①10 million or less at a rate of 1.5%, such as the project budget of 10 million yuan, the rate = 1000 × 1.5% = 150,000 yuan;
② 1001-50 million yuan at a rate of 1.2%, such as the project budget of 50 million yuan, the rate = 15 + (5000-1000) × 1.2% = 630,000 yuan;
③ construction unit management fee calculated in accordance with Table 4-1 rate of 1.1 times.
3) 5001-1000000 yuan at 1% rate, such as the project budget of 100000000 yuan, the rate = 63 + (10000-5000) × 1% = 1130000 yuan;
4) 10001-5000000 yuan at 0.8% rate, such as the project budget of 500000000 yuan, the rate = 113 + (50000-10000) × 0.8% = 1130000 yuan;
4) 10001-5000000 yuan at 0.8% rate, such as the project budget of 500000000 yuan, the rate = 113 + (50000-10000) × 0.2% rate; < 10000)×0.8%=4.33 million yuan;
⑤50001-1000000 yuan to be charged at the rate of 0.5%, if the project budget is 100000000 yuan, the rate=433+(100000-5000000)×0.5%=6.83 million yuan;
6100001-2000000 yuan to be charged at the rate of 0.2%, if the project budget is 200000000 yuan, the rate=433+(100000-50000)×0.5%=6.83 million yuan;
6100001-200000 yuan to be Charge, such as the project budget of 200,000,000 yuan, the rate = 683 + (200000-100000) × 0.2% = 8.83 million yuan;
⑦ 200000 more than 0.1% rate, such as the project budget of 280,000, the rate = 883 + (280,000-200000) × 0.1% = 9.63 million yuan.
2, the construction unit is the investor of the construction project, the project has property rights (there are exceptions, such as: A company to build a bridge project, the construction process affects the B company-owned structures, need to renovate, reinforcement, agreed by the B company, entrusted to the construction of the C company; at this time, the A company for the capital, A for the construction unit, the property rights of all owners of B, the owner of the B company.)
3, the construction unit management fee refers to the construction unit for the construction project project, preparation, construction, completion (handover) acceptance, summary of the work incurred. Does not include the construction unit should be included in the budget price of equipment, materials, construction unit procurement and storage of equipment and materials required.