Beijing 01 quota in the fee is how to take the fee, Guanglinda how to take the fee?

1. Measure fee in the list = the relevant subheading in the fixed amount, such as mechanical fee, super-high fee, template, etc. in the list belongs to the measure fee, respectively, in the fixed amount of the corresponding subheading.

2. The fees in the list and the provisions of the Beijing 2001 quota, see the "Beijing construction fixed [2003] No. 5" text, as follows:

Notice on the implementation of the "Specification for the Bill of Quantity Pricing of Construction Works" on the relevant issues

Beijing Construction Fixed [2003] No. 5

Related units:

In order to ensure the implementation of national standards of the Specification for Bill of Quantity Pricing of Construction Works" GB50500-2003, on July 1, 2003 in the city to implement smoothly, standardize the city's construction works bill of quantities pricing behavior, the Beijing Municipal Construction Commission issued the Beijing Construction Economy [2003] No. 340 "on the implementation of the implementation of the" Specification for Bill of Quantity Pricing of Construction Works "implementation of the views of the ". According to the "implementation of the spirit of the opinion", now combined with the 2001 "Beijing construction budget quota" (hereinafter referred to as the 2001 budget quota), on the relevant issues are notified as follows:

One of the bill of quantities of works in the bill of quantities of pricing refers to the government and the relevant departments of the mandatory payment of fees. 2001 budget quota of fees included in the budget quota. The fees included in the budget quota and the basis of measurement:

1. housing fund (Beijing Municipal Bureau of Finance, Beijing Caijian (1995) No. 1144 "forwarding the Ministry of Finance on the issuance of a number of financial issues on the reform of the housing system of the enterprise's notice of financial issues")

2. the basic medical insurance fund (Beijing Municipal People's Government Decree No. 68, "the basic medical insurance fund"). Beijing Municipal People's Government Decree No. 68 "Beijing Municipal Basic Medical Insurance Regulations").

3. Basic Pension Insurance Premiums (Decree No. 2 of the Beijing Municipal People's Government "Provisions on Pension Insurance for Urban Workers in Beijing Enterprises").

4. Unemployment Insurance Fund (Decree No. 38 of the Beijing Municipal People's Government "Regulations on Unemployment Insurance of Beijing Municipality").

5. Work Injury Insurance Fund (Decree No. 48 of the Beijing Municipal People's Government "Provisions on Work Injury Insurance for Urban Workers in Beijing Enterprises").

6. Employment Guarantee Fund for the Disabled (Beijing Municipal Bureau of Finance and Beijing Municipal Federation of the Disabled, Beijing CaiShe (1995) No. 457, "Notice on Transmitting the Interim Provisions on the Administration of the Employment Guarantee Fund for the Disabled Issued by the Ministry of Finance").

2001 budget fixed labor cost unit price and site funds in the pension insurance and medical insurance, enterprise management fees in the social security and other cost content, in the preparation of the tender, can refer to the following ratio included in the fee.

No.

Item name

Base

Proportion (%)

1

Unit price of labor fee

Corresponding unit price of labor fee

18.73

2

On-site funding

Corresponding rate

14.45

3

Enterprise management fee

Corresponding rate

29.16

When bidding for the offer, the enterprise may determine or refer to the above rate to be included in the fee according to the provisions of relevant documents.

Two, in the bill of quantities pricing, the calculation and preparation of the comprehensive unit price is determined according to the following program table:

1. Direct cost as the basis for calculation

No.

Item name

Calculation formula

1

Labor cost

Consumption of work days × unit price

2

Material Costs

Material Consumption x Unit Price

3

Mechanical Usage Costs

Mechanical Consumption x Unit Price

4

Subtotal

(1) + (2) + (3)

5

Site Expenses

(4) x Rate

6

Direct costs

(4) + (5)

7

Corporate overhead

(6) x rate

8

Profit

[(6) + (7)] x rate

9

Risk costs

(6) x rate

10

Consolidated unit price

(6) + (7) + (8) + (9)

In determining the unit price of labor, the rate of site provision and the rate of corporate overheads, no account shall be taken of what has been included in the first regulation.

Third, the other costs of the relevant instructions:

1. Material secondary handling costs 2001 budget fixed base price, the material included in the secondary handling costs refers to the construction materials, finished products, semi-finished products and accessories, such as on-site and off-site transportation costs. In the preparation of the bill of quantities, should be included in the list of sub-projects; due to the construction site is small (construction land area less than three times the first floor area) and other special circumstances and the occurrence of building materials, finished products, semi-finished products and accessories, such as construction site outside the second handling costs (including transportation and handling costs), should be included in the list of measures.

2. Winter and rainy season construction increase 2001 budget fixed base price, including the winter and rainy season construction increase refers to the winter and rainy season construction during the rain, heat preservation, to ensure the quality of the project and other costs required for winter and rainy season construction of labor efficiency. In the preparation of the bill of quantities, should be included in the list of component items; due to the rainy season flood control measures or winter construction heating measures adopted by the costs incurred, should be included in the list of measures.

3. Finished product protection costs 2001 budget fixed base price, has included the construction process of general finished product protection costs. In the preparation of the bill of quantities, should be included in the list of items; for the completion and acceptance of the completed project and equipment for the protection of the measures taken by the cost, should be included in the list of measures.

4. Night construction costs 2001 budget quota, including the normal construction process of night construction lighting consumed electricity. In the preparation of the bill of quantities, should be included in the list of sub-projects; due to the owner's request to shorten the construction period, increase the night construction and other reasons, night construction of the night shift subsidies, night construction of efficiency, night construction of lighting equipment amortization costs, etc., should be included in the list of measures.

Beijing Construction Project Cost Management Office

June 30, 2003