conditioning plant room safety management system 2

First, the air-conditioning plant room management system

1, strictly prohibit unrelated personnel to enter the air-conditioning plant room. In case of special circumstances to enter, must be approved by the competent leadership, and after registration and sent to the engineering staff accompanied by. The case before entering. Into the room should be closed, to prevent small animals scurrying to the electrical control box cabinet, resulting in short circuits and other major events; the distribution box cabinet door should be locked; room requirements have been to keep clean, dry, box cabinet lines organized and orderly.

2, the distribution room in winter and summer seasons to implement 24-hour duty, duty personnel shall not string post, off duty or sleep post. What's more, no gambling, smoking, drinking and other recreational activities in the room; not to leave work during working hours or in the inspection records of false

3, air-conditioning room indoor cleanliness and hygiene, so that the equipment is no ash, no grease, no garbage, no debris indoors.

4, air-conditioning plant room must be equipped with a sufficient amount of firefighting equipment. The water supply pipeline should have a special paint color, marking the direction of the pipeline; water supply valves required to mark the normally open or normally closed sign; equipment required to mark the equipment ledger number, name, age.

5, strengthen the inspection tour and related technical indicators check, and make a record. Inspection should check the door, windows, walls and floors, lighting, units, pumps and other equipment, facilities are intact, whether the operation is normal, there is no abnormal sound. In the inspection, on time to write down the pump operating voltage, current and water supply pressure, water supply system in the water tank situation is normal, the pump operating conditions and water supply water regulating felling, backwater felling working conditions are normal. Drainage valve and piping for any abnormalities. Whether all kinds of valves and meters are working normally. Check whether the lubricating oil system of each rotating machinery needs to be supplemented with lubricating oil. The inspector should sign in the relevant column of the form after copying the readings.

6, timely grasp of heating and cooling technical data, and make a record. In case of emergency, timely contact with the relevant units to make proper handling, and report to the relevant leadership.

7, on-duty personnel required to have water supply and drainage, electrical and other HVAC professional knowledge and licensed after training. Strengthen the daily maintenance of various types of equipment and regular maintenance, strict implementation of the refrigeration (heating) unit open operating procedures.

8, strict handover system:

(1) the shift personnel should be 15 minutes in advance to the post, and carefully review the previous shift operating records.

(2) The shift handover personnel should keep the equipment and site clean.

(3) The person on duty shall not leave the post until the person taking over has arrived.

(4) The shift handover should keep the tools complete and clean, strict shift handover procedures, and if the tools are found to be lost or damaged after the shift handover, the person on duty will be responsible for it.

(5) If an abnormality or accident occurs in the equipment before shift handover, the staff on duty is not allowed to leave the scene, and only after the accident has been dealt with can the shift handover take place.

(6) The shift handover should be a good record of the shift handover, the shift handover personnel should sign.

Second, the air conditioning system report record management system

1, the following conditions report supervisor:

(1) the main equipment (including all the various types of pumps, air handlers,

Page 2/3

fresh air machine and other various instruments, such as the opening and stopping of the abnormal operation.

(2) Adjustment of major air conditioning equipment other than normal operation.

(3) the parts of the equipment transformation, replacement or processing repair;

(4) equipment failure or shutdown maintenance;

(5) operating personnel for a short period of time away from the post;

(6) operating personnel work to go;

(7) external shift contact.

2, the following circumstances must be reported to the higher leadership:

(1) refrigeration unit in addition to the normal operation of the adjustment;

(2) the failure of the main equipment and shutdown maintenance;

(3) the system adopts a new mode of operation;

(4) the system failure and overhaul;

(5) important parts and components of the renovation, replacement or processing repairs;

(6) the operation of the staff work. processing and repair;

(6) the use of tools, spare parts, materials (except for low-value consumables);

(7) outsourcing contacts.

Third, the air conditioning system maintenance tools and spare parts management system:

1. Equipment maintenance spare parts by a person to implement unified management. Regularly formulate the use of spare parts each month, reported to the leadership.

2. Spare parts collection, the supervisor with a purchase order reported to the leadership approval before receiving, and will be used to record.

3. Strictly prohibit the replacement of non-similar specification spare parts, causing hidden danger to the equipment.

4. The use of public tools by a person responsible for the management.

Central air-conditioning plant room safety management system 3

To ensure the safe operation of air-conditioning equipment, to ensure the normal work of the office building needs to develop this provision.

First, the central air conditioning plant room operators must be proficient in the refrigeration principle of the screw unit, the structure and operating specifications, and strictly comply with the operating procedures;

Second, do a good job of maintenance and repair of refrigeration units, so that the equipment to maintain a good state, to prevent the emergence of faults or insecurity, to ensure that the supply of air-conditioned office buildings;

Third, during the operation of the unit, the duty personnel should be During the operation of the unit, the duty officer should regularly monitor the instrumentation (once every two hours), make a good operating record, and regular inspection of the host and auxiliary equipment, found that poor working conditions, should be dealt with in a timely manner and detailed records, if the duty officer can not be dealt with, should be notified to the higher leadership;

Fourth, it is strictly prohibited to smoke around the equipment, the use of open flames, and is strictly prohibited to pile up combustible wastes in the room, to prevent spontaneous combustion caused by fire;

Fifth, strict compliance with the handover of the equipment to ensure that good condition, to prevent failure or security risks. p> V. Strictly abide by the shift handover system, strictly prohibit the use of alcohol at work, not to leave their posts without authorization. Do a good job of health, fire prevention, as far as possible to eliminate all potential accidents;

Six, unauthorized changes in the set value of the unit parameters, if necessary, should be notified in advance to the plant debugging personnel, after permission to change, and will change the parameters to make a record;

Seven, during the shutdown period, should be done to the host computer and the auxiliary equipment, cleaning, maintenance work;

Eight, Duty personnel to leave the engine room at any time to lock the door.

;