The emergency response plan should form a complete document system. Usually a complete enterprise-level emergency plan consists of four parts: the general plan, procedural documents, guidance instructions and records. Below I bring you the 2022 storm flood control response program, I hope you like it!
2022 rainstorm flood control response program 1
1, purpose
To cope with the possible occurrence of special natural disasters, to ensure that the normal urban sewage treatment, to protect the company's property and the safety of personnel.
2, the scope of application
This program applies to the control process of sewage treatment during heavy rainfall and flooding.
3, responsibilities
In order to strengthen the leadership of the flood emergency response, the establishment of the plant flood emergency response leading group.
4, flood duty
According to the release of rainstorms, flood warning level, the arrangement of different administrative duty system, the relevant departments to arrange for emergency repair personnel, flood control, flood preparedness, unexcused absence will be held accountable for the relevant personnel. Flood emergency work leading group need to do a good job of logistical support according to different duty arrangements.
Flood control, flood prevention period to ensure smooth flow of information, the relevant leaders and responsible persons must keep their cell phones on 24 hours.
The specific duty arrangements during the flood prevention and control period are as follows:
When the blue warning, the duty is carried out according to the normal management system of the plant;
When the yellow warning is in effect, in addition to the normal duty personnel on rest days and at night, a person from the process laboratory department is guaranteed to be on duty;
When the orange warning is in effect, in addition to the normal duty personnel on rest days and at night, one person from each of the operation and mechanic maintenance is guaranteed to be on duty. On duty, flood control, flood control team in place;
red warning, flood emergency team all members of the site on duty, flood control, flood control team in place.
5, management regulations
5.1 Preparation stage
5.1.1 pump room in the flood season to ensure that the pumps are intact, so that the water level of the catchment wells to maintain a low water level operation.
5.1.2 Heavy rains, flood season before the arrival of repair personnel should be all repair equipment overhaul and maintenance, so that it is in good. Standby state.
5.1.3 Before the arrival of heavy rainfall and flooding, the department using the equipment shall inspect the wastewater treatment facilities under the jurisdiction of the department to determine that they are in good condition and have inspection records available.
5.1.4 should be through the weather station forecast to understand the trend of weather changes in a timely manner, in accordance with the requirements of the higher level in a timely manner to implement a good flood prevention and flood control programs.
5.1.5 Before the arrival of rainstorms and floods, all departments should close the doors and windows, and check whether there are any safety hazards in the indoor hangings and fixtures.
5.1.6 In accordance with the principle of hierarchical responsibility, reserve the necessary flood control and disaster prevention materials, and reasonably allocate them. In the flood control, flood control key areas to reserve a certain amount of emergency materials, in order to meet urgent needs.
5.1.7 communication preparedness, make full use of the plant's internal telephone network and social communication network, to ensure that the flood control, flood control communication system is intact and smooth, timely transmission of command and scheduling instructions.
5.2 process control
5.2.1 When the flood water volume, high water level in the collection wells open all the pumps running.
5.2.2 Process laboratory department according to the actual situation, adjust the flood season process operation program; flood season timely adjustment of the operating conditions, in the case of large water volume, fresh water intake quality, to ensure that the total effluent discharge, try to deal with the sewage water volume, reduce the discharge to the outside.
5.2.3 operation class in the flood season to strengthen the inlet and outlet pumps, reaction pool inlet and outlet gates and power substations and other key equipment and parts of the inspection and monitoring, make a good record of the operating conditions of the equipment; found faults and other abnormalities in a timely manner to report to the department of equipment or to notify the leading group of the flood control. Strengthen the site inspection, especially structures, in order to prevent high wind weather falling objects.
5.2.4 Mechanical repair class in the flood season before the arrangement of production and operation of key equipment and substation inspection, maintenance work and do a good job of outdoor equipment rain work. And timely inspection of the plant machinery and equipment grounding, timely rectification of facilities with potential safety hazards.
5.2.5 According to the weather forecast, the organization of the operation of the workers in advance of the inspection of the equipment to ensure that intact, the organization of forces on the plant rainwater pipeline dredging, to ensure smooth; timely and effective release of early warning information.
