Five-story school building, do construction organization design, construction elevator special plan. With what type of construction elevator is good?

Elevator construction organization program

1 Project Overview

1.1 Location: Jinshanjiao, Xinyang, Henan Province

2 Equipment Model Parameters: TDTT/630/1.0

Model: TDTT 5 floors and 5 stops (Passenger Ladder Staircase) ***Counting for 1 unit

2 Preparation Basis

According to the relevant systems, regulations and management requirements, programming is divided into two parts: construction quality standards and construction site management.

2. 1 installation construction quality standards:

Based on the "Safety Code for Elevator Manufacturing and Installation" (GB7588-2003), "Elevator Installation and Acceptance Code" (GB10060-1993), "Elevator Engineering Acceptance Code" (GB50310-2003), and the "installation of electrical installations Elevator Electrical Installation and Acceptance Code" (GB50182-1993) and so on. GB50182-1993) as the basic standards, while referring to the Guangzhou Hitachi Elevator Company "vertical elevator installation process," the relevant factory standard requirements for construction.

2.2 construction site management:

According to the "Regulations on the Safety Supervision of Special Equipment", "Rules for Licensing the Installation, Reconstruction and Maintenance of Electromechanical Special Equipment" and the company's relevant system, before entering the site, each installation team should sign a labor contract to determine the quality and safety of the person responsible for ensuring that personnel are licensed, before construction, according to the relevant provisions of the local technical supervision department to report the start of construction, and to the safety Supervision department for the record, construction to comply with site regulations and the company's requirements system, as follows:

2.2.1 Site management flow chart.

Getting the contract

Understanding the site situation

No

Compliance with the requirements Arrangement of processing

Yes

Reporting the start of work Preparing for construction

Construction Construction records

Individual project inspection

Commissioning

The company's acceptance of the rectification

Qualified

Technical Supervision Bureau acceptance and rectification

Qualified

2.2.2 personnel management: the site by the Sang Jianmin total responsibility, Qin Liheng for the site of a full-time quality inspector, Fan Shixun installation team safety officer.

Site safety group Sang Jianmin

Site quality management

2..2.3 Construction equipment

Elevator installation equipment tools

Type Name Specification Unit Quantity Remarks

Winches 1.5t 1

Starting manual hoists 3t part 1

Heavy manual hoists 5t part 2

Work pulley

Working pulley

Working pulley

Weight manual hoists 5t part 2

Work pulley 2t pcs. 3

Tools U-ring each type pcs. to meet the need

Wire rope sets to meet the need

Electricity welding machine BX6-300 1

Welding machine BX1-200 2

Equipment Welding cap hand-held 3 to meet the need

Equipments Welding pliers pcs. 3

Welding wire 100 mm2 root 50×3

Hammer HR2410 2

Hammer 38E 1

Impact Drill SB2-500 2

Clamp Angle Grinder SIM-SJ100A 2

Hacksaw 4

Worker's Hammer 1.5/2.0 5 meets the need

Slab Handle each Model number 24 meets the need

Worker Sleeve Handle 4032E set 1

Vise 5 meets the need

Tool File 5 meets the need

Ribbon cutter Model number 16 meets the need

Wire pendant 300 meets the need

Type Name Model number Unit Quantity Remarks

Specialized Calibrator 13k 18k pays 3

Tools Guide file pays 3

Long magnetic wire drop 5m only 3

Degree tape measure 3.5m,5m 4

Inspection

Measurement steel plate ruler 150 150mm only 6

Work level 600 3

Tools ink cartridge 10m only 3

Multi-meters 3 < /p>

Type Model Specifications Unit Remarks < /p>

Specialized Calibrator

Offset pliers 3

Electric sharp-nosed pliers 63

Wire strippers 3

Industrial electric pen only 3

Industrial soldering iron 150w 3

Wire number pen

Tools electric knife multi-functional

The main testing equipment instruments, meters

Sequence Name Model No. Number Production Complete

The number of specification quantity of the instrument is not more than 3,000,000 pieces.

