Who has the e-mail address of the General Contract Terms in Chapter 4, Section 1 of People's Republic of China (PRC) (China) Standard Construction Bidding Document (2007 Edition)? 82822669@qq.com。

General contract terms

1. GATT

1. 1 Definition of words

The following words in the General Terms and Conditions of Contract and the Special Terms and Conditions of Contract shall have the meanings given in this clause.

1. 1. 1 contract

1. 1. 1 contract document (or contract): refers to contract agreement, letter of acceptance, tender letter and its attachments, special contract terms, general contract terms, technical standards and requirements, drawings, priced bill of quantities and other contract documents.

1. 1. 1.2 contractual agreement: refers to the contractual agreement referred to in article 1.5.

1. 1. 1.3 Letter of Acceptance: refers to the letter from the employer informing the contractor of winning the bid.

1. 1. 1.4 tender letter: refers to the tender letter filled out and signed by the contractor and is an integral part of the contract documents.

1. 1. 1.5 appendix to tender letter: refers to the appendix to tender letter attached to the tender letter to form the contract document.

1. 1. 1.6 technical standards and requirements: refers to the documents named technical standards and requirements that form part of the contract documents, including modifications or supplements agreed by both parties.

1. 1. 1.7 drawings: refer to the engineering drawings included in the contract, as well as any supplementary and modified drawings provided by the employer according to the provisions of the United Nations, including supporting descriptions.

1. 1. 1.8 priced bill of quantities: refers to the bill of quantities filled in by the contractor according to the specified format and requirements as part of the contract documents and marked with prices.

1. 1. 1.9 Other contract documents: refer to other documents that constitute the contract documents confirmed by both parties.

1. 1.2 contract parties and personnel

1. 1.2. 1 parties to the contract: the employer and/or the contractor.

1. 1.2.2 Employer: refers to the party specified in the special contract terms and signed with the contractor in the contract agreement. 1. 1.2.3 contractor: refers to the party that signed the contract agreement with the employer.

1. 1.2.4 contractor's project manager: refers to the full-time person in charge of the contractor at the construction site.

1. 1.2.5 subcontractor: refers to the subcontractor who subcontracts a part of the project from the contractor and signs a subcontract with it.

Guarantor

1. 1.2.6 supervisor: refers to the legal person or other organization that is stipulated in the special contract terms and entrusted by the employer to manage the performance of the contract.

1. 1.2.7 chief supervision engineer (director): refers to the person in charge appointed by the supervisor to manage the performance of the contract at the construction site.

1. 1.3 engineering and equipment

1. 1.3. 1 project: refers to permanent projects and/or temporary projects.

1. 1.3.2 permanent project: refers to the project completed according to the contract and handed over to the employer, including engineering equipment.

1. 1.3.3 temporary works: refers to all kinds of temporary works built to complete the permanent works agreed in the contract, excluding construction equipment.

1. 1.3.4 unit project: refers to the permanent project with specific scope specified in the special contract terms.

1. 1.3.5 engineering equipment: refers to electromechanical equipment, metal structural equipment, instruments and devices and other similar equipment and devices that form or plan to form a part of the permanent project.

1. 1.3.6 construction equipment: refers to the equipment, appliances and other articles needed to complete all the work agreed in the contract, no.

Including temporary works and materials.

1. 1.3.7 temporary facilities: refers to the production and living facilities temporarily built to complete the work agreed in the contract.

1. 1.3.8 contractor's equipment: refers to the construction equipment brought by the contractor.

1. 1.3.9 construction site (or site): refers to the site used for the construction of the contract project and other sites designated as part of the construction site in the contract, including permanent land occupation and temporary land occupation.

1. 1.3. 10 permanent land occupation: refers to the land that needs to be permanently occupied for the implementation of the contract project as stipulated in the special contract terms. 1.1.3.11Temporary occupation: refers to the land that needs to be temporarily occupied for the implementation of the contract project as stipulated in the special contract terms.

1. 1.4 date

1. 1.4. 1 notice of commencement: refers to the letter that the supervisor notifies the contractor to start construction according to clause11.

