Living integrated wastewater treatment equipment commissioning before what to do the preparatory work ah?

Life integrated wastewater treatment equipment is still very important before the commissioning of the preparatory work, if not done properly, will affect the commissioning cycle and effect.

General engineering companies, construction units and equipment installation units need to civil conditions, equipment, water and electricity and many other items for self-checking to ensure that the project meets the commissioning conditions, the specific requirements are as follows:

1, civil conditions: civil construction works to build such as (grille drains, regulating pools, sludge tanks, equipment foundations, etc.) complete the establishment of a commissioning group to prepare the commissioning outline, stand-alone debugging linkage test drive Microbial culture trial run work and through the single acceptance, to meet the normal operation of integrated domestic sewage treatment equipment related requirements.

2, equipment installation: and integrated equipment supporting equipment mainly includes lifting pumps, level meters, blowers, ultraviolet sterilizers, electromagnetic flow meters, valves, sludge reflux system, mixed liquid reflux system. The installation of each supporting equipment should meet the requirements of the grid use, installation instructions, and to meet the use of integrated domestic sewage treatment equipment.

3, electrical installation: electrical installation in accordance with the design of the process provided by the electrical conditions required to complete the instructions, and meet the requirements of the use of a variety of electrical equipment

4, pipeline installation: pipeline installation to meet the design requirements, and to meet the requirements of horizontal flat, vertical, no leakage of water (gas)

5, water and electricity: sewage network has been accessed within the sewage treatment (station), the equipment into the line Power has been connected to the equipment and meet the requirements of use

The more standardized water quality commissioning will usually be constructed by the construction unit, the design unit supervisory units, construction and installation units, operation and management units, integrated sewage treatment equipment suppliers constitute the commissioning team. Facilities after trial operation, water quality stabilization standards before the completion of water quality commissioning.