No. Specification Quantity Manufacturer Status

1 Multi-function Sound SK-401 1 Changsha Xinde 完好

Grade Instrument Instrument Factory

2 Digital Ground PC22 1 Shanghai Sixth 完好

Resistance Measuring Instrument Electricity Meter Factory

3 Clamp Electricity DT266 1 Zhangzhou Weiyu 完好

Current Meter Electric Factory

4 Megohmeter ZT266 1 Zhangzhou Weiyu mint condition

The main testing equipment instrumentation

Maintained

4 Megohmmeter ZC25-3 1 Shanghai Yuanzhong 完好

Electronic Instrument Factory

5 Vernier caliper 0-125mm 1 Jingjiang Measurement Factory 完好

6 Digital MF-64 3 Shanghai Fourth 完好

Multi-meter Electricity Meter Factory

7 Dynamometer 30Kg 1 Cangzhou Measurement Factory 完好

8 Digital Voltmeter UT60 1 Hongkong Hongchang 完好

9 Percentage meter WCZ-6C 1 Wuxi Far East Electric 完好

0-5mm Tools Co. ?33?0-5mm工具有限公司 ?35? 0-5mm Tools Co ?34? Cangzhou Measurement mplete

0.02-1.00 Tools Factory

The above equipment must be inspected by the quality inspector before entering the site to ensure that the insulation of the electrical tools is reliable, the precision of the measuring tools meets the requirements, and the labor protection supplies are complete and documented before the construction work is allowed to begin. At the same time, the construction safety officer should always check the work of the construction personnel to ensure that it is in accordance with the operating procedures for construction. Repair of equipment damaged during construction shall be re-inspected by the quality inspector before being allowed to put into use.

2.2.3 Construction site management:

2.2.3.1 Quality process

(1) The on-site construction process is as follows:

Laying out the sample frame, lifting line

Installation in the engine room Installation in the shaft Installation at the door

Load bearing beams

Tractor

guide wheel

(). (2) The requirements of the main construction projects are as follows

Main projects: Shaft alignment measurement

Installation and calibration of guide rails

Installation of hall door

Installation of main engine

Installation of wire rope

Installation of car

Installation of door opener

Installation of control panel and trunking

Specific processes Requirements:

Parts: release line, stable line

A, release line:

Relay line is an important important process in the elevator installation process, the release line must pay great attention to. In the use of sample wood, sample wood must be dry and flat, to the shaft wall must be fixed firmly, bracket level error should not be greater than 3 ‰, sample wood level error is not greater than 5 mm. The horizontal offset of the top and bottom sample boards should not be more than 1㎜.

When measuring, it should be absolutely accurate, each size should be measured back and forth, each diagonal must be symmetrical and consistent, the specific steps are:

Fixed the big bracket, first of all, the hall in front of the door of the triple line put down, in the pit and the same bracket and the size of the above to the line is solid, ice from the bottom layer of the upward dimension to determine the installation of its hall door, to be sure that there is no error, the sample wood on the sample board on the shelf put in place, ice from the bottom layer of upward dimension to determine its hall door installation position, to be sure that there is no error, to put the sample wood on the sample board above Shelf on the sample wood put in place, in accordance with the drawings of the size of the hall door on the sample wood as a benchmark, back to measure the main rail and sub rail sample wood position, fixed to re-measurement, to be measured and corrected, to be marked on the drawings of the rail spacing dimensions plus the thickness of the two rails of the dimensions of the line to determine the support parts.

Two, stabilize the line:

Stabilize the line and put the same line, is the installation of the elevator is another important process, stabilize the line is to be put on the line hanging with heavy objects (such as: bricks, wire pendant, iron fast, etc.), so that the line naturally sagging ice in the wind is very small or to take the necessary measures to prevent the wind to stabilize the line, fixed in the pit nailed wells on the sample board wood. Stabilized must be carefully measured, each size and each diagonal must be consistent with the size of the sample frame above.

Three, to be determined after the line, the person in charge of the measured dimensions should be organized and returned to the company for archiving.

Note: 1, the specific size and method of release line please refer to the attached chart

2, in the absence of the completion of self-inspection and special inspection of the money will not allow anyone to unauthorized dismantling of the line.

Part: bracket and support

Requirements:

1, support and neighboring a support must be strictly controlled within 2.5m.

2, a circle of four brackets must be on the same level, ice has ink line obvious level mark.

3, the main rail bracket at the same level, two bracket error is not greater than 20 mm, vice guide two brackets at the same level error should not be greater than 5 mm.

4, the bracket and support the level should be strictly controlled within 1.5%.

5. The support surface of the support bracket should be vertically corrected after each circle of bracket is welded, and the error should be controlled within 0.5㎜.

6. If the bracket of the support frame can not be installed according to the position in case of special circumstances, it should be moved downward (i.e. ≤2500㎜) and another supplementary bracket should be installed on it.

