Table of Contents
Volume 1 Overview of the Project 2
Volume 2 Construction Deployment 2
Volume 3 Construction Progress Plan 3
Volume 4 General Layout of the Construction 3
Volume 5 Preparation for Construction 4
Volume 6 Construction Methods for Major Projects 5
< p>Volume 7 Main Construction Machines and Equipment 11Volume 8 Labor Organization, Team Equipping 12
Volume 9 Quality, Safety, and Economy Control Measures 12
Volume 10 Civilized Construction: 14
Volume 11 Measures for Superiority Achievement: 15
Organizational Design of Pipeline Construction of Wastewater Plant in a County
Volume 1 Project Overview
This project is located in the southeastern part of a county, for the sewage treatment plant engineering plant pipe network part, mainly by the underground sewage pipeline, process pipeline, beyond the pipeline, venting pipeline, rainwater pipeline and water pipeline to the water and so on. Pipeline location for the layered connection between the building structures, sewage pipe excavation trench depth of about 4.3m soil quality for the fine yarn soil due to the design of the pipeline from the structure is close to the cross operation of the narrow construction is too difficult.
Site geological conditions, the site soil for the fine yarn soil and site more powder soil, low cohesion, high permeability, engineering construction should be good trench drainage.
Duration requirements: November 11, 2007 - December 8, 2007, the effective duration of 30 days.
Quality standard: strive for excellent
Volume 2 construction deployment
(A) construction process
According to the construction site conditions and project characteristics, the construction process is: sewage pipeline - process pipeline - beyond the pipeline - water pipeline for the water supply
A: sewage pipeline
(1) site, the initial measurement and positioning; (2) site leveling, three passes and one level; (3) trenching and drainage (4) transporting earth (5) leveling the trench measurement again, accurately set out the centerline and elevation of the pipeline; (6) please supervise the inspection of the trench; (7) paving sand (8) under the pipe masonry check well earth backfill, sampling layered tamping; (9) clean up the site.
Other pipeline burial in addition to steel pipe welding construction procedures with the sewage pipeline.
(2) construction section
(1) base trench excavation: a construction team dedicated to pipe excavation and backfill and installation.
(2) steel pipe anticorrosion and welding: there are three professional teams to do steel pipe descaling and anticorrosion and welding,
(3) pipeline section: according to the construction characteristics of the project, combined with the construction force of Sunshine Company, to carry out the section layering from deep to shallow for the pipe burial.
Volume 3 construction schedule
This project is a large amount of construction difficulty, according to the owner's requirements, completed on December 8, the effective construction date of 26 days.
Construction progress network plan diagram: see attached.
Volume 4 construction general layout
Because the construction site is narrow and crowded, materials, tool storage, on-site office, carpentry shed, steel processing shed, canteen, and other arrangements.
Construction site main temporary facilities list Table 4-1
Name Area (length×width)m2 Structure form Remarks
Site office 12 m2 (3×4) military tent with built-in thermal insulation
Militant workers' dormitory 150 m2 (6×5) military tent 3
Worker's canteen 80m2 (10×4) asbestos sheet wall, light steel skeleton.
Workers' canteen 80m2 (10×4) Asbestos wall, light steel frame, tiled roof, 50 people's meals
Steel processing shed 200m2 (20×10) open space Setting up bending and cutting equipment
Materials storage 200m2 (20×14) open space Stacking of valuable materials
Tools storage 90m2 (18×5) Asbestos wall, light steel frame, tiled roof, Storing of small tools and machines
Volume 5: Construction Workers' Canteen 150 m2 (6×5) Military tent 3 tents >
Volume 5 Construction Preparation
(A) Production Preparation
1. Removal (demolition) of all temporary structures within the scope of the project, 2. such as trees, communication lines, etc. 3. in the elimination of du pools next to the cement warehouse and the east fence by the cable and other construction units such as cross-work factors are seriously affecting the normal construction, so the owner of the above situation please coordinate, the construction unit to cooperate to solve the problem. Construction unit with the solution.
4. According to the site conditions, 5) laying out the office, temporary construction, 6) water and electricity, 7) and test water and electricity. Project electricity can be considered from the sewage treatment plant power supply.
8. Preparation of construction budget, 9. Preparation of materials for the project. Proposed material varieties, models, specifications, quantities, 10. indicate the time to enter the field. 11. pipe procurement based on the design drawings 12. steel pipe elbow by the processing plant to process the finished product, into the field.