5.2.6 In case of sudden rainfall, each post will close the doors and windows tightly to prevent the inflow of rainwater, affecting the operation of equipment. Production and operation team to increase the number of pumps, reduce the water level of the collection wells, until the full load for it. Outside patrol, must be a group of two people, pay attention to anti-skid. Transformer duty personnel in a timely manner to check whether the lightning play a role; plant repair team members, vehicles to do on-call, standby, in order to dispose of the occurrence of unexpected accidents.
5.2.7 If the instantaneous flow is too high to make all the structures in overloaded operation, should immediately get in touch with the higher authorities, the higher authorities agreed to open the primary sedimentation tank beyond the valve of the emergency discharge of sewage, in order to ensure that the whole plant structure operation, process production and operation of normal.
5.3 Emergencies
5.3.1 When the power interruption process can not run normally, the duty officer should immediately report to the relevant leadership, and hold on to their positions, waiting for the instructions of the leadership.
5.3.2 When rainstorms, floods cause property damage and casualties, the duty officer should immediately report to the relevant leadership, and within the scope of the ability to carry out the relevant rescue work.
5.4 Flood control and prevention of late
5.4.1 After heavy rainfall, flooding, laboratory positions should increase the frequency of inlet and outlet water quality testing.
5.4.2 Repair the equipment and facilities damage caused by heavy rainfall and flooding, and ensure the normal operation of all equipment;
6, rescue and relief
After the occurrence of a major danger, the leading group of flood emergency response work should be based on the nature of the event, rapid monitoring and tracking of the event, and immediately contact with the relevant departments.
Flood emergency response work leading group should be based on the specifics of the incident, in accordance with the program immediately put forward emergency disposal program for the company or the relevant departments at the upper level or the local government command decision-making.
The leading group of flood emergency response work should quickly mobilize the resources and strength of the department to provide technical support; organization of flood control, anti-thunderstorm and wind personnel to quickly carry out on-site disposal or rescue work.
Disposal of major hazards, should be unified command, functional division of labor, each in its own way, unity and cooperation, rapid response, efficient disposal, minimize losses.
7, safety protection and medical care
The leading group of flood emergency response should attach great importance to the safety of emergency personnel, mobilize and reserve the necessary protective equipment, disinfectant drugs, standby power supply and rescue of the injured necessary instruments, etc., in order to prepare for the application of any time.
Emergency personnel to enter and withdraw from the scene by the leading group of flood emergency response to make a decision as the case may be. Emergency personnel to enter the threatened scene before, should take protective programs to ensure their own safety.
The leading group of flood emergency response should issue timely notices in accordance with the instructions of the local government and higher leading organizations to prevent people and animals from entering the danger zone.
8, the mobilization of social forces and participation
After the disaster, the flood emergency leading group can be based on the nature of the incident and the degree of harm, reported to the local government for approval, the key areas and key parts of the implementation of emergency control, to prevent the state of affairs and its harm to the further expansion; if necessary, through the local people's government to mobilize social forces to participate actively in the emergency response to emergencies.
9, the end of the emergency
When the disaster is effectively controlled, the leading group of flood emergency response can be declared the end of emergency response depending on the actual situation.
In accordance with the provisions of the relevant emergency response period requisition, call for materials, equipment, transportation tools, etc., should be returned to its original position in a timely manner after the end of the emergency. After the end of the emergency disposal work, should be promptly restored to normal life, production, work order, repair of water-damaged infrastructure, minimize the losses and impact of the emergency.
2022 Rainstorm Flood Control Response Program 2
Defense against severe weather is the focus of the school's safety work, in order to effectively protect our school in the prevention of rainstorms, hailstorms, lightning and other weather during the life and property safety of teachers and students, to ensure that the ideology that is in place, preventive programs in place, the responsibility for the implementation of the arrival of rainstorms, hailstorms and lightning in place. Possible losses caused by rainstorms, hail, thunder and lightning to a minimum, according to the town of Si channel education management secondary school requirements, combined with the reality of my school, specially formulated this program.