1. 1.4.2 Commencement date: refers to the commencement date specified in the commencement notice issued by the supervisor according to clause11.

1. 1.4.3 time limit: refers to the time limit for completing the contract project promised by the contractor in the tender letter, including 1 1.3, 1 1.4,1/kloc-.

1. 1.4.4 completion date: refers to the date when the construction period agreed in 1. 1.4.3 expires. The actual completion date is subject to the date indicated in the project acceptance certificate.

1. 1.4.5 defect liability period: refers to the time limit for performing the defect liability stipulated in clause 19.2, and the specific time limit is stipulated in the special contract terms, including the extension according to clause 19.3.

1. 1.4.6 benchmark date: refers to the date 28 days before the bidding deadline.

1. 1.4.7 days: unless otherwise specified, all refer to calendar days. If the time is calculated in days in the contract, the first day is not counted, and it is counted from the second day. The last day of the deadline is 24:00 on the same day.

1. 1.5 contract price and expenses

1. 1.5. 1 Signing contract price: refers to the total contract amount stated in the contract agreement at the time of signing, including provisional amount and provisional estimate.

1. 1.5.2 contract price: refers to the amount that the employer should pay to the contractor after the contractor completes all the contracting work including the defect liability period as agreed in the contract, including the changes and adjustments that occur during the performance of the contract.

1. 1.5.3 expenses: refers to all reasonable expenses that have occurred or will occur for the performance of the contract, including management fees and other expenses that should be shared, but excluding profits.

1. 1.5.4 Provisional amount refers to the provisional amount listed in the priced bill of quantities, which is used when signing the agreement.

Uncertain or unpredictable change amount of required construction and materials, engineering equipment and services, including daily payment amount.

1. 1.5.5 provisional estimate: refers to the amount given by the employer in the bill of quantities to pay for materials, equipment and professional projects that are bound to happen but whose prices cannot be determined temporarily.

1. 1.5.6 daywork: refers to a pricing method for sporadic work, which is paid according to the daywork subheads and their individual prices in the contract.

1. 1.5.7 quality deposit (or retention money); Refers to the amount agreed in item 17.4. 1, which is used to ensure the performance of the defect repair obligation during the defect liability period.

1. 1.6 others

1. 1.6. 1 written form: refers to the forms such as contract documents, letters, telegrams and faxes that can tangibly express the contents contained.

Type.

1.2 language

Except for the special terms, the language used in this contract is Chinese. When necessary, the special terms shall be accompanied by Chinese notes.

1.3 law

The applicable laws of this contract include laws, administrative regulations and departmental rules of People's Republic of China (PRC), as well as local regulations, autonomous regulations, separate regulations and local government regulations of the project location.

1.4 Priority of contract documents

The documents constituting the contract should explain each other and explain each other. Unless otherwise agreed in the special terms and conditions of the contract, the priority order of interpreting the contract documents is as follows:

(1) Contract Agreement:

(2) Letter of Acceptance:

(3) Letter of Tender and Appendix to Letter of Tender:

(4) Special contract terms:

(5) General contract terms;

(6) Technical standards and requirements:

(7) Drawings:

(8) priced bill of quantities:

(9) Other contract documents.

1.5 Contract Agreement

The contractor shall sign the contract agreement with the employer at the time specified in the letter of acceptance. Unless otherwise provided by law or contract, the contract shall be terminated after the legal representatives of the employer and the contractor or their entrusted agents sign the contract agreement and affix the official seal of the unit.

1.6 drawings and contractor's documents

1.6. 1 Provide drawings.

Unless otherwise agreed in the special terms and conditions of the contract, the drawings shall be provided to the contractor within a reasonable period of time according to the quantity agreed in the contract. If the construction period is delayed due to the Employer's failure to provide the drawings on time, it shall be handled according to the provisions of Clause 1 1.3.

1.6.2 documents provided by the contractor

Documents provided by the contractor as agreed in the special contract terms, including detailed drawings and processing drawings of some projects, shall be submitted by the contractor to the supervisor according to the agreed quantity and time limit. The supervisor shall give a reply within the time limit agreed in the special contract terms.

