A wastewater treatment plant project, the data clerk specifically what information needs to be done?

Data Volume Table of Contents

Project Name

Yunnan So-and-So Limited Wastewater Treatment Project

Constructor

Yunnan So-and-So Limited

Contractor

Yunnan So-and-So Environmental Protection Equipment Co.

Remarks

1

Contractor's qualification

2

Contract

3

Engineering design plan

4

Engineering commencement report

5

Construction organization design and report

6

Construction Site Acceptance Record Form

7

Major Equipment Certificate of Conformity

8

Equipment/Piping/Electrical Installation Project Engineering Inspection Application Form and Acceptance Report Form

9

Completion Report Submission Form

10

Engineering Completion Report

11

Water Quality Monitoring Report

12

Project Completion and Acceptance Handover Certificate

13

As-built Drawings (see attachment)