First, the scope of application of this program
rainstorms, hail, thunder and lightning and other kinds of abnormal weather
Second, the work objectives
attention to the weather forecast, in the prediction to the impact of the town of rainstorms, hail, thunder and lightning before the arrival of the combination of the higher level of the requirements of the implementation of effective preventive programs to ensure the safety of personnel as the first goal, to the rainstorms, hail, thunder and lightning to come The possible losses caused by rainstorms, hail, thunder and lightning to a minimum.
Third, the organization
The establishment of the defense against severe weather leading group leader:
Deputy leader:
Members:
Fourth, the defense against severe weather during the work arrangements and programs
(a), the pre-checking of the work
1, the head of the school committees should be regularly organizing the staff will be in charge of the work of strict and meticulous inspection, leaving no dead ends. Meticulous inspection, leaving no dead ends, found that the problem is repaired in a timely manner. Each class should do a good job of classroom inspection every day, timely understanding of the living conditions of students' families especially those living in remote areas, and keep in touch with parents to educate students to raise awareness of disaster prevention.
2, the school office phone, school committee members phone, classroom teacher phone to ensure smooth; Logistics Department to comprehensively check the school electricity facilities and lines, to ensure the safety of electricity;
Teaching Office to organize professional staff of the school building, comprehensive building, such as the doors, windows and buildings on the hanging objects such as inspections, found that the hidden problems in a timely manner to exclude; the Mission to the whole school sewers, open and dark ditches and Flat roof sludge debris dredging and cleaning to ensure smooth drainage;
Teachers should check their own dormitory doors and windows hangings, found hidden trouble in a timely manner; hostesses should check students' dormitory doors and windows hangings, found hidden trouble in a timely manner; Mr. An Xiangyang to the cafeteria's doors and windows hangings, found hidden trouble in a timely manner; security personnel should check the door and the guard room of the school. The guards should check the door and windows of the janitor's office to find hidden dangers and eliminate them in time; the political education department should check the school wall and easy to landslide sections to supervise.
3, the class once encountered dangerous situations, to be organized and quickly in accordance with the escape drill route withdrawn to the safety zone. Regularly in the class of students to carry out defense of bad weather education, enhance everyone's awareness of prevention and self-help self-care ability.
4, in order to prevent torrential rain, hail, thunder and lightning to the pro, all teachers are defending against severe weather disaster relief and rescue team members, ready to stand by, waiting for dispatch, ready to deal with emergencies.
(ii), duty, reporting system
The duty room and patrol group, in the rainstorms, hail, thunder and lightning to come must ensure that twenty-four hours a day duty personnel on duty. School leaders, duty personnel to ensure smooth communication, communication tools to remain open state.
When the disaster occurs, school leaders, patrols and duty officers should grasp the situation in a timely manner, in the shortest possible time to the higher authorities to reflect the details, and the damage to the loss of all the circumstances reported truthfully.
(C), logistical support work
In the heavy rain, hail, thunder and lightning before the arrival of all kinds of items to do a good job of reserve work. Spare rain gear, torches and other urgently needed items to provide logistical support. And establish contact information with the Siqiu Town Health Center, safety supervision departments and other units to ensure timely rescue.
V. Emergency disposal action
1, in this rainstorm, hail, thunder and lightning before the arrival of the school janitorial office, hostel management began to implement a 24-hour duty system, all members of the leading group of cell phones on 24 hours a day, pay close attention to rainstorms, hail, thunder and lightning movements. Doors and windows in the school, canopies, facilities, wires and electrical equipment, schools in construction sites and other hazardous areas of the facilities to check and eliminate dangerous situations, the possibility of accidents on the facilities, to be reinforced reinforcement, the removal of the demolition.
2, heavy rain, hail, thunder and lightning once the arrival, immediately stop all outdoor activities in the school.
3, in the rainstorm, hail, thunder and lightning, the organization is in a dangerous environment in the emergency transfer of students, and pay attention to the safety of the items outside the classroom into the classroom, and close all the doors and windows of the school. Prevent electrical wires from scraping off and causing short circuits that can cause fires or electrical injuries to those inside. Also prevent from being struck by lightning and other accidents.
4, heavy rain, hail, thunder and lightning, all the people in the school shall not go out to avoid accidents.
5, heavy rain, hail, thunder and lightning, should be timely rescue of the injured, the school is fully engaged in disaster self-help work, and timely report to the higher authorities of the disaster. Ensure that the school normal teaching order.