1.6.3 Drawing modification

If it is necessary to modify and supplement the drawings, the supervisor shall, after obtaining the consent of the Employer, issue the modified drawings to the contractor within a reasonable period before the construction of the project or the corresponding parts of the project, and the specific issuance period shall be agreed in the special contract terms. The contractor shall carry out the construction according to the revised drawings.

1.6.4 drawing error

When the contractor finds obvious errors or omissions in the drawings provided by the Employer, it shall promptly notify the supervisor. 1.6.5 Preservation of drawings and contractor's documents

The supervisor and the contractor shall each keep a complete set of drawings and contractor documents at the construction site, including the contents agreed in 1.6. 1, 1.6.2 and 1.6.3.

1.7 contact person

1.7. 1 Notices, approvals, certificates, instructions, requirements, requests, consents, opinions, decisions and decisions related to this contract shall be in written form.

1.7.21.7.1j pages of notices, approvals, certificates, instructions, requirements, requests, consents, opinions, determinations, decisions, etc. shall be delivered to the designated place and recipients within the time limit stipulated in the contract, and the receipt formalities shall be handled.

1.8 Transfer

Unless otherwise agreed in the contract, a party shall not transfer all or part of its contractual rights or its contractual obligations to a third party without the consent of the other party.

1.9 Bribery is prohibited.

The parties to a contract shall not seek improper benefits or damage the rights and interests of the other party by bribery or disguised bribery. If the other party suffers losses due to bribery, the actor shall compensate for the losses and bear corresponding legal responsibilities.

1. 10 fossils and cultural relics

1. 10. 1 All cultural relics and other relics, fossils, coins or articles with geological research or archaeological value excavated at the construction site belong to the state. Once the above-mentioned cultural relics are found, the contractor shall take effective and reasonable protection measures to prevent any personnel from moving or damaging the above-mentioned articles, and immediately report to the local cultural relics administration department and notify the supervisor. The employer, supervisor and contractor shall take proper protection measures according to the requirements of the cultural relics administrative department, and the increased expenses and/or delayed construction period shall be borne by the employer.

1. 10.2 if the contractor fails to report or conceal the cultural relics in time after discovering them, thus causing the cultural relics to be lost or damaged, it shall compensate for the losses and bear corresponding legal responsibilities.

1. 1 1 patented technology

1.1.1.1When the contractor uses any materials, contractor's equipment, engineering equipment or construction technology, the contractor shall bear the responsibilities arising from the infringement of patent rights or other intellectual property rights, except those arising from the compliance with the design or technical standards and requirements provided by the Employer.

1. 1 1.2 If the contractor adopts patented technology in the bidding documents, the royalty for the use of patented technology shall be included in the tender offer. 1. 1 1.3 The technical secrets and statements of the contractor shall be kept confidential, and the employer and the supervisor shall not disclose them to others for the purpose of the contract.

1. 12 confidentiality of drawings and documents

1. 12. 1 Drawings and documents provided by the Employer shall not be disclosed to others or publicly published and quoted for purposes other than the Contract without the consent of the Employer.

1. 12.2 Without the consent of the contractor, the employer and the supervisor shall not disclose the documents provided by the contractor to others or publicly publish and quote them for purposes other than the contract.

2. Employers' obligations

2. 1 Abide by the law

The employer shall abide by the law in the process of performing the contract, and ensure that the contractor is free from any responsibility caused by the employer's violation of the law.

2.2 issue a commencement notice

The employer shall entrust the supervisor to issue a notice of commencement to the contractor according to the provisions in the first paragraph 1 1. 1.

2.3 provide the construction site

The Employer shall provide the Contractor with relevant information such as the construction site, underground pipelines and underground facilities in the construction site, and guarantee its authenticity, accuracy and completeness.

2.4 Assist the contractor in handling documents and approval documents.

The Employer shall assist the Contractor in handling relevant construction certificates and approval documents stipulated by law.

2.5 organization design disclosure

The Employer shall organize the design unit to make design disclosure to the Contractor according to the contract schedule.

2.6 Pay the contract price

The employer shall pay the contract price to the contractor in time as agreed in the contract.

2.7 organization completion acceptance

The employer shall timely organize the completion acceptance as agreed in the contract.

