1, construction site quality management inspection records;
2, drawing review records; the existence of design changes and engineering negotiation, should also check the design change records and engineering negotiation records
3, equipment and materials into the field inspection records and equipment unpacking inspection records;
4, Record of acceptance of concealed works (checking with the work);
5. Record of acceptance of installation quality and visual quality;
6. Record of self-inspection;
7. Record of acceptance of quality of sub-items;
8. Record of trial operation.
(b) construction site quality management inspection records should be filled out by the construction unit, the project supervision agency superintendent engineer (or construction unit project manager) to make the conclusion of the inspection, and the format of the record should be in line with the provisions of Appendix A of this specification.
(C) drawing review records, design change records and engineering negotiation records should be consistent with the current national standard "intelligent building engineering construction specification" GB 50606.
(d) equipment and materials into the field inspection records and equipment unpacking inspection records shall comply with the following provisions:
1, equipment and materials into the field inspection records should be filled out by the construction unit, supervision (construction) unit of the supervisory engineers (project professional engineering
Division) to make a conclusion of the inspection and the format of the records should be consistent with the provisions of Appendix B of the specification of the Table B.0.1;
2, equipment unboxing inspection records shall comply with the current national standard "intelligent building engineering construction specification" GB 50606.
(E) hidden works (check with the work) acceptance records should be filled out by the construction unit, supervision (construction) unit of supervision engineers (project professional engineers) to make a conclusion of the inspection, and the format of the records should be in line with the provisions of this specification, Appendix B, Table B.0.2.
(F) installation quality and visual quality acceptance record shall be completed by the construction unit, supervision (construction) unit of supervision engineers (project professional engineers) to make the conclusions of the inspection, and the format of the record shall comply with the provisions of this specification appendix B table B.0.3.
(VII) self-inspection records filled out by the construction unit, the construction unit's professional and technical personnel to make inspection conclusions, and the format of the record should be consistent with the provisions of Appendix B of this specification Table B.0.4.
(h) sub-project quality acceptance record should be filled out by the construction unit, the construction unit of professional and technical personnel to make inspection conclusions, supervision (construction) unit of supervision engineers (project professional and technical person in charge) to make acceptance conclusions, and the format of the record should be in line with the specification of the table in appendix B, B.0.5 of the provisions.
(ix) test run record should be filled out by the construction unit, supervision (construction) unit of supervision engineers (project professional engineer) to make the conclusion of the inspection, and the format of the record should be in line with the provisions of this specification appendix B table B.0.6.
(J) In addition to checking the contents stipulated in Article 3.2.4 of this specification, the quality control of software products shall also check the documentation and technical indexes, and shall conform to the following provisions:
1. The license and scope of use of commercial software shall conform to the contractual requirements;
2. For the application software prepared for the engineering project, the functionality and performance of the test report shall conform to the contractual requirements of the engineering project. test results shall meet the contractual requirements of the project.
(xi) In addition to checking the contents stipulated in Article 3.2.4 of this specification, the quality control of interfaces shall also conform to the following provisions:
1. The interface technical documents shall conform to the requirements of the contract; the interface technical documents shall include an overview of the interfaces, interface block diagrams, interface positions, interface types and quantities, interface communication protocols, data flow, and interface responsibility boundaries, etc.
2. p>2, according to the actual situation of the project revised interface technical documents should be signed by the construction unit, the design unit, the interface unit and the construction unit to confirm;
Intelligent Building Engineering Quality Acceptance Specification and the development of our country's current national standards are complementary, so the acceptance of the quality of intelligent building engineering not only to comply with the intelligent building engineering quality acceptance specification formulated Standards should also comply with the current national standards, so that the quality of intelligent building projects qualified to meet the standard.