6, subject teachers in the rainstorm, hail, thunder and lightning, to organize the emergency transfer of students in dangerous environments, and pay attention to safety, and close all the doors and windows of the classroom. Prevent electrical wires from breaking, causing short circuits that can lead to fires or electrical injuries to people inside the room. At the same time also to prevent lightning strikes and other accidents, in time to the end of the class time to delay the end of the class to ensure the safety of students.
Responding to severe weather is a comprehensive and arduous task, all relevant personnel must cooperate with each other, support each other, and strive to do their jobs. A check on the scope of duties work, ready to wait for the defense of severe weather leading group's dispatch, on call, *** with the efforts, collaborative, really do a good job of disaster relief.
2022 rainstorm flood control response program 3
I. Purpose
To establish and improve the property management in the sudden public **** events in the early warning and emergency response system, to ensure that the property company in the event of major floods can be efficient and orderly flood rescue and relief work, according to the requirements of the competent authorities and the leadership of the company. In order to put the rescue and relief work into practice, to ensure the safety of this year's flood, combined with the actual situation of our company, the development of this plan.
Second, the guiding ideology
Conscientiously implement the national, municipal and county flood control work conference, active defense against flooding, in order to build a harmonious society, the implementation of the "safety first, prevention-oriented, unremitting, all-out rescue" approach; unified leadership, careful deployment, coordinated action, hierarchical management, clear division of labor, scientific scheduling and management of the work.
Third, the main tasks
1, the implementation of accountability. Conscientiously implement the project manager responsibility system as the main content of the flood prevention and flood control responsibility system, improve the rules and regulations, clear work responsibilities, responsibility to implement.
2, the organization to develop and implement emergency plans for flood control. Combined with the actual situation of each department, each project, fully foresee the problems that may occur, scientific and reasonable development of flood control, flood control work emergency plan.
3, each department, each project to the implementation of flood control materials in place, to achieve adequate flood control materials, to do point, location, by the person responsible for the management.
4, the projects to do 24-hour duty, and a leader on duty, the implementation of the project manager responsibility system. Ensure the smooth flow of information, and properly respond to emergencies.
Fourth, the leadership of the command and rescue and relief agencies
1, the establishment of the flood control team
Commander:
Deputy Commander:
Members:
2, the establishment of the company's flood control and flood rescue team
The projects themselves to form a rescue team, the captain of the project manager (or the order of the head of maintenance) respectively. As.
Fifth, the main responsibilities
1, the leading group of flood control responsibilities
(1) quickly receive and convey the flood control department and the higher leadership on the flood control and flood relief instructions.
(2) deployment and command implementation of flood control and flood relief operations. The emergence of dangerous situations, the rescue commando by the flood control work leading group command.
(3) grasp the basic situation of each unit of flood control and flood prevention work, understand the flood situation and timely report.
(4) the implementation of other tasks assigned by the superiors.
2, flood rescue commando duties
(1) receive and report flood relief.
(2) directly involved in flood control and disaster relief operations.
(3) Coordinate the resettlement and transit of affected households.
(4) Perform other tasks assigned by the company's leading group of flood control work.
Sixth, the preparatory work (each project in conjunction with the actual situation with reference to the implementation)
1, in advance to check and dredge the ground and roof drains, clean up septic tanks and sewage wells, check the drainage main and municipal pipe network interface, to ensure that unimpeded.
2, check the sewage pump, to ensure that important locations (generator room, pump room, power distribution room) and other locations of the sewage pump can run automatically.
3, overhaul standby generators and control lines to ensure that the emergency power supply is safe and reliable.
4, check the integrity of the flashlight, check the equipment room emergency lighting.
5, check the cell lightning protection system.
6, check the facade, notify residents, organize balconies, roof gardens, clean up overhead shelving, canopies.
7, pruning large trees in the neighborhood with dead branches, insect pests serious branches.
8, determine the evacuation route and location of emergency vehicles and personnel.
9, the project fixed people, regularly watching the local weather forecast every day, and will report important information to the project leader in a timely manner.
7, the project focus on location and equipment and facilities (each project in conjunction with the actual situation with reference to the implementation)
1, the equipment room, and below the level of the community elevation of the equipment and facilities to focus on monitoring (basement, elevator shaft).