2.8 Other obligations

The employer shall perform other obligations stipulated in the contract.

3. Supervisors

3. 1 Duties and powers of supervisors

3. 1. 1 The supervisor is entrusted by the employer and enjoys the rights stipulated in the contract. The supervisor needs to obtain the consent of the employer in advance before exercising a right, but if it is not stipulated in the general contract terms, it should be stipulated in the special contract terms.

3. 1.2 Any instruction given by the supervisor shall be deemed to have been approved by the employer, but the supervisor has no right to exempt or change the rights, obligations and responsibilities of the employer and the contractor as agreed.

3. 1.3 The obligations and responsibilities stipulated in the contract shall not be relieved or alleviated by the supervisor's examination or approval of the documents submitted by the contractor, the inspection and inspection of the project, materials and equipment, and the implementation instructions issued by the supervisor.

3.2 Chief Supervision Engineer

The employer shall notify the contractor of the appointment of the chief supervision engineer before issuing the commencement notice. When the chief supervision engineer changes, he shall notify the contractor 14 days before the handover. If the chief supervision engineer leaves the construction site for a short time, he shall designate a representative to perform his duties and notify the contractor.

3.3 supervisor

3.3. 1 The chief supervision engineer may authorize other supervisors to perform one or more supervision tasks assigned by him. The chief supervision engineer shall notify the contractor of the names of the authorized supervisors and their authorized scope. Instructions issued by authorized supervision personnel within the scope of authorization shall be deemed to have been approved by the chief supervision engineer and have the same effect as those issued by the chief supervision engineer. When the chief supervision engineer revokes the authorization, he shall promptly notify the contractor of the decision to revoke the authorization.

3.3.2 If the supervisor fails to put forward negative opinions on any work, project or materials and engineering equipment used by the contractor within the agreed or reasonable time limit, it shall be deemed to have been recognized, but it shall not affect the supervisor's right to refuse the work, project, materials or engineering equipment in the future.

3.3.3 When the contractor has any doubt about the instructions issued by the supervisor authorized by the chief supervision engineer, he may raise a written objection to the chief supervision engineer, who shall confirm, change or cancel it within 48 hours.

3.3.4 Unless otherwise agreed in the special terms and conditions of the contract, the chief supervision engineer shall not authorize or entrust the power specified in Clause 3.5 to other supervisors.

3.4 Supervision's instructions

3.4. 1 The supervisor shall issue instructions to the contractor according to the provisions of Clause 3. 1, and the supervisor's instructions shall be stamped with the site seal authorized by the supervisor and signed by the chief supervision engineer or the supervisor authorized by the chief supervision engineer according to the provisions of Clause 3.3. 1.

3.4.2 The contractor shall abide by and carry out the instructions given by the supervisor in item 3.4. 1. If the instruction constitutes a change, it shall be handled in accordance with Article 15.

3.4.3 In case of emergency, the chief supervision engineer or his authorized supervisor may issue temporary written instructions at the scene, and the contractor shall comply with them. The contractor shall issue a written confirmation letter to the supervisor within 24 hours after receiving the above temporary written instructions. If the supervisor fails to reply within 24 hours after receiving the written confirmation letter, the written confirmation letter shall be regarded as the official instruction of the supervisor.

3.4.4 Unless otherwise agreed in the contract, the contractor only obtains the instructions from the chief supervision engineer or its authorized supervision personnel according to item 3.3. 1.

3.4.5 If the supervisor fails to give instructions, delay instructions or make mistakes as agreed in the contract, which leads to the increase of the contractor's expenses and/or the delay of the construction period, the employer shall be liable for compensation.

3.5 Agree or decide

3.5. 1 When it is stipulated in the contract that the chief supervision engineer shall agree or determine anything according to this clause, the chief supervision engineer shall negotiate with the parties to the contract and try to reach an agreement. Cannot reach an agreement, the chief supervision engineer should carefully study and carefully determine.