7, the main rail support bracket should be ≥300mm out of the shaft wall with diagonal braces; the secondary rail should be ≥500mm out of the shaft with reinforcement bars.

8, need to lengthen the buried iron, the length of "300 mm, lap length" 50 mm, one end and the original iron welding, weld continuous; the other end with two Φ16 expansion bolts fixed fixed (out of the length of "70 mm can not be used to fix the expansion bolts).

9. The gap between the support surface of the support frame and the back of the rail must be within 2mm (i.e. at least one shim can be put in).

10, hit the bracket of the rise of the chain if it is 100mm ----120mm long to be tightened after the rise of the chain nut. The length of the exposed screw buckle should not be more than 3-5 buckles.

11, the bottom circle of support from the pit floor and the top circle of support from the roof distance should be strictly controlled within 500 mm.

12, in the welding of support pieces of the weld must be full of double-sided welding and is continuous.

13, in the establishment of the rail, the top one pounding ghost from the floor gap shall not be greater than 50 millimeters.

Note: when playing bracket expansion tether, in practice, such as encountering steel bars on the rebar chiseled out, the screw rod welded.

Part: school rail

Requirements: school rail is an extremely important process in the installation of the elevator, because it exists after the removal of the line can not be rectified after the weaknesses, so we must be careful in the school.

1. First of all, we have to carry out the school guide line stabilization process, pay attention to take must have its oh windproof measures. (Refer to the requirements of stabilizing the line in the release)

2. After stabilizing the line, the major diagonal and minor diagonal must be consistent with the size of the top sample, and should be repeatedly measured.

3. Before connecting the rails, the grooves of the joints must be cleaned.

4. In the calibration guide, the left and right deviation of the guide should be corrected by the calibration guide, and the general error should not be more than 0.3 millimeters.

5. In the school rail, the rail joints shall not have a continuous gap, the local gap shall not be greater than 0.5 millimeters, such as joints gap generation is large must be corrected with tools such as brocade file.

6. The gap between the two rails must ensure that the drawings required, the general allowable error of the main rail +1 mm, pay rail error of +2 mm.

7. Two rail joints at the step shall not be greater than 0.05 millimeters, such as non-compliance with the requirements to be amended, the length of the amendment must be greater than 300 millimeters.

8 In the next part of the bracket before the school must check this part of the bracket screws are not missing, loose.

Note: Before schooling the next bracket, the school wire must be measured and checked frequently.

Part: hall door (floor, column, door beam, door, door, door lock, etc.)

Requirements:

1. In the installation of the floor, in strict accordance with the construction process to install, but its level should be strictly controlled within 1 ‰ and should be higher than the final floor of 2-5 mm, the center of its center and the position of the center of the cabin should be less than 1 mm, and its in the cabin floor of the gap between the car and the car. Its clearance to the car floor is 30+2mm.

2. The floor cantilever should be reinforced with diagonal support if it is too much into the shaft.

3. When installing the column, both sides of the column and lintel connection should be tight without gaps, and the column and lintel hanging them at the side must be flat, and its verticality should be controlled within 1‰.

4. In the installation of the door beam when the fixed point must be firm, the door slide must be parallel, and the door slide from the highest place to put the hall door line distance of 72.5 mm, from the door beam cover 37 mm (this size for the Mitsubishi and Fuji elevator all dimensions, and the car floor and hall door floor gap of 30 mm)

(in the installation of different types of elevators, you should carefully refer to the installation process to determine). to determine).

5. When installing the hall door, the hall door should not be deformed and twisted, if there is deformation. The hall should be corrected, the verticality should be strictly controlled within 1 ‰, the hall from the bottom edge of the ground clearance and from the column clearance should be 5mm ± 1, its full closure gap of 1mm.

6. When installing the door lock, the door lock must be rotated parallel and flexible, its teeth with the lock hook is 7mm, after the door is closed, its gap with the lock hook is 2mm+1, and the position of the contact is 2.5±1.

7. Before installing the hall door, the columns must be installed, and the door is installed after the untouchable protective film is removed.

Note: When making the floor, if the civil engineering is not completed without making the final ground, you should ask the civil engineering and the A side to make an accurate 500mm--1000mm final ground line, and after correcting, there must be a written report for the A side or the person in charge of the civil engineering to sign.