2, office computers and monitoring host, road gate equipment and other public **** electricity equipment.
Eight, material preparations (each project in conjunction with the actual situation with reference to the implementation)
1, the preparation of spare pumps, buckets, brooms, towels.
2, prepare the necessary rain gear such as umbrellas, rain shoes, raincoats.
3, emergency lighting such as: flashlights, emergency lights.
4, emergency communications such as: walkie-talkies.
5, medical care: tourniquet, anti-inflammatory drugs, iodine, band-aid.
6, rescue tools and materials such as safety belts, safety ropes, shovels.
7, prepare the necessary funds.
8, emergency protection vehicles.
Nine, the emergence of flood emergency measures
1, ordinary flood emergency
(1) to strengthen communication with the county flood control department, strengthen the flood monitoring and forecasting.
(2) According to the actual situation of our units, flood control requirements for each department and project, and organized evacuation of households.
(3) Take measures to guarantee the smooth contact of the flood control system.
(4) Supervise the preparations for rescue and relief work and check the implementation.
(5) Based on the flood control department's judgment of the trend of flood conditions, strengthen the publicity and education on flood control to households, quell rumors, stabilize people's minds, and maintain normal production and living order.
2, major flood emergency
(1) After receiving the notice of major flood emergency from the higher authorities, the flood relief team of each project involved in the flood situation will concentrate quickly and put into the flood control and rescue work.
(2) Organize forces to do a good job of evacuation and resettlement of households, and take favorable measures to try to protect the basic living conditions of households.
(3) Organize the relevant personnel to maintain public **** order, to prevent people from taking advantage of the opportunity to make trouble.
(4) Understand the disaster, do a good job of publicity, quell rumors and misinformation, and maintain social stability.
Specific emergency measures refer to the above process, combined with the actual situation of the project, in accordance with the project's flood emergency work program implementation.
X. Information summary and report
Project flood control headquarters according to their respective division of labor, is responsible for the collection, collation and study of the jurisdiction may occur flood control information analysis and summary, in accordance with the principle of early discovery, early reporting, early disposal, and quickly report the situation to the company's competent leadership. For all kinds of flood control emergencies and may lead to a variety of hidden dangers, any individual has the right and obligation to report to the company's office, and the right to the relevant departments of the work of negligence and mishandling of the behavior of the report, flood control information reporting and processing follow the principles of:
1, the important information is reported immediately, due to objective reasons it is difficult to accurately grasp the information, it should be reported in a timely manner to report on the basic situation, and at the same time Grasp the situation, and then make up the details of the report.
2, general information according to sub-project management authority, reported to the person in charge of flood control projects.
3, the company's flood control work group received a major flood, industrial, risk, disaster report, should be reported immediately.
XI, other
When faced with a major, emergency, emergencies or involving the normal work of the residents, business, life order, with the customer service center of the project near the verbal notification of the customer, and do a good job of customer appeasement and explanation of the work.
2022 rainstorm flood response program 4
According to the actual situation of the hotel, the 20__ rainy season flood control work specially formulated this plan:
First, the general objective of flood control work:
In accordance with the "safety first, unremitting, prevention-oriented, all-out rescue" work policy. In accordance with the "safety first, unremitting, prevention-oriented, all-out rescue" approach to the work, the effective implementation of the flood control system of responsibility, to achieve the responsibility in place, command in place, personnel in place, materials in place, measures in place, rescue in a timely manner, to ensure that the hotel personnel and property safety, the hotel's work is normal.
Second, the principle of work
The hotel flood rescue work, the implementation of "unified management, unified coordination, unified deployment, rapid response, scientific response, graded implementation" principle.
Third, the organization and responsibilities
1, the hotel set up a leading group of flood control and rescue work:
Leader:
Responsibilities: Responsible for the overall work of flood control and rescue, responsible for the issuance of the hotel's flood control plan to start the instructions.
Deputy leader
Responsibilities: responsible for the implementation of the hotel plan, responsible for the hotel flood control organization and coordination of the command work.
