Before the article begins, the first thing to note: this example applies to Anhui local standards, other regions can refer to
1, the date of commencement, date of completion, date of operation, test date in the report of the unity of the issue; date of request for instructions and the order of the visa date.
2, the preliminary information and test, test batch easy to miss less installed; attention to the feasibility study report, project proposal, plan mission statement, start report, project management planning, design submission, drawing submission, preliminary design and budget estimates for approval of the date of the sequence of the report signature handwriting unity; the signer identity accuracy issues.
3, test reports, engineering acceptance, engineering hidden information, individual types of inspection reports, construction records, events and supervision log process content, date to be unified.
4, equipment and building materials into the field when the quality certificate and test report is complete, which test report has a quality certification chapter and test unit chapter, quality certificate has a construction unit warranty chapter, delivery unit chapter and manufacturer chapter three chapters. The date of the project hidden information and the date of individual types of inspection reports, construction diaries, etc. Whether the date between the various types of information cross-circle.
(1) equipment packing list need not be stamped, there are packing signature.
(2) equipment inspection needs to be stamped.
(3) electrical equipment adjustment test records signing order: team, construction team, project department, supervision. Test records to be consistent with the content of the supervision log records.
(4)Reinforcing steel
①Quality specification: provided by the production unit, stamped with three chapters: Anhui Transmission and Transformer Warranty Special Chapter, the production unit quality special chapter and quality inspection chapter.
② test report (re-inspection): the test unit construction engineering quality testing center, commissioned by the unit: Transmission Company, stamped with two chapters: MA Quantity Recognition (Anhui) word chapter and construction engineering selection testing center test special chapter.
Note that the factory date in the front, send test date, test date, report date in turn after.
(5) cement
① Cement quality inspection report form: the manufacturer to provide, manufacturers of quality inspection special seal, the person in charge, the report signed.
② cement inspection report: the test unit construction engineering quality testing center, commissioned by the unit: Transmission Company, stamped with two chapters: MA Quantity Recognition (Anhui) word chapter and the construction engineering selection testing center test special chapter.
Note that the factory date in the front, send test date, test date, report date in turn after.
(6) gravel test report: provided by the test unit construction engineering quality testing center, commissioned by the unit: power transmission company, stamped with two chapters: MA volume recognition (Anhui) word chapter and the construction engineering selection testing center test special seal; inspection unit, technical responsible person, audit, inspector's signature.
Note that the factory date in front, send test date, test date, report date in turn after.
(7) brick
① brick inspection report: manufacturers to send for inspection, product quality supervision and inspection of the report, stamped with two chapters, manufacturer's chapter and product quality supervision and inspection of the inspection of the special seal, approval, audit, preparation of the signature of the person.
② brick test report: the test unit construction engineering quality testing center to provide, commissioned by the unit: Transmission Company, stamped with two chapters: MA Quantity Recognition (Anhui) word chapter and the construction engineering selection testing center test special chapter.
Note that the factory date in the front, send test date, test date, report date in turn after.
(8) concrete and mortar
1) concrete and mortar proportion notification form: provided by the test unit construction engineering quality testing center, commissioned by the unit: Transmission Company, stamped with two chapters: MA volume recognition (Anhui) word chapter and construction engineering selected testing center test special seal. Test unit, technical responsible person, audit, inspector signature.
② concrete compressive strength test report: the test unit construction engineering quality testing center, commissioned by the unit: power transmission company, stamped with two stamps: MA volume recognition (Anhui) word chapter and construction engineering selection testing center test special chapter. Technology responsible for, audit tester signature.
3 mortar compressive strength test report: provided by the test unit construction engineering quality testing center, commissioned by the unit: power transmission company, stamped with two stamps: MA volume recognition (Anhui) word chapter and construction engineering selection testing center test special seal.
Note that the factory date in front, send test date, test date, report date in turn after. Inspection unit, the technical person in charge, audit, inspector signature.
4 mortar strength assessment form: supervision, assessor's signature.
(9) soil sample density test report: provided by the test unit construction engineering quality testing center, commissioned by the unit: power transmission company, stamped with two chapters: MA quantitative recognition (Anhui) word chapter and construction engineering selection testing center test special chapter.
Note that the factory date in front, the date of delivery of the test, the test date, the date of the report in turn after. The technical person in charge, audit, the tester's signature.
(10) waterproof coatings, waterproofing roll-roofing, manhole covers, doors
①Product certification: manufacturer's quality control seal, date of production, name, inspector, implementation standards. If the product is a foreign province, there should also be the province's quality supervision department inspection report.
② production province inspection report: the location of the production plant building materials product quality supervision and inspection station out of the report, the manufacturer's special seal, approval, audit, signature of the chief inspector.
③ province inspection report: the use of building construction quality supervision and inspection station inspection report,, stamped with two chapters, testing station chapter and MA chapter.
(11) components:
① Product quality specification: manufacturer's quality seal and merchant seal.
② Inspection report: cement products quality supervision and inspection station out of the report, the manufacturer's special chapter and quality supervision and inspection station special chapter. Attached page with the seal. Components do not need to do the test, so no test report. Approval, inspection, audit signature.
(12) profiles:
① Certificate of Conformity: manufacturer's special seal of quality control. Product name, specification number, contract number, batch size, implementation standards, inspection conclusions, quality inspector, factory date.
