1, the list of sub-parts of the project should be noted when the offer:
(1) review the amount of work in the list of quantities of sub-parts of the project and whether the project is accurate.
(2) Study the characterization of items in the list of quantities of sub-elements.
(3) Performs the calculation of the comprehensive unit price of the list.
In engineering practice, there are two main methods of grouping the comprehensive unit price: 1) calculation based on the fixed amount, 2) estimation based on the actual cost.
(4) according to the bidding strategy, combined with their own strength to adjust the comprehensive unit price of the bill of quantities.
(5) Preparation of list price list of component works, item code, item name, item characteristics, item unit of measurement and quantity of works in the list price list of component works must be consistent with the list provided in the bidding documents, and the bidding unit only fills in the list of comprehensive unit price and total price (including sub-item total price and the total total of the list of sub-items).
2, the measures of the project bill of quantities
In view of the list of measures proposed by the list compiler of the project bill of quantities is based on the general situation, without taking into account the different bidders of the "individuality", the bidders can be quoted according to the actual situation of the enterprise to increase or decrease the cost of the project content of the measures quoted. Contractor in the measures of the project bill of quantities pricing, according to the preparation of the construction program or construction organization design, for the measures of the project bill of quantities that do not occur, the cost can be filled to zero; for the actual need to occur and the bill of quantities of the project does not have, you can fill in the increase, and quote.
Measure project bill of quantities pricing table to "item" as a unit, fill in the corresponding amount required.
The cost of each measure project should be calculated in accordance with the provisions of the bidding documents, accordingly, the use of comprehensive unit price or total price per measure project.
It should be noted that the cost of civilized construction, safety construction and temporary facilities of the measure items shall be calculated in accordance with the requirements of the Provisions on the Administration of Costs and Uses of Safety Protection and Civilized Construction Measures for Construction Projects issued by the Ministry of Construction, based on the standards stipulated by the competent national or provincial and industrial construction authorities, and shall not be subject to competition.
3. Bill of Quantity Pricing for Other Items
1) In bill of quantity pricing for other items, the provisional amount must be filled in according to the amount set out in the bidding documents, and shall not be increased or decreased;
2) The provisional price of materials shall be included in the comprehensive unit price according to the unit price given in the provisional material price bid provided by the bidder, and the provisional price of professional works shall be filled in according to the amount set out by the bidder in the other items list
3) Day laborers shall independently determine the comprehensive unit price and calculate the total according to the items and quantities listed by the bidders in the list of other items
4) The amount of the general contracting service fee may be determined according to the actual estimated cost according to the instructions in the bidding documents or according to the calculation method stipulated by the relevant cost management department;
4. Fees and Taxes The calculation of
Fees and taxes should be calculated in accordance with the provisions of the national and provincial construction administrative departments, fees do not participate in the competition, so the bidding should be raised or lowered will be the fees quoted, otherwise there is no hope of winning the bid.
5, other relevant forms of filling
Should be in accordance with the bidding documents require contractors to submit a bid to fill in the relevant forms provided. Such as the "partial list of quantities of work comprehensive unit price analysis table" "measures project cost analysis table", "the main material price list" and other.