Members:
Responsibilities: with the deputy head of the flood control and rescue work in various departments
Disaster relief and rescue team, supply team:
Disaster relief and rescue team:
Captain: Zhang effect Qi
Vice Captain: Li Hongsheng
Team:
Supply team
Captain:
The team:
2, the hotel flood telephone to implement twenty-four small duty system:
Duty phone:
Duty personnel work: according to the manager of the month duty list sort of implementation
Fourth, the hotel basement disaster relief and rescue personnel evacuation plan.
(1) during the flood season, each unit to strengthen the duty patrol, duty personnel must adhere to their posts, due diligence, to maintain twenty-four-hour communication, there is heavy rain above the weather, the basement into the water and other dangerous situations, must be immediately reported to the hotel flood control and rescue headquarters, and the organization of disaster relief and rescue team rescue and rescue.
(2) The rescue team must be ready to participate in the flood control and rescue work.
(3) basement water leakage, and there is an expansion of the momentum, must be immediately evacuated from the staff quarters, the evacuation channel from the staff restaurant door stairway straight to the second and third floor of the sprinkler, the evacuation channel key by the staff meal Xu director and duty manager respectively, start the hotel evacuation plan, should be in the first time by the duty manager to open the evacuation channel, to ensure that the staff safely evacuated the disaster area.
(4) The duty manager must do a good job of security evacuation channel key strict management as well as careful handover.
(5) the evacuation of employees, should be based on the principle of women first, the duty manager to ensure the safety of the evacuation of order, there shall be no confusion; male employees to ensure personal safety, ready to volunteer to assist in the rescue.
(6) The hotel should organize no less than one flood drill
V. Other issues that should be noted
(1) to ensure that the staff's living housing does not leak, no water.
(2) Pay special attention to environmental hygiene, adhere to the daily fly disinfection work.
(3) Do a good job of preventing heatstroke and cooling the distribution of medicines, reasonable arrangements for self-time, to ensure that no epidemic, food poisoning, heat stroke phenomenon.
(4) The hotel flood emergency plan according to the requirements of the higher-ups in a timely manner to supplement the revised.
2022 rainstorm flood control response plan 5
I. Organizational structure and responsibilities
The hotel set up a flood and typhoon emergency response headquarters, the typhoon came to the command of the various organizations members of the command must immediately do a good job in the hotel to respond to the flood and typhoon prevention and duty work. Organization is as follows:
Commander-in-chief:
Deputy Commander-in-chief:
Members:
Second, the typhoon procedures
(a) the typhoon before the self-inspection preparations
1, the front office department: the collection of banners at the main entrance and the main entrance of the lantern and other decorations and the POP notice boards; lobby or elevator entrance to the placement of typhoon information notice boards, and Prepare a typhoon reminder card to the guest room department with the room; prepare umbrellas and rain gear, every employee of the front office should be aware of the typhoon information, timely answers to guests' inquiries, ready to emergency lighting at the front desk, the lobby assistant should be scheduled in the lobby, to do a good job in the customer's inquiries and pay attention to the doorway and the lobby of the situation reported in a timely manner, to ensure that the front office of the normal order of business.
2, Rooms, Food and Beverage Department, Finance Department: check the closure of each room, box, aisle and hallway doors and windows; do a good job on the guest of the typhoon prevention notification Rooms Department should be the typhoon reminder card with the room; prepare emergency lighting;
3, switchboard: responsible for understanding the typhoon situation in a timely manner to report to the leadership of the hotel and the relevant departments responsible for the preparations for the emergency lighting, walkie-talkie, and check the switchboard Backup power supply is normal operation, and under the guidance of the department manager to do a good job in the power outage emergency services, and do a good job of the guest's inquiry service.
4, each department should be prepared 1 day in advance to report the loss of fabrics, in order to emergency use.
5, by the Engineering Department of the hotel perimeter, platforms, neon lights, billboards, satellite receivers, business departments and tenants of the doors and windows of a comprehensive inspection with wire, rope, stakes and other reinforcement of the unsound suspension should be temporarily removed. Check the underground electric room engine room and other important parts, do a good job of reinforcing the hotel door, and cut off the possibility of short-circuit triggered a fire in the circuit, the pool should be filled with water to ensure that the hotel's normal supply of water, electricity, gas, ready to prepare enough sandbags.