Preparing measuring instruments to organize personnel for control measurements, order (rent) construction of special machinery and equipment, maintenance of machinery and equipment for construction.
(II), technical preparations
1. Carefully study and review the construction drawings, and organize a comprehensive review of drawings for civil engineering professionals. Conduct design briefing and technical briefing.
2. Establishment of surveying and mapping team, the establishment of the measurement program, according to the construction design of the general plan, set the reference point, make a good measurement of macro-control.
3. Prepare specific construction plan for pipeline construction. Organize construction personnel to study, technical training for professionals, and hold program meetings.
Volume 6 Main Project Construction Methods
(I) Measurement and Layout
A. Technical Design Program
(I) The design program is the core part of the technical design, which includes the selection and determination of the main specifications of the results, the basic accuracy, the process, the operation method and the main technical provisions.
Surveying and mapping results include:
(1) Plane coordinates and elevation system
(2) Scale of topographic map
(3) Delineation of topographic categories
(4) Plane and elevation control point number and location
Technical design of survey and production, as shown in the figure:
Selecting lines on the map --Field survey --Field point making and staking --Line measurement --Grade calculation
Measurement of longitudinal and transverse section -- Level observation -- Measurement of curve, condition coordinates, center line measurement -- Center line construction sampling, pipeline, working well sampling measurement
Internal work Curve Measuring curve, coordinates, elevation calculation -- Spreading longitudinal and transverse cross-section map -- Spreading pipeline line -- Preparing the report of survey -- Preparing the result table -- Preparing the report of survey. Preparation of result sheet
Part I: External Survey
Includes: technical design requirements, line selection, center line and starting point, fixed point measurement of turning points, curve measurement, measurement of conditional coordinates, measurement of the center line, level measurement, measurement of longitudinal and transverse sections, external inspection, and execution of the as-built drawing of the project at 1 :500.000000。
Part II: Internal Work
Including: curve calculation, coordinate calculation, elevation calculation, spreading of longitudinal and transverse sections and centerline diagrams, preparation of survey report, and preparation of result table.
B)Construction measurement technology design content
First of all, we should check the original big place and the intact degree of the measurement sign when we set foot on the survey.
(A) based on:
1. "Urban Engineering Pipeline Comprehensive Planning Specification" (GB 50289 - 98)
2. "Engineering Measurement of the basic terminology standard" (GB/T 50228 - 96)
3. 50026 - 93)
(2) according to the problems in the measurement area to put forward the general principle of dealing with the problem
1. Supporting pipeline project is an underground building, laying in the urban areas of dense buildings, in a narrow section of the arrangement of a variety of pipelines, often up and down, crisscrossing. Therefore, in the pipeline project measurement, the surveyor is required to strictly in accordance with the design position on the drawings, the correct pipeline measured on the ground. To this end, must use the city's unified coordinates and elevation system, in accordance with the "whole to local, first control after the broken part" and "step by step with the check" principle.
2. This project construction construction goal is "excellent", must be high quality, high standards, strict requirements for engineering construction, measurement tasks must be accurate, fast, high-quality construction of the project to provide reliable and accurate data.
3. Construction measurement, a process of measurement error exceeds the limit, must be analyzed, re-measurement.
4. According to the specification requirements, the construction of the project to take measures as follows:
(1) the error in the location of the wire network points shall not be greater than 5 centimeters.
(2) four equal triangular network measurement angle error shall not be greater than ± 2.5 "".
(3) The level measurement adopts the method of fourth-class level measurement, and the inaccuracy of level measurement closure is ±12√L (L is the length of the line).
(4) A construction control point is set every 150 meters or so.
C) construction measurement (according to the progress of construction, measurement work to do a good job with the work)
A) construction preparation and the establishment of the construction control network
1. Instrumentation of professional testing, detection of some of the systematic errors of the instrument itself, and make a good record.
2. The design unit provided by the control points, leveling points one by one to check the number, level, pile type, orientation, firmness, reliability of a thorough investigation, to be approved after the error, and then testing, tethered stakes, marking, and tethered stakes measurement results into the drawing of the point of record.