Part: (tractor, steel beam, host, guide wheel)

Requirements:

1, in the stabilization of the traction program must first of all the steel beam in the middle of the two wire rope holes out (waterproofing table if necessary), and the bottom of the steel beam must be enough with the ability to the cement piers and iron plate, the level of the steel beam should be guaranteed within 2%, and the depth of steel beams buried in people beyond the bearing wall

2, in lifting the traction machine, to carefully check whether the inverted chain is reliable, and in lifting the wire rope shall not directly lift the motor shaft head. (In the stable shock absorbing pads should be correctly positioned, the verticality of the tractor wheel should be controlled in the loading within 0.5mm unloaded before the man is higher than 3mm).

3, in the installation of the guide wheel, its position must be correct (nozzle must face out to facilitate refueling) and its verticality should be controlled within 0.5mm, after the installation of the guide wheel and the traction wheel parallelism shall not be greater than 0.5mm, stable after the bolts must be tightened firmly, the cotter pin must be complete on the good.

4, in the traction machine after the machine is stabilized, the traction wheel and guide wheel center line before, after, left, can be on the sample wood center line error shall not be greater than 1mm (special ladder depending on the actual situation, such as Mitsubishi, etc.) and the dowel on the diagonal pads must be used to weld on the welder spot welding.

5, tractor, motor, guide wheel installation is completed, must check whether the lubricant injection.

6, each installation must be completed after all the screws to prevent leakage, loose.

Part; put the wire rope

To the car frame and counterweight frame after installation. When putting the wire rope must first support the height of the counterweight. Specific support counterweight height method: spring buffer final according to the counterweight frame low distance should be 200mm - 350mm, hydraulic buffer for 200mm - 350mm. in support of the counterweight frame must take into account the bottom of the ground to the top of the car The hall door of the ground can not afford the distance, and add the length of the wire rope bent in the rope sleeve (twice the depth of the cone sleeve) and subtract the elongation of the wire rope, the elongation of the wire rope is generally 7 ‰.

Note: 1, wire rope storage should be protected from water and direct sunlight.

2, wire rope should be prevented from trauma and deformation during transportation.

3, the wire rope should be prevented from circling and twisting when the whole disk is pulled apart.

Part: traction wire rope rope head

Requirements:

1, to do the wire rope head, should be measured quasi-reservation size (generally for the depth of the taper set of 2 times), measured after the lead wire must be fixed, the fixed length of not less than 20mm. fixed after the rope rope within the hemp rope should not be cut off too short, at least to be higher than the fixed point of 10mm, to be made to the head of the rope to be filled with alloy, the curved wire rope should be exposed in the rope sleeve. Wire rope should be exposed in the rope sleeve 2-5mm (site of the actual mastery of the alloy temperature: a piece of paper into the burnt alloy immediately on the burning is appropriate).

2, to be loaded onto the car and the counterweight, each rope head locking nut (pay attention to anyway, the plane of the opposite) should be locked and the cotter pin inserted.

3, the elevator has a weighing device, pay special attention to protect the device, and after loading with plastic paper surrounded.

Part: car

Requirements:

1, the wall of the car and the wall of the joints should be tight without gaps, stainless steel wall joints should be removed beforehand to protect the car wall, after the installation of the car around the car and the back of the car wall re-straightness should be strictly controlled within 2 ‰, the door of the car at the two car wall should be strictly controlled in the full height within 1mm.

2, the bottom of the car level control within 1‰. In the car wall to the bottom of the car on the top of the car cover, correction frame can not be too hard, must be loosely put in, the doorway car wall and the car within the car wall weight straightness must be in the required range.

3, after the installation is completed, must check the screws have no severance, loose.

Note: No one shall remove the gibbet without the consent of the company.

Part: door opener (car door, safety contact plate, door knife, etc.)

Requirements: door opener in the installation process must be serious and careful, because it directly affects the car door, door knife and other components of the installation and adjustment, so we must pay attention to in the installation.

1, open the door motor drive wheel to vertical, verticality should be controlled within 0.5mm, belt tension should be moderate, and the door opener midpoint must be coincident with the center line of the car floor, front, back, left, right must be horizontal, its level is not greater than 1‰, and the door slide sliding plate bottom side of the car floor should be guaranteed to the distance of the car floor 2200mm.

2, in the installation of the car door, must check whether the door is deformed, the door knife and other components of the installation and adjustment. Be sure to check whether the door is deformed, and the door, columns on the installation is not easy to reach after the removal of the protective film.

3, the door column gap is less than 1mm.

