Name: Beijing Asuwei domestic waste incineration power plant project.

Project geographic location: Asuwei, Xiaotangshan Town, Changping District, Beijing.

Construction nature: new construction.

Construction content and scale: The project is a response to the National Development and Reform Commission, the Ministry of Construction, the State Ministry of Environmental Protection, "on the issuance of the national construction of harmless urban waste treatment facilities "Eleventh Five-Year Plan" notice" (Development and Reform Investment [2007] 1760) and the Beijing Municipal Commission of Development and Reform, Beijing Municipal Commission of Development and Reform, Beijing Municipal Commission of Construction "on the issuance of Beijing 2009 key construction project plan notice" (Beijing Development and Reform [2009] No. 155) of the spirit of the proposed in Beijing Changping District, Baishan Town, Beijing, the construction of "Beijing Asuwei domestic waste incineration power plant". The project is intended to use waste incineration disposal technology, the project content includes the transportation and reception system of domestic waste, sorting system, incineration power generation treatment facilities, wastewater and flue gas purification and treatment facilities and so on.

The designed treatment scale of this project is as follows: screening domestic garbage 1400 t/d , incinerating domestic garbage (screened material) 1200t/d.

Environmental protection: According to the requirements of Beijing Municipal "Domestic Waste Incineration Air Pollutant Emission Standards" (DB11/502-2008), the incineration plant plant boundary distance from the residential (village) houses, schools, hospitals and other public **** facilities and similar buildings should be no less than 300 m. The government will build a recycling economy industrial park in a larger area outside the waste plant that is conducive to the development of the region, develop a variety of green eco-industries, develop the local economy, and improve the quality of the environment. After the completion of the project, it can greatly reduce the direct landfill of primary garbage, reduce the emission of foul-smelling gas from the landfill, and improve the local environmental quality. The pollution sources that may be generated by this project mainly include waste gas, waste water (including leachate), noise and solid waste (such as slag and fly ash). The project proposes to take proper sorting measures for the incoming domestic garbage and complete the treatment in a short period of time; adopt cyclone dust removal, semi-dry deacidification and bag filter dust removal for the waste gas, etc., and design the emission indexes of the waste gas all in accordance with the national and Beijing Municipal "Domestic Waste Incineration Air Pollutant Emission Standards" (DB11/502-2008) emission limits, among which, the dioxin is controlled to be under the value of 0.1 ng/Nm3 (the same as the EU emission standards), the flue gas is discharged through the 60m chimney after the treatment; the effluent from the sewage treatment station is fully reused in the plant after reaching the standard, and there is no discharged wastewater; measures such as increasing mufflers, isolation or protection are taken to target the noise sources and ensure that the noise at the plant boundary is up to the standard; the incineration process produces the slag and the fly ash according to the characteristics of the incineration process, and it is strictly carried out in accordance with the requirements of national and Beijing regulations and standards, respectively. According to the characteristics of the slag and fly ash produced after incineration, the final disposal will be carried out in strict accordance with the requirements of national and Beijing regulations and standards.

Project investment: the total investment is about 83.251 million yuan. The evaluation of this project is jointly undertaken by the China Academy of Meteorological Sciences and Tsinghua University.

Trash package

(1) China Academy of Meteorological Sciences

Certificate grade: Class A; Certificate No.: State Environmental Assessment Certificate A No. 1003

Address: No. 46, Zhongguancun South Street, Haidian District, Beijing;

Contact person: Liu Qinya

(2) Tsinghua University (Environmental Impact Assessment Room)

p>Certificate Grade: Class A; Certificate No.: State Environmental Impact Assessment Certificate A No. 1022

Address: 2504A, Huaye Building, Tsinghua University, Beijing;

Contact Person: Chen Dayang, 1. Working Procedures

(1) The construction unit commissions a qualified EIA organization

(2) The construction unit announces the relevant information about the project's EIA work to the public

>(3) The EIA organization carries out on-site survey and investigation of the current state of the environment and public opinion survey

(4) The EIA organization prepares the environmental impact report

(5) The EIA organization publicizes the main results of the EIA work

(6) The construction unit declares the environmental impact report and other relevant materials to the competent department of environmental protection

(7) The competent department of environmental protection approves the project

2, the main work:

Project overview and engineering analysis; (2) environmental impact identification; (3) environmental characteristics of the construction area; (4) compatibility of the project construction with regional planning; (5) analysis of the impact of ambient air, noise, solid waste pollution; (6) analysis of the impact of the construction period; (7) analysis of clean production; (8) analysis of the feasibility of pollution prevention and control technology; (9) public participation; (10) analysis of the environmental and economic gains and losses; (11) Environmental management and monitoring plan; (12) Conclusions and recommendations.

(1) Solicitation of public opinion:

Waste treatment equipment

This public notice mainly solicits the public's opinion on the current environmental quality of the proposed project area; their awareness of the main environmental problems existing in the regional environment at present; their attitude towards the construction of the project; their suggestions for the improvement of the environmental quality of the project's proposed site; their focus of interest in the environmental problems that may exist in the course of construction of the project; and their views on the construction and monitoring of the project. environmental problems; suggestions for solving the environmental problems that may arise during the construction of the project and after the completion of the project. The content of non-environmental protection is not included in the scope of this solicitation.

(2) Starting and ending time:

Within 10 working days from the date of publication of this notice (letter postmarked date shall prevail)

After the public announcement of this information, the relevant public at the location may express their opinions on the construction of the project and the EIA work by sending e-mails to the designated address, by telephone, by fax, by letter, or by face-to-face interviews, etc. The public is requested to provide information on the construction of the project and the EIA work while expressing their opinions. The public is requested to provide detailed contact information at the same time of expressing their opinions, so that we can provide you with timely feedback of relevant information.

The purpose of this public announcement is to disclose the information after the evaluation unit undertakes the EIA project, and the next EIA work will be carried out in strict accordance with the requirements of the relevant national laws, regulations, standards and norms. After the conclusion of the EIA, the evaluation unit will take various ways to further solicit public opinions, when the public can refer to the work results of the EIA unit to make specific comments.