3. Establishment of plane, elevation of the professional construction control network
Surveying work must follow the "from the whole to the local, the first control after the broken part" principle. First of all in the construction area selected points with control significance, naming. Considering the characteristics of the construction site work and the need for frequent sampling, construction control points should be drawn on the construction plan, tethered stakes, do point map. Then use concrete stake markers to fix them as the basis for construction sampling and other measurement work. Then control measurement, accurate determination of the position of the established control points, and then control measurement as the basis for the fragmentation of the measurement and measurement work.
Control measurement consists of two parts: plane control measurement and elevation control measurement. According to the characteristics of the project and the requirements of construction measurement, the plane control network using wire network as the basic control. The guide line measurement system determines the length of each side and the turning angle to gradually establish the control points, and then according to the coordinates of the starting point and the starting azimuth can be calculated from the coordinates of each control point. In the establishment of elevation control network, according to the characteristics of the project site and save money on the point of view, the plane and elevation control network of two control points into one for use, reduce the cost of concrete piles even if it is to improve the accuracy of measurement and convenient construction sampling.
Two pipeline centerline measurement and well sampling
Before the start of the line, according to the drawings provide the basis for the line, the centerline of the pipeline centerline and check well location. Each check well in addition to nailing stakes, but also set up a hitching point stakes, and in the hitching point on the hitching point to indicate the hitching pile number, hitching pile material, check well number, distance, direction, with the point of the mark to do a good job of record-keeping work.
The task of centerline survey is to measure the position of the designed pipeline in the river channel and mark it with wooden stakes, which includes the measurement of the main point (i.e., the starting point, the end point and the turning point of the pipeline) and the burying of the mileage stakes, etc. The survey will be carried out in the middle of the river channel.
1. Main point measurement
First, according to the design coordinates of the main point of the pipeline, calculate the relationship between these points and the nearby control points, and then use the method of measurement and positioning, through the coordinates of the inverse calculation of the measurement data, the main point will be calibrated on the ground.
2. Setting mileposts and adding piles
In order to determine the length of the pipeline and map the longitudinal and transverse sections, a milepost is set along the centerline of the pipeline from the starting point at regular intervals (generally 20 meters, 30 meters or 50 meters), and piles should be nailed at the important features between the adjacent mileposts and at the changes in the ground gradient.
When making centerline measurements, distances should be measured back and forth with a steel ruler in order to avoid errors.
3. Pipeline longitudinal and transverse cross-section measurement
(1) leveling points
Longitudinal leveling should be set up along the pipeline before a sufficient number of leveling points, leveling, longitudinal leveling and pipeline construction of the segment attached to the construction of the citation of the basis of the elevation.
In the center line of the piles, measured perpendicular to the center line in the direction of the distance from the center line and the elevation of each feature point, according to these data to draw a cross-section map, is the cross-section map. It is the basis for calculating the amount of earthwork and determining the boundary of trenching during construction.
Three) pipeline construction measurement
1. Before trenching, first in the check well wells buried in a sample plate (with a straight support plate can be, the length of the slot width plus 2 meters), and will be the center line and the mouth line moved to the sample plate. Such as mechanical trenching, you can first use white ash to spread a good side line, to be dug after the trench earth, should still be supplemented with a sample plate to ensure that the center line of the pipe position is accurate. According to the measured ground elevation to calculate the depth of the trench, the width of the upper mouth, and use wooden stakes or white ash to put out the pipeline and check the edge of the trenching well line.
2. Pipeline construction survey is the main task according to the project progress requirements, for the construction of measuring and setting up a variety of signs, so that the construction personnel can easily grasp the direction of the center line at any time and the location of the elevation.
After the pipeline center line is set out, according to the center line position and the width of the pipeline excavation, in the river after dredging the bottom of the trench ground scattered gray line shows the excavation boundary. In the trench digging pipeline slot, the center line of each stake will be dug out, therefore, when the trench excavation to a certain depth, the pipeline must be re-examination of the center line position. First of all, the center line of each turning point measured in the trench calibration, the latitude and longitude instrument placed in the pipeline starting point, aiming at the other end of the pipeline point of the stake on the sign, the direction of the line of sight that is the direction of the pipeline center line, according to the direction of the stake calibration in the trench.
In order to indicate the depth of the trench excavation, but also in the stake mark to make the elevation mark. According to the nearby control level, determine the top surface elevation of each stake.