4, in the installation of the touch plate, first of all to check the rotating parts of the jamming and rotation of the phenomenon of inflexibility, such as must be refueled and trimmed. When installing, its verticality must be guaranteed, after installing, when the car door is fully open, the contact plate should protrude from the car door 13+2mm, and the maximum amount of protruding in the action should be 48+2㎜, and when the car door is fully closed, one side of the contact plate should be blocked from the middle seam of the car door 10㎜+2, and the two contact plates shouldn't be collided with each other, and the gap should be 6+1㎜.

5. When installing the door cutter, its verticality must be guaranteed, and the error of verticality of the whole length of the door cutter is not more than 1㎜, and after installing it, the clearance according to the hall door should be controlled within 8-10㎜. When the door of the car is fully closed, the opening distance of the door knife should be controlled at 72+1㎜.

6. After the installation of each part is completed, the screws must be checked for leakage and looseness.

Note: The above dimensions are the dimensions of Mitsubishi and Fuji. If you encounter a different ladder, please refer to the drawings carefully, and to the drawings required size shall prevail.

Part: control cabinets

Requirements:

1, control cabinets in the machine room to refer to the drawings placed in a reasonable manner. Double and multiple, the control cabinet to strictly distinguish between the elevator number (especially distinguish the fire ladder). Maintenance is not less than 600MM from the wall and doors and windows elsewhere is not less than 500mm. its verticality should be guaranteed within 2‰, wire trough and cabinet joints should be no gaps, the cabinet plug-in line should be tied neatly, the cabinet wiring should be laid out reasonably, the line number is clear and have a good grounding.

2, power lines and control lines in the trunking should be separated from the power supply into the zero, the ground should always be separated, the grounding wire should be yellow and green insulated wire and shall not be strung to repeat the grounding.

Part: wireway (machine room, shaft, call ladder line, etc.)

Requirements:

1, machine room wireway location must be placed reasonably, the direction of the interface must be horizontal and vertical interface is tight and flat, no warping. Its parallelism should be no more than 2 ‰. Each hole must be opened with a hole opener, the import and export should be added to the protective pad.

2, shaft line channel must be vertical, no gaps at the interface verticality is strictly controlled within 5 ‰, the need to open the hole must be opened with a hole opener.

3, the line pipe in the shaft, the fixed point should be no more than 1M, end fixed point should be no more than 0.1m, and must be fixed firmly without loose phenomenon.

4, the shaft of the soft line must be taken to the correct location, appropriate length, horizontal and vertical.

5, shafts, engine room trunking must have obvious grounding mark.

(3) According to the process, the quality of the main construction projects must meet the following requirements:

A rail bracket welding should be continuous, double-sided welding, and from the bottom of the pit, the first pre-embedded parts from the bottom of the pit ground for 500mm, above the spacing of each for 2500mm, and to ensure that each rail bracket not less than 2, spacing is no greater than 2.5m, the top floor according to the drawings Special requirements for construction. In the same layer of the level of each bracket is not greater than 15%, the concrete structure should be fixed with M16 expansion bolts (each piece of pre-embedded parts should be set up with four bolts, the depth of its burial is not less than 120mm, on the level of the door door beams and the ground can bracket pre-embedded steel plate should also comply with this requirement).

Guide rail lifting correction process should be in line with: car guide rail working face 5m plumb line of the maximum deviation should not be greater than 0.6mm, T-type counterweight guide rail working face 5m plumb line of the maximum deviation should not be greater than 1.0mm, guide rail joints should be a continuous gap, and the local gap is not greater than 0.5mm.

B storey door installation:

Requirement of its storey door The clearance of the floor door from the car floor is 30mm, the error is +0-1mm, the level is 1/1000; the verticality of the door column and the door beam is not more than 1/1000. meanwhile, it is guaranteed that: the floor of the hall door should be higher than the decoration ground 2-5mm: the clearance of the hall door door and the door, door and door set, the lower end of the door set and the floor, the clearance of the passenger elevator is 3-6mm: the freight elevator is 3-8mm; the electrical safety of the hall door lock is 3-6mm; the clearance of the door lock is 3-8mm; the clearance of the door lock is 3-5mm. 8mm; the minimum engagement length of locking element is 7mm before the electrical safety device of the hall door lock is operated.

