201X Hospital Preparation Project Acceptance Request Report
Report.com authoritatively released 201X Hospital Preparation Project Acceptance Request Report, for more information about 2018 Hospital Preparation Project Acceptance Request Report, please visit Report.com.
xx Municipal Health Bureau:
xxxx hospital after nearly two years of preparatory work is now basically completed, basically with opening conditions. Now the hospital acceptance report and all the information is submitted, please grant acceptance and guidance for the hope.
Hereby
Salute
xxxx Hospital Preparation Group
December 19, 201X
First, the basic situation of the hospital:
Since April 10, 2012, we received the approval of the municipal bureau of the set up of medical institutions since the instrument, in the leadership at all levels and the relevant departments of the care and help, the work progresses smoothly, the work completed better. The work has been completed well. In the early stage, according to the hospital functions and departments set up to complete the decoration and supporting facilities, recruitment of various types of professionals at all levels, the introduction of technical personnel, the purchase of various types of large and medium-sized medical equipment. Some of them are entering the stage of installation and commissioning one after another. The construction of various systems and the training of all staff have been completed. According to the current situation of the hospital, has basically with the opening conditions, please leaders, experts to further work guidance.
Second, the hospital department set up:
Third, the hospital staff composition:
At present, the total number of hospital employees 121 for people. High, middle and junior levels of personnel of all kinds of basic in place, the structure is reasonable, can meet the needs of clinical medical work. (Attached personnel roster)
Fourth, the hospital system construction:
In order to strengthen the quality of medical management, to prevent medical errors and accidents, and further improve the quality of medical care and medical level, to better serve the people's health. According to the actual situation of our hospital, we have formulated various medical rules and regulations, administrative management system, medical and nursing technical operation procedures, hospital emergency plans and staff manuals, etc., and compiled and printed into a booklet for the convenience of employees to learn. The establishment of the above systems will undoubtedly provide sufficient protection to strengthen and improve the management of our hospital, standardize medical behavior, further improve the quality of medical care and promote the healthy development of the hospital. (Attached to the regulations of medical institutions, medical institutions, technical regulations)
V. Basic equipment acquisition:
According to the needs of the hospital's business work, equipped with various types of clinical medical equipment, these equipment arrived one after another, part of the installation debugging is still underway. Outpatient wards of the basic equipment, infrastructure are readily available to meet the needs of clinical medical work. (With a list of equipment)
Six, the hospital staff training:
In order to further improve the quality of staff, to fully explore the potential of each employee, and constantly enhance the staff's awareness of the ideology, work consciousness, sense of responsibility, sense of service, and to establish the spirit of hard work, dedication, devotion, teamwork; the hospital attaches great importance to the training of staff, and has carried out a variety of training on the entire staff. Various types of training. We also organized staff to learn different knowledge of hospital rules and regulations, technical operation procedures, infectious disease prevention and control law, knowledge of nosocomial infections, knowledge of disinfection and isolation, and disposal of medical waste. We also organized lectures on fire fighting knowledge, thus enabling the staff to enhance their fire fighting awareness, learn fire fighting knowledge, avoid and eliminate the occurrence of potentially dangerous factors, and safeguard, collective, individual life and property safety. The hospital often organizes business lectures for its staff to continuously improve their business knowledge and skills, enhance their academic awareness and level of learning, thus improving their medical knowledge. Above, we do the preparatory work before the opening of the hospital to lay the foundation for the smooth opening of our hospital, the future work of the hospital will also have a positive role in promoting.
VII, disinfection supply room basic situation:
Disinfection supply room is an important department of the hospital, is mainly responsible for the hospital's medical disinfection supply work. In this regard, the hospital leadership attaches great importance to the professional health professionals to guide the construction of the commissioning is now complete, and equipped with senior nursing staff as the head of the department, can meet the hospital disinfection supply work.
Eight, medical waste disposal:
The hospital leadership attaches great importance to the treatment of medical waste. We have signed a medical waste incineration contract with Kangsheng, the hospital's medical waste is all recycled and disposed of by the company.
The hospital has a temporary storage place for medical waste, which is labeled as different storage points for medical waste and domestic waste, and has a person in charge of recycling, and has done a good job of registration. Medical waste temporary storage in line with the requirements of the room closed, locked, anti-rodent, anti-theft, security measures in line with the requirements. Indoor lighting, and the installation of ultraviolet lamps, to achieve regular disinfection, in order to prevent environmental pollution caused by medical waste.
