I. List of Quantity of Sub-items
1, four uniform: code, name, unit, rules
2?List code: 12 digits, the first 9 digits of the national unified code, the last 3 digits by the compiler according to the setting of the list of items compiled.
Project name setting
A, pricing specification appendix project name
B, pricing specification of the project characteristics
C, the proposed project
Missing items can be programmed to supplement the project code in the column with the "fill in" shown.
3, the difference between the budget quota and the list of items: the former according to process points, the latter according to the integrated entity.
Two: the list of measures
1, measures to take into account the preparation of the project
2, measures to take
General project: all professions are available
Specialized projects: the professional engineering available
Three, the list of other items
Provisional amount
General contracting service fee
Day labor
Provisional estimate
Expanded informationSignificance: in the cost management reform in the pricing model of the reform of the first, electric power project cost management reform can not be separated from the national economic system reform, so the establishment of a market-oriented market mechanism for the formation of the project price is also the electric power project pricing system is the core of one of the aspects of the reform and inevitable road.
Role: the implementation of bill of quantities pricing, is conducive to the transformation of the government management function of China's project cost. The implementation of the bill of quantities juice price, will be controlled by the government in the past the directive quota pricing into the development of suitable for the laws of the market economy needs of the bill of quantities pricing method, from the past direct government intervention into the project cost supervision in accordance with the law, and effectively strengthen the government on the macro-control of the project cost.
The use of the bill of quantities to prepare tender documents and pricing advantages
(a) to provide a fair basis for competition in the bidding
(b) the bidding has to take advantage of the quality and quantity of the combination of bidding enterprises must take into account the bidding documents to complete the bill of quantities of all the costs required, not only to take into account the actual situation of the project itself but also requires companies to schedule, quality of workmanship and management techniques and other programs to the list of items implemented. Management techniques and other programs implemented into the list of items quoted in the competition to truly reflect the comprehensive strength of the enterprise
(c) is conducive to the reasonable sharing of risk
(d) dilute the role of the bidding process, is conducive to the management and control of the bidding process
(e) to promote the establishment of the enterprise's own quota library
(f) is conducive to the control of engineering claims.