C part of the machine room (top of the shaft):

The deviation of traction sheave to the plumbline is not more than 2mm, and the deviation of the rope sheave of the speed limiter to the plumbline is not more than 0.5mm. Control cabinet of the machine room is installed according to the drawings in combination with the reality, and the base of it should be higher than 50mm above the ground level, and the deviation of verticality should not be more than 3mm. Verticality deviation is not greater than 3 ‰; wire channel installation, to horizontal and vertical; wire channel of the Department of the line area of not more than 60%, the line pipe Department of the line area of not more than 40%; In addition, the machine room should have good lighting, through the cooling facilities, fire fighting facilities, communication facilities and anti-theft door.

D car part:

Car part of the car to adjust the bottom of the car its level is not greater than 2/1000, and corrected with the correction pieces.

E Electrical installation wiring should be based on the "Electrical Installation Engineering Elevator Electrical Installation Construction and Acceptance Code" (GB50182-1993) and the factory issued by the electrical drawings construction, special attention to the choice of grounding with TN-C or TN-C-S grounding methods to ensure that the resistance to ground is not greater than 4 Ω, and each charged equipment effectively grounded.

(4) quality records: According to the company's management regulations, construction personnel must fill out the "construction diary", detailed records of the construction process. At the same time in the quality inspection point must be timely to the quality inspector to declare special inspection, there is a requirement should also be the same time to the site users or supervisors to declare the inspection, can not record the construction diary or do not declare the inspection of each time for no good reason based on the company's relevant systems to be punished 50-100 yuan.

2.2.3.2, construction safety:

Company regulations: elevator installation and maintenance operators must be licensed, the construction site to set up a full-time or part-time safety officer, according to the need for the construction site must be equipped with the appropriate labor protection supplies, including: safety belts, helmets, insulated shoes, gloves, masks, glasses, etc., in order to protect the safety of the construction to achieve the purpose of safe construction. In order to ensure the safety of the construction environment, the hall door of the shaft is equipped with a guardrail, or closed, and posted in the opening part of the hall door eye-catching warning signs. To take security. The company stipulates that a full-time safety officer is set up at the construction site. In order to ensure the safety of the construction environment, the site with oxygen and acetylene should be placed in accordance with the requirements of the smooth spacing of not less than 5M, or effective isolation, to check to ensure that there is no fire hazard at the close of business. In order to ensure the safety of late construction, the company regulations prohibit the unauthorized transfer of elevator keys to the user or unauthorized transfer of elevators to the user to use their own.

The company's 5S system provides that the safety system education and publicity materials must be posted in the depot in a prominent position, the violation of the safety system, according to the company's requirements, the penalty 50-200 yuan.

Special provisions for safety signs: shaft entrance should be written, signage method of identification "shaft construction, please do not approach" or "elevator out of service, please do not approach" or the factory issued signs; machine room with writing or signage method of identification The machine room should be marked as "machine room is an important place, no one is allowed to enter" or factory-issued marking; the power supply part should be marked with writing or signage "Beware of electrified". Construction parts due to the working environment, the user needs to move, should be removed in a timely manner, such as the distance should be farther away from the original storage part of the writing to mark its new location.

2.2.3.3, civilized construction:

In order to cooperate with the safety and quality management of the construction site, the company has formulated the construction site management rules (5S), and made detailed regulations on the placement of the components and related items, which requires that the components on site must be neatly arranged or put into the shelves, and be placed in layers according to the sequence of use, and the fragility of the precious situation, which ensures that the site equipment is intact and the warehouse is clean and tidy. The warehouse is clean and tidy.

At the same time, the behavior of the construction staff clothing requirements, strict compliance with the site system to ensure that the cooperative unit to maintain good relations of cooperation, and to maintain the user and the company's image.

2.2.3.4, comprehensive evaluation:

In order to ensure the effective management of the team, constraints, rewards and penalties, the company has developed a comprehensive evaluation system can be quantified, each construction team's performance in all aspects of the evaluation, the implementation of the final elimination of the future project, to promote the conscientious compliance with the rules of the team.

4, emergency response measures

4.1 safety accidents: fall, electrocution, fire and other safety accidents, the person responsible for safety should be in accordance with the company's accident handling procedures, remedial measures for the accident, while trying to retain the scene and cooperate with the security department's investigation.

4.2, quality accidents: quality inspector found quality accidents, should order the parties concerned to immediately stop work and report; company investigation and personnel, information, and check the scene after writing an analysis report to put forward corrective measures and report for approval.

Well-thought-out and perfect plan is only the first step to the successful completion of the construction, our company will continue to self-check on this basis, improve the level of management, improve the construction process, and strive to achieve customer satisfaction, the installation of high-quality engineering.