Nine, on the hospital environmental assessment:
The hospital attaches great importance to environmental protection. Medical waste hospital has signed a medical waste incineration contract of intent with Kang Sheng company, the hospital's medical waste is all recycled by the company to dispose of, and became an infection section, the establishment of hospital infection, disinfection and supply, garbage disposal, and other relevant rules and regulations as well as hospital sensory team, to protect the environment and reduce pollution have a positive significance.
In view of the hospital's preparations have been ready, special application for the superior arrangement of experts to visit our hospital acceptance guidance.
Equipment Acceptance Report Template
Equipment Unpacking Acceptance Record
Xxxxxx Unit xx October
I. Appearance Inspection
1. Check the surface and encapsulation status of the outer box;
2. Check the surface of the equipment and accessories for damage, corrosion, bruises, etc., focusing on the inspection of the rotor impeller with or without damage, the main components and the main working surfaces;
3. If you find that there is damage to the package, the equipment and accessories have damage, corrosion, signs of use and so on, you should make a detailed record and focus on the photo Leave a record, timely return to the supplier for replacement, claim procedures.
Second, the number of inspections
1. Quantity inspection should be based on the supply contract and packing list, check the host, accessories and other equipment specifications, models, configurations and quantities, and piece by piece inventory check;
2. Carefully check the completeness of the random information, such as instruction manuals, certificates of conformity of the product inspection, warranty, etc.
3. Serial number and factory number, if necessary, you can check online;
4. Carefully make a good record of unpacking and counting, write down the location, time, participants, box number, product name, should be to the actual number of real, such as found in shortages, misdirection and other issues, we must promptly make a good record and retain the relevant materials.
Third, fill in the acceptance record sheet
1. Box acceptance is completed, found that any one does not meet the requirements of the contract documents, must be recognized by the supplier's representative (signature, seal).
2. Write the equipment opening inspection record sheet, serial number and factory number, field photos as part of the equipment acceptance documents.
Equipment unpacking inspection record sheet
No.
House renovation completion acceptance report
Report.com authoritative release of the report on the completion of the house renovation acceptance report, more information about the report on the completion of the house renovation acceptance report, please visit report.com.
Client:
Client's contact number:
Entrusted with the project acceptance unit:
Project acceptance of participants:
Supervisors:
Project acceptance of the address:
Project acceptance of the completion of the project is based on:
The quality of acceptance of the project quality of the decoration of the family room standards
Project Overview:<
This project is two rooms, two halls and one bathroom, with a floor area of 37 square meters and a floor height of 2.8 meters.
The conclusion of the completion of the acceptance of housing decoration:
First, the project decorative surface layer of multiple hollow drums, cracking (see commissioning order diagram ③ ⑤ ⑧ ⑨ ⑾), the acceptance of the unqualified.
Based on: Standard 9.0.2 putty should be used with water-resistant putty, putty and the substrate combination of solid, firm, not peeling, not chalking, not cracked.
Second, a hall door and door frame paint with brush lines, falling (see commissioning order schematic diagram (12)), the acceptance failed.
Based on: standard 9.0.3 paint surface should be smooth, clean, no leakage of brush, peeling and stains, clear varnish wood grain clear, large surface without wrapping prisms, falling and wrinkled skin, the color is basically the same, no brush lines. Hardware, glass clean.
Third, a hall floor tile drum rate of 20.8%, the second hall floor tile drum rate of 12.5% and bathroom wall tile drum rate of 5.98% (see commissioning order ② ⑩ (13)), the acceptance failed.
Based on: Standard 8.1.4 wall and floor tiling should be smooth and solid, clear pattern, no dirt and pulp marks, the surface color is basically the same, uniform seams, plates without cracks, corners and missing edges, a single plate edge drumming rate shall not exceed 5% of the number.
Fourth, the wall power line is not set of conduit buried directly into the plaster layer, the top power line at the joints are not into the wire box (see commissioning sheet schematic diagram (7)), the acceptance failed.
Based on: Standard 3.0.2 electrical wiring should be used for concealed piping, wires in the pipe should not be kinks and kinks, wires from the telephone line, closed-circuit television line shall not be less than 50 centimeters, ceiling is not allowed to have exposed wires, it is strictly prohibited to bury the wires directly into the plaster layer.
Fifth, the water supply pipe is not fixed, pipe bending (see commissioning order schematic diagram ⑥), the acceptance failed.
According to standard 2.0.2 pipeline installation should be flat and straight, firmly laid, slope in line with the requirements, valves, faucets installed correctly, the use of flexible and easy to use, open pipe brush rust paint, dark pipe brush anticorrosion paint.
Six, bathroom toilet, there are traces of water seepage around the mouth of the water (see the commission single intention ①) due to the lack of water, can not do the water test (solid the results of the results of the water source to be determined).
Reported by: