What are the main processes of completion acceptance?

1. The construction, survey, design, construction and supervision units respectively report the performance of the project contract and the implementation of laws, regulations and mandatory standards in all aspects of the project construction.

2, review the construction, survey, design, construction and supervision units of the project files.

3, on-site inspection of engineering quality.

4. Comprehensively evaluate the quality of engineering survey, design, construction, equipment installation and various management links, and form the project completion acceptance opinions signed by experienced personnel.

What is the main basis for the completion and acceptance of construction projects?

1, various documents approved by the higher authorities for this project.

2. Feasibility study report.

3, construction drawing design documents and design change negotiation records.

4. Various national standards and current construction acceptance specifications.

5, engineering contract documents.

6, technical equipment specifications.

7. The unified provisions of the construction and installation project and the provisions of the competent department on the completion of the project.

8. Projects of new technologies and complete sets of equipment imported from abroad, as well as Sino-foreign joint venture construction projects, shall be accepted according to the contracts and design documents provided by the importing countries.

9, the use of the World Bank and other international financial institutions loans for construction projects, should be in accordance with the provisions of the World Bank, timely preparation of the "project completion report".

What conditions should be met for the completion and acceptance of construction projects?

1. Complete the design of the construction project and the contents agreed in the contract.

2, a complete technical files and construction management information.

3. Main building materials, building components and equipment used in the project.

4. There are quality documents signed by survey, design, construction and project supervision units.

5. There is a project warranty signed by the construction unit. The construction project can not be delivered until it has passed the acceptance. The construction unit shall, in strict accordance with the relevant provisions of the state on archives management, collect and sort out the documents of all aspects of the construction project in time, establish and improve the archives of the construction project, and hand over the archives of the construction project to the construction administrative department or other relevant departments in time after the completion and acceptance of the construction project.