Pipeline construction measurement in the detailed coordinates and detailed elevation measurement:
Detail coordinates: start, end, turn, intersection (all measured pipe centerline or trench center) and the center of the pipeline line of the large well wells,
Detail elevation: the ground, the well platform, the top of the upper water pipe, the bottom of the lower water pipe.
(2) Elevation measurement
First in the pit, set a temporary level point, the level meter is placed in the pit, the back view of the temporary level point, the front view of the pipe to be measured at the point of the ruler (the use of a smaller than the diameter of the pipe of the homemade ruler), you can get to the point to be measured elevation. The measured elevation and the bottom of the tube design elevation comparison, the difference is more than ± 1 cm when you need to correct.
In order to ensure the quality of construction, every 0.5 meters of jacking should be carried out once the center line measurement and elevation measurement, deviation in the allowable range, before continuing jacking.
(B) drainage
Because of the tight schedule, so the form of open ditch, set up a water pit in the downstream to ensure that the construction surface is dry, ditch depth of 800mm, 500mm wide, i=1%; artificial catchment wells pumping, catchment wells set up every 15 meters to 20 meters, wells dug and dry brick, the periphery of the grass bag wrapped, or the seat of the well plate sinking method of water pumping. In the case of serious sand flow, play a large well beforehand, one for every 20 to 25m, and then dig the soil after stabilizing the pump and lowering the water in advance. Appropriate increase at the working well and water collection well.
Specialized personnel are responsible for monitoring the water level of all collection wells, and special people watch the pumps, strictly control the groundwater level under the construction work surface, and ensure that the groundwater level is 0.5m below the work surface.
(C) Foundation
The excavator is used to excavate and load the soil for transportation. Clear the bottom by hand according to the horizontal pile, and strictly prevent over-excavation or disturbance of the foundation. Found soft or over-depth (silt ≥ 0.5 meters, foundation treatment and design **** fixed) should find design, supervision agreed to backfill with stone chips, according to the design requirements of the compaction coefficient of compaction treatment.
(E) pipe installation
This project uses socket ring steel PVC, PE pipe steel pipe, 360 degrees gravel foundation. Pipe diameter, pipe length (6m a section), self-important. It is difficult for transportation, pipe lowering and pipe stabilization.
1, foundation treatment - due to the soil quality of this project for the backfill of fine sandy soil is prone to collapse, over-excavation of part of the consultation with the superintendent, the owner, and do another treatment.
2, 90 ° gravel foundation - stone is with 2 inch ~ 2.5 inch mixed ballast bedding, according to the "municipal engineering quality inspection and assessment standards" (drainage engineering) provisions of the construction, layered tamping (0.93). Do the bottom of the pipe in the sand support corner, in the corner of the bottom of the brick, the pipe on the bullet line, hanging horizontal line, to ensure the quality of the project.
3, inserted PVC pipe - artificial pipe, hang the outer edge of the line to control the straightness, with a level to follow the measurement of the elevation. When the tube hanging down, the rubber ring set in the socket head, straight and not twisted. When the socket is inserted into the socket, the center of the two sections of pipe is straight and inserted slowly. Tensioning equipment using 10t hand chain hoist tightening in place, so that the socket small platform into the mouth can be, in order to enter the smooth, can also be coated with lubricant on the rubber ring. Measure the top elevation of the pipe after it is in place (reserve about 25mm for self-sinking), and so on. Encounter the well location according to the well size requirements to reserve spacing. (Note that in the mouth of the pre-digging groove)
4, steel pipe - with the crane down the pipe, hanging the outer edge of the line to control the straightness of the level meter to follow the measurement of the elevation. When the tube hanging down, the rubber ring set on the socket head, straight and not twisted. Counterpart inserted into the socket, the center of the two sections of the pipe straight, tensioning equipment using 10t hand-held hoists to tighten in place, welding.
5, layered backfill soil, tamping - pipeline construction is complete, 250mm for a layer of backfill soil, tamping with a frog tamper.
6, pipeline inspection wells and other structures near the backfill soil using flat plate vibration tamper two-way symmetrical tamping.
