How to write the final payment of the project?

1, cover, including contract name, construction unit and completion date.

2. Contents.

3, the completion settlement application form.

4, the construction unit project settlement to submit data and data compliance audit list.

5. Power of attorney.

6. settlement book has completed.

7. Engineering visa summary table, visa form and corresponding attachments.

8. Design change summary table, design change order and corresponding attachments.

9, materials, equipment nuclear price table.

10, meeting minutes and letters.

1 1. List of public works used by the construction unit.

12, fined.

13, commencement report and completion acceptance report.

14, project completion drawing.

15, construction organization design.

16, Contract and Supplementary Agreement.

17, other materials related to project settlement that affect the cost.

18. Provide electronic documents of settlement book.