3.5.2 The chief supervision engineer shall notify both parties to the contract of the agreed or determined matters, and attach detailed basis. If there is any objection to the determination of the chief supervision engineer, which constitutes a dispute, it shall be handled in accordance with the provisions of Article 24. Before the dispute is settled, both parties shall temporarily implement it according to the decision of the chief supervision engineer. If the decision of the chief supervision engineer is modified according to Article 24, the modified result shall prevail.

4. Contractor

4. 1 General obligations of the contractor

4. 1. 1 Abide by the law

The contractor shall abide by the law in the process of performing the contract, and ensure that the employer is free from any responsibility caused by the contractor's violation of the law.

4. 1.2 Pay taxes according to law

The contractor shall pay taxes according to relevant laws and regulations, and the taxes payable shall be included in the contract price.

4. 1.3 Complete all contracted work.

The contractor shall carry out and complete all the works according to Clause 3.4 and the instructions of the contract and supervisor, and remedy any defects in the works. Unless otherwise agreed in the special terms and conditions of the contract, the contractor shall provide the labor, materials, construction equipment, engineering equipment and other items needed to complete the contract work, and be responsible for the design, construction, operation, maintenance, management and demolition of temporary facilities as agreed in the contract.

4. 1.4 is responsible for the integrity of construction operations and construction methods.

The contractor shall prepare the construction organization design and construction measures plan according to the work content and construction progress requirements agreed in the contract, and be responsible for the integrity, safety and reliability of all construction operations and methods.

4. 1.5 Ensure the safety of engineering construction and personnel.

The Contractor shall take construction safety measures as agreed in Clause 9.2 to ensure the safety of the project and its personnel, materials, equipment and facilities, and prevent personal injury and property loss caused by the project construction.

4. 1.6 is responsible for the protection of the construction site and its surrounding environment and ecology.

The contractor shall be responsible for protecting the environment and ecology around the construction site according to Article 9.4.

4. 1.7 Avoid the damage of construction to the public and others' interests.

The Contractor shall not infringe upon the right of the Employer to use public facilities such as public roads, water sources and municipal pipe networks. , and avoid disturbing the nearby public facilities. If the contractor occupies or uses other people's construction sites, which affects other people's work or life, it shall bear corresponding responsibilities.

4. 1.8 Provide convenience for others

The contractor shall, according to the supervisor's instructions, provide possible conditions for others to carry out other work related to the project at or near the construction site. Unless otherwise agreed in the contract, the contents of providing relevant conditions and possible expenses shall be agreed or determined by the supervisor according to Clause 3.5.

4. 1.9 Maintenance and maintenance of the project

The contractor shall be responsible for the care and maintenance of the project before the project acceptance certificate is issued. If there are some unfinished projects when the project acceptance certificate is issued, the contractor shall also be responsible for taking care of and maintaining these unfinished projects until they are handed over to the employer after completion.

4. 1. 10 Other obligations

The contractor shall perform other obligations stipulated in the contract.

4.2 Performance guarantee

The contractor shall ensure that its performance bond is valid before the owner issues the project acceptance certificate. The Employer shall return the performance guarantee to the Contractor within 28 days after the project acceptance certificate is issued.

4.3 subcontracting

4.3. 1 The contractor shall not subcontract all contracted projects to a third party, or dismember all contracted projects and subcontract them to a third party in the name of subcontracting.

4.3.2 The contractor shall not subcontract the main body and key work of the project to a third party. Unless otherwise agreed in the special terms and conditions of the contract, the contractor shall not subcontract other parts or work of the project to a third party without the consent of the Employer.

4.3.3 The qualifications and abilities of subcontractors shall be suitable for the standards and scale of subcontracted projects.

4.3.4 If the project is subcontracted according to the provisions in the appendix to the tender letter, the contractor shall submit a copy of the subcontract to the employer and the supervisor. 4.3.5 The Contractor and the Subcontractor shall be jointly and severally liable to the Employer for the subcontracted project.

4.4 Consortium

4.4. 1 The parties to the consortium shall sign a contract agreement with the owner. The parties to the consortium shall be jointly and severally liable for the performance of the contract.

4.4.2 The consortium agreement shall be confirmed by the owner as an annex to the contract. During the performance of the contract, the consortium agreement shall not be modified without the consent of the Employer.