Volume 7 main construction machinery and equipment
Table 7-1
Machinery name specifications, performance units Quantity Usage
Excavator W1001 1 Excavator
Car Crane 8 1 Lifting Pipeline
Bulldozer T3-100 2 Leveling the site
Dump Truck 4.5t TBD. Transportation of sludge (quantity to be adjusted according to the distance)
Concrete mixer J4-1500 Type 2 Stirring concrete
Mortar mixer HJ-200 Type 2 Stirring mortar
Submersible pump 2# Type 2 Precipitation
Welder
BX3-300-2 Type 2 Welding steel pipe
Water hose bag 3# meters 2000 Conveying Sewage
Frog tamping machine HY-II Type 3 Vibrating backfill soil
Electric toothless saw φ350 Type 2 Cutting rebar
Dump truck 0.5m3 Type 20 Transportation of concrete
Volume 8 Labor organization, team equipment
1) trenching two task forces (40 people)
2) pipeline anticorrosion 1 Team (22 people)
3) Pipeline welding 1 professional team 15)
Volume 9 quality, safety, saving control measures
(a) quality assurance measures
Establishment of the project manager as the head of the quality assurance system, the implementation of the ISO9002 series of standards, the operation of the documented quality assurance system, to strengthen the staff's education on quality awareness, and conscientiously implement the quality of Special inspection, self-inspection, mutual inspection, process handover, weekly quality inspection.
Make good measurement control, protect the measurement mark, often retesting and testing, to ensure that the position and elevation of each pipe culvert is correct.
Conscientiously make construction records, construction technical summary and the original data, to complete information, and timely filing in the water closure test, the first brick plug removal, and then demolition of the dam. Demolition of attention from the dam respectively to the two sides of the demolition, the dam in the grass bags and soil are demolished without leaving the root of the dam, demolition of debris are transported, and clean up the river slopes. Gate well construction, pay attention to the settlement joint construction must be in accordance with the above operation process construction, to ensure that the water stopper does not leakage. Concrete construction, to ensure that their own water does not leak, horizontal joints are strictly dealt with.
For the characteristics of the project, set the quality control points are:
a, pumping station outlet reinforced concrete works
b, sewage pipe installation and interface.
c, steel pipe installation and welding
(2) safety measures
1. Strengthen the safety education of the workers, strict implementation of the production safety system and operating procedures, and make a good safety handover to ensure that the whole process of safe construction. Strengthen the safety inspection, set up a full-time and non-discharge safety officer. Regular inspection of the construction site.
2. Keep the site transportation road unobstructed, strictly control the road slope, turning radius, to ensure the safe operation of vehicles.
3. Strictly control the construction of electricity, the implementation of three-phase five-wire power delivery, to ensure that a machine, a
box, a gate, a leakage. Strengthen mechanical maintenance, inspection, maintenance. Descending with a motor operated by a person, seriously comply with the safe operation of the regulations and instructions for the use of machinery, to prevent overloading operation. Use 36V safe voltage for construction in square culvert. The site is equipped with generators to prevent sudden power outages, causing engineering accidents and affecting construction.
4. pit on both sides of the safety railing, height h ≮ 1.2m have a safety team responsible for safety inspections found to exist in the immediate elimination of potential safety hazards.
5. Large machinery (excavators, etc.) to set up a person to direct.
6. Living area fire prevention measures. The machine is operated and used by a person, and the power is cut off after the shift.
7. Site staff, must wear helmets. Alcoholism is strictly prohibited during working hours, and it is strictly prohibited to take off work without any reason.
(C) saving measures
1. Do a good job of sewage, precipitation, to reduce the amount of dredging.
2. Flexible use of materials to reduce material costs.
3. Material site, 24 hours a material officer send and receive materials, materials into the field, the number must be accurate, there are three certificates. Materials are neatly stacked, reasonably arranged, no secondary handling.
4. The distribution of materials, according to the limit of the single distribution, not more than one, to avoid waste. If there is any surplus of reusable materials, they are immediately recycled.
Volume 10 Civilized Construction:
1. Site appearance:
1) The site should always be flat, clean, smooth drainage, no littering.
2) in line with the "first life, then production" principle, in order to make the site workers and management personnel life is guaranteed, for this reason, the site set up office, kitchen, dormitory, bathrooms, toilets, etc., for the site personnel to create a good living environment.
2, material stacking: on-site materials, machinery and equipment, semi-finished products are classified according to the location shown in the floor plan stacking, and set up a good signage. Machinery and equipment are maintained on time, parked neatly, and ensure that the machine appearance is neat and intact.
3, environmental health:
1) the construction site of the living hygiene, into the overall plan of the site, a full-time health management personnel and cleaning staff, the development of health management system, set up the necessary sanitation facilities.