② Profile quality inspection report form: manufacturers of quality inspection seal.
(13) steel:
Inspection report: Product Quality Supervision and Inspection Institute chapter and manufacturer's chapter.
(14) paint: product certification manufacturer's seal.
(15) building materials: merchant chapter, quality supervision and testing center inspection seal.
(16) equipment packing list: Certificate of Conformity: model, factory number, name, inspector, factory date, inspector, factory inspection seal.
(17) packing list: equipment name, project name, contract number, plan number; packing person, inspector signature.
(18) product inspection report has the manufacturer's quality inspection seal.
(19) electrical equipment test report: stamped by the manufacturer, the inspector, the person in charge of quality, the date of the test with the inspection department signatures and stamps. Test procedures according to the specification, the date of the test report to be consistent with the date recorded in the supervision log.
(20) transformer product test certificate and test report: factory documents, factory information, transformer data and installation and use instructions.
(21) welded steel pipe: product quality certificate provided by the manufacturer, stamped with the manufacturer and merchant chapter.
(22)Pipe: cement products quality supervision and inspection station out of the report, the manufacturer to send inspection, on the manufacturer's chapter and cement products quality supervision and inspection station chapter.
(23)Decorative materials:
①Product factory inspection reports provided by the manufacturer, with the manufacturer's inspection seal.
② National Center for Quality Supervision and Inspection of Chemical Building Materials report, businesses or manufacturers to send inspection, stamped with the National Center for Quality Supervision and Inspection of Chemical Building Materials chapter.
(24) anti-static activity floor: the Ministry of Information Industry, anti-static product quality supervision and inspection center report, the production of three sent for inspection, stamped with the Ministry of Information Industry, anti-static product quality supervision and inspection center chapter.
(25) completely glass stone: manufacturers to send inspection, the National Quality Supervision and Inspection Center for Building Sanitary Ceramics report, stamped with the National Quality Supervision and Inspection Center for Building Sanitary Ceramics chapter and manufacturer's chapter.
(26) aluminum alloy grooved keel main, high strength gypsum calcium silicate ceiling, tiles, etc.: the manufacturer to send inspection, the National Building Materials Industry Decoration Building Materials Quality Supervision, Inspection and Testing Center out of the report, stamped with the manufacturer's chapter and the National Building Materials Industry Decoration Building Materials Quality Supervision, Inspection and Testing Center out of the report chapter.
(27) Yashi multifunctional square shell model high elasticity coating:
① quality certificate;
② production plant inspection, the National Center for Quality Supervision and Inspection of Chemical Building Materials inspection and report, stamped with the production plant chapter and the National Center for Quality Supervision and Inspection of Chemical Building Materials chapter.
(28) Polar Bear brand strong universal adhesive: production plant inspection, Guangdong Product Quality Supervision and Inspection Center and the Guangdong Provincial Paint Product Quality Supervision and Inspection Station report, and stamped with the manufacturer's chapter, the Guangdong Provincial Product Quality Supervision and Inspection Center chapter and the Guangdong Provincial Paint Product Quality Supervision and Inspection Station chapter.
(29) laminate flooring certificate: manufacturer's product certification; the implementation of the standard GB/T18102-2000, formaldehyde emission standards: E1; Grade: Qualified Products; inspector's signature; date of production; stamped with the manufacturer's chapter. No inspection.
(30) water tank fittings: manufacturer's product certification; Grade: excellent; inspector: check 5, inspection date; no another inspection report.
(31) power poles product qualification certificate: manufacturing plant (anhui power transmission and transformation engineering company prefabricated components factory) chapter, the person in charge of quality and quality inspector signature.
(32) frame beams, lightning arrester, ladder and other products certificate of conformity: the manufacturer of electric railroad manufacturing joint-stock cooperative company issued a certificate, the manufacturer's quality inspection section cover sheet. (No inspection report)
(33) standard parts products factory quality certification: the manufacturer's quality inspection section signed and stamped.
(34) construction of insulated electrical casing: certificate of conformity of the manufacturer's seal and the provincial product quality supervision and inspection center of the special seal of inspection.
5, whether the design changes in the project documents specifically reflected (hidden acceptance, etc.)
6, the need for all parties to the main body of the unit signed and stamped the accuracy of the information, completeness should be high, such as foundation groove inspection records, foundation division of the quality of the project acceptance records, the main body of the quality of the project acceptance records, etc..
7, the accuracy and completeness of the information related to the safety of the main structure should be high, such as concrete, masonry raw material certification and test reports, various test block reports and ratings.
8, involving the use of the building to affect the accuracy and completeness of the information to be high, such as the exterior walls, bathrooms, house test water, aluminum window inspection.
9, test information and the actual inconsistency, such as the test batch of rebar test is not greater than 60T, while the site of the actual rebar varieties, types of goods are often not greater than 60T, the date of rebar and the date of the test does not match the representative of the amount of rebar is also easy to be inconsistent with the certificate of conformity.
10, electrical construction test records focus: electrical commissioning, adjustment records, transformer core inspection records, energization and full load records, grounding and insulation test records
More about the engineering/service/procurement category of the tender writing production, enhance the rate of winning the bid, you can click on the bottom of the official website of the customer service for free advice:/#/?source=bdzd