4.4.3 The leader of the consortium is responsible for contacting the owner and the supervisor, receiving instructions and organizing all members of the consortium to fully perform the contract.

4.5 Contractor Project Manager

4.5. 1 The contractor shall appoint a project manager according to the contract and be on duty within the agreed time limit. The contractor shall obtain the consent of the employer in advance when changing the project manager, and notify the employer and supervisor 14 days before the change. If the contractor's project manager leaves the construction site for a short period of time, he shall obtain the consent of the supervisor in advance and appoint a representative to perform his duties.

4.5.2 The project manager of the contractor shall be responsible for organizing the implementation of the contract project according to the contract and the instructions issued by the supervisor according to Clause 3.4. In case of emergency, when it is impossible to get in touch with the supervisor, measures can be taken to ensure the safety of life and property of the project and personnel.

Emergency measures, and submit a written report to the supervisor within 24 hours after taking measures.

4.5.3 All letters sent by the contractor to perform the contract shall be stamped with the seal of the construction site management organization authorized by the contractor and signed by the contractor's project manager or his authorized representative.

4.5.4 The project manager of the contractor may authorize his subordinates to perform one of their duties, but shall notify the supervisor of the names and scope of authorization of these personnel in advance.

4.6 Management of Contractor's Personnel

4.6. 1 The contractor shall, within 28 days after receiving the notice of commencement, submit to the supervisor a report on the management organization and personnel arrangement of the contractor at the construction site, including the setting of the management organization, the list of technical and management personnel of each main post and their qualifications, as well as the arrangement of skilled workers of each type of work. The contractor shall submit to the supervisor a report on personnel changes at the construction site.

4.6.2 In order to complete all the work agreed in the contract, the contractor shall send or employ a sufficient number of the following personnel to the construction site:

(1) Professional and technical personnel and qualified general workers with corresponding qualifications:

(2) Technical personnel with corresponding construction experience;

(3) Managers at all levels with corresponding post qualifications.

4.6.3 The main management personnel and technical backbones arranged by the contractor at the construction site should be relatively stable. The contractor shall obtain the consent of the supervisor when replacing the main management personnel and technical backbone.

4.6.4 Special post personnel shall hold corresponding qualification certificates, and supervisors shall have the right to check at any time. When the supervisor thinks it is necessary, he can conduct on-site evaluation.

4.7 Replace the project manager and other personnel of the contractor

The contractor shall effectively manage its project manager and other personnel. If the supervisor requests to replace the incompetent, misbehaving or dereliction of duty project manager and other personnel of the contractor, the contractor shall replace them.

4.8 protect the legitimate rights and interests of the contractor's personnel

4.8. 1 The contractor shall sign labor contracts with its employees and pay wages on time.

4.8.2 The contractor shall arrange the working hours according to the provisions of the labor law, and ensure that its employees enjoy the right to rest and vacation. Those who occupy holidays or extend working hours due to the special needs of engineering construction shall not exceed the limit prescribed by law, and shall be given compensatory time off or paid wages according to law.

4.8.3 The contractor shall provide its employees with necessary accommodation conditions and a living environment that meets the requirements of environmental protection and hygiene. In the construction site far away from the town, necessary medical personnel and facilities should also be provided for injury prevention and first aid.

4.8.4 The contractor shall take effective labor protection measures according to the relevant national labor protection regulations, such as dust prevention, noise reduction and control of harmful gases to ensure the safety of high temperature, cold and aerial work. If its employees are injured in the construction, the contractor shall immediately take effective measures for rescue and treatment.

4.8.5 The contractor shall provide insurance for its employees according to relevant laws and contract provisions.

4.8.6 The contractor shall be responsible for dealing with the aftermath of work-related casualties of its employees.

4.9 The project price shall be earmarked.

According to the contract, all the money paid by the employer to the contractor shall be used exclusively for the contract project.

4. 10 contractor site survey

4. 10. 1 The employer shall provide the contractor with the on-site geological exploration data and hydrometeorological data it has, and shall be responsible for their accuracy. However, the contractor shall be responsible for the explanations and inferences made after reading the above-mentioned relevant materials.