2) the canteen to take standardized management, in line with the "Food Sanitation Law", there are isolation of flies and rats precautions, there is a meal covered containers. Do a good job of eliminating du sterilization, prevention of disease transmission, construction and living garbage at any time to remove and dispose of.
3) site toilets to keep clean, no maggots less odor, well ventilated, set up a person in charge of cleaning, no open defecation, toilets flushed with water in a timely manner.
Office space is kept clean and tidy, no hanging, littering, scribbling, tables, chairs and cabinets are placed in order, office information is stored neatly, and office facilities are complete and undamaged.
4, comprehensive governance: into the labor force for civilized construction education, improve their awareness of compliance with the law, the site to develop security systems, dormitory management system, finished product protection system and open fire management system. To ensure that the project is completed on time according to the quality and quantity, construction of a party, for the benefit of a party.
Volume 11 excellent measures:
For this project, the company's quality management department is responsible for the quality control of the whole process of the project, the project manager's site management is the key. Therefore, choose to understand the process, understand the technology and have practical construction experience of personnel as quality officer. The personnel of Quality Management Department and Construction Management Department cooperate with the project manager and quality officer to grasp the quality of the project. Project manager, quality clerk to the various construction processes on the operators often carry out quality education, conscientious and responsible, in accordance with the requirements of their duties to ensure the quality of the project. If we find hidden quality problems, we take the quality system as the main body, play its role, nip the hidden quality problems in the bud, the specific approach is: quality clerk to the scene of the hidden quality problems found on the summary up, analyze and come up with specific solutions, as soon as possible, to guide the construction team to improve the improvement of the improvement of the report to the Department of Quality Management, the Ministry of Construction Management and the project manager to participate in the quality management department of the quality of the hidden problems to make the rectification of the opinions And do a good job of correcting and preventing tracking records. Through this can achieve a clear division of labor on-site quality supervision, but also to achieve the role of layer by layer control. In addition, the quality management department, construction management department can also be found in the construction process of the quality of hidden trouble directly put forward corrective comments, the project manager should be immediately corrected, the quality management department to do the relevant records.
1, the quality management of the project to fully implement the "Zhoukou Municipal Engineering Construction Technical Regulations", "Zhoukou Municipal Engineering Quality Inspection and Evaluation Standards" in the standards and procedures for the document requirements, and in this way to monitor the whole process of construction.
2, quality assurance system once established, all agencies must obey the command, one level to one level of accountability, respect for supervision, absolute obedience to the supervision of the management.
3, quality officer and construction of the main person in charge of the project in accordance with the characteristics of the project and the technology to be carried out in advance of the quality and technical training, and let all the construction personnel are clear about the project's quality assurance system and technical quality requirements.
4, the construction team to each process and technology construction standards and acceptance criteria for construction.
5, the quality officer should be based on the construction standard and acceptance specification of each process and technology, to the construction team to put forward quality requirements and quality objectives.
6, sub-parts of the project every step to complete the self-inspection and quality officer self-inspection, and make the appropriate records.
7, the material clerk should cooperate with the quality clerk to verify and accept the customer's equipment, materials and self-supplied equipment and materials, and collect the test data and product qualification certificates and so on.
8, the data clerk should be hidden works and each process in a timely manner to summarize the information, fill out the reports, stay on file, reported to the supervising engineer, the completion of the data according to the customer's request to summarize the delivery of inspection.
9, all materials used in the project, finished products, semi-finished products must have a certificate of conformity.
10, the test of raw materials, finished products, semi-finished products for inspection, so that the test content is complete.
11, self-inspection of finished products formed in the construction, strict control of hidden works acceptance, carefully carry out the handover and acceptance of the project, self-inspection before acceptance, so that unqualified processes are not transferred to the sequence, in strict accordance with the three inspection system, hidden acceptance system implementation, failure to pass the acceptance of the process of immediate rework.
12, regular quality meetings, once a week, to improve the quality of construction team personnel awareness.
13, strict screening of construction teams, improve the construction of all personnel "quality consciousness.
14, measuring instruments set up special custody, regular inspection.
15, the establishment of finished product protection system, the responsibility of implementation.
16, construction and measurement synchronization, parts and processes acceptance synchronization, completion and data synchronization, completion and delivery synchronization.