6, the general office is responsible for the typhoon information conveyed to all employees in all departments, the arrangement of all department heads to stay on duty.
7, the security department notified the dormitory security guards to prepare for duty, and with the engineering department to check the hotel periphery, roof and other key parts of the sewers, guttering is smooth, prepare lighting appliances and rain shoes and raincoats, safety helmets, flashlights, emergency lights, and so on.
(ii) review: by the General Office, Engineering Department, the head of the Security Department in accordance with the above terms of the preparation of each department to review.
(C) the wind is strong when the emergency procedures should be initiated:
1, the security department, the head of the engineering department should remain in the hotel at any time to deal with unexpected danger, to ensure that enough manpower and material resources to do a good job of repair and remedial work.
2, guest rooms, private rooms, cloth, liquor, food warehouse, if there is water seepage, the department should immediately transfer the contents of the room to a safe place, the Ministry of Engineering to do a good job of plugging the leaks and drainage work.
3, the front door of the rain may backflow into the lobby, the security department, the engineering department will sandbags piled up at the door to prevent the inflow of PA class is responsible for additional manpower to remove the water.
4, the back door of the rain may be backed up into the staff elevator, the security department, the engineering department will sandbags piled up in the back door to prevent the inflow of the back door post security guards are responsible for the removal of water, such as rain has been backed up to the elevator, the engineering department should immediately control the elevator in the elevator above the 1F floor, prohibit elevator operation to -1F -2F.
5. When the wind is strong, the front door and back door should be reinforced with wood plugs and boards to prevent the glass door from being destroyed by the wind, and when reinforcing the glass door, the glass door should be properly kept partially open to reduce the resistance of the wind to the glass door, and the glass of the front door should be guarded by the baggage handlers and the foreman of the security department*** with the same guards. The back door glass is guarded by the security guard at the back door.
6, when the wind is very strong, the gate post security guards baggage should pay attention to falling objects and guide the guest vehicles parked in the underground garage, if necessary, wear a helmet, the front office should be placed on the front desk desk lamps, flower pots, etc. put away, so as not to be blown over.
7, if there is water in the elevator, the engineering department should immediately start the drainage system to remove the water, in order to avoid if the wind is strong, resulting in the passenger elevator can not run, the restaurant screen should be pushed to the elevator entrance to cover.
8, when encountering a power outage, the Engineering Department immediately contacted the property office to generate power to restore lighting. The Security Department maintains the hotel security order during a power outage. When the power outage restaurant cashier by the restaurant management personnel responsible for in place to guard, the main desk cashier by the Security Department front door post and 02 or 01 guard. Lobby assistant, 01, 02 should do a good job of passenger elevator service, check whether the guests were off the ladder, do a good job of being off the passenger elevator guests to appease the work of the floor workers and managers of various departments should be dispersed to the various floors, restaurants to guests to do a good job of explaining and appeasing the work.
9, gutter blockage, by the Ministry of Engineering, the Ministry of Security *** with the people to be sent to unblocking, unblocking personnel should pay attention to their own safety, must wear a helmet, if necessary, should be tied to the safety rope, by two people a front and a back *** with the operation. Should pay attention to the roof equipment layer of electrical equipment whether there is leakage phenomenon.
10, the wind is very large, the office should be responsible for notifying the dormitory employees are prohibited from going out, in the store outside of the staff should be arranged to stay in the hotel, the office and department heads should be discouraged from leaving work employees are not allowed to leave the hotel, the office should be a good arrangement for food and accommodation of stranded employees.
11, the switchboard is responsible for understanding through the TV, timely report to the head of each department of the typhoon situation, such as airports, highways, bridges closed information should be reported to the front office in a timely manner, the front office should be timely to the guests of the hotel notice.
12, the typhoon larger hotel executive general manager, engineering manager, security manager, should stay in the hotel to make emergency preparations, other department managers whether to stay in the hotel should be based on the hotel arrangements, such as leaving the hotel should be reported to the hotel executive for approval.
(d) After the typhoon has caused the loss of the hotel, the departments should be summarized within two days to report the loss.
The hotel's staff will be able to provide a full report of the damages within two days after the storm.