4. 10.2 The contractor shall investigate the construction site and the surrounding environment, and collect relevant local data such as geology, hydrology, meteorological conditions, traffic conditions, customs and habits required to complete the contract work. In all contract work, it shall be deemed that the contractor has fully estimated its responsibilities and risks.

4. 1 1 unfavorable material conditions

4. 1 1. 1 Adverse material conditions refer to unforeseeable natural material conditions, unnatural material obstacles and pollutants encountered by the contractor at the construction site, including underground and hydrological conditions, but excluding climatic conditions, unless otherwise agreed in the special contract terms.

4. 1 1.2 When the contractor encounters unfavorable material conditions, it shall take reasonable measures to adapt to the unfavorable material conditions and continue the construction and notify the supervisor in time. The supervisor shall give instructions in time, indicating that if it constitutes a change, it shall be handled according to 15. If the supervisor fails to give instructions, the Employer shall bear the increased expenses and/or delays due to the reasonable measures taken by the Contractor.

5. Materials and engineering equipment

5. 1 Materials and engineering equipment provided by the contractor

5. 1. 1 Unless otherwise agreed in the special contract terms, the contractor shall be responsible for purchasing, transporting and keeping the materials and engineering equipment provided by the contractor. The contractor shall be responsible for the materials and engineering equipment it purchases.

5. 1.2 The contractor shall submit the supplier, variety, specification, quantity and delivery time of various materials and engineering equipment to the supervisor for approval according to the special contract. The contractor shall submit to the supervisor the quality certification documents of the materials and engineering equipment it is responsible for providing, and meet the quality standards agreed in the contract.

5. 1.3 For the materials and engineering equipment provided by the contractor, the contractor shall conduct inspection and delivery acceptance together with the supervisor, check the material certificate and product certificate, and conduct sampling inspection of materials and inspection and test of engineering equipment according to the contract and the supervisor's instructions. The inspection and test results shall be submitted to the supervisor, and the required expenses shall be borne by the contractor.

5.2 Materials and engineering equipment provided by the Employer

5.2. 1 For the materials and engineering equipment provided by the Employer, the name, specification, quantity, price, delivery method, delivery place and planned delivery date of the materials and engineering equipment shall be stipulated in the special contract terms.

5.2.2 The Contractor shall, according to the arrangement of the contract progress plan, submit the date plan requiring the Employer to deliver the goods to the Supervisor.

The employer shall submit materials and engineering equipment to the contractor according to the delivery date agreed by the supervisor and the contract parties.

5.2.3 The Employer shall notify the Contractor 7 days before the arrival of materials and engineering equipment, and the Contractor shall, together with the supervisor, go to the delivery place for acceptance within the agreed time. Unless otherwise agreed in the special terms and conditions of the contract, the contractor shall be responsible for receiving, transporting and keeping the materials and engineering equipment provided by the Employer after acceptance.

5.2.4 The Contractor shall not refuse the request of the Employer to deliver the goods to the Contractor in advance, but the Employer shall bear the responsibilities of the Contractor.

This increases the cost.

5.2.5 When the contractor requests to change the delivery date or place, it shall report to the supervisor for approval in advance. Due to the contractor's request to change the delivery time or place, the increased expenses and/or construction delay shall be borne by the contractor.

5.2.6 If the specifications, quantity or quality of materials and engineering equipment provided by the Employer do not meet the contract requirements, or the delivery date is delayed or the delivery place is changed due to the Employer's reasons, the Employer shall bear the increased expenses and/or delay in construction period, and pay reasonable profits to the Contractor.

5.3 Materials and engineering equipment are dedicated to the contract project.

5.3. 1 Materials and engineering equipment brought into the construction site, including spare parts, special installation instruments and random data, must be dedicated to the contract project. Without the consent of the supervisor, the contractor shall not transport it out of the construction site or use it for other purposes.

5.3.2 Spare parts, special instruments and random data brought into the construction site with engineering equipment shall be counted according to the supplier's packing list and stamped with the supervisor, and shall not be used without the supervisor's consent. When the contractor needs to use the above items for contract work, he shall apply to the supervisor.

Hope to adopt