1 Purpose:

Establish the company's environmental protection management system to ensure that pollutants and noise in the production process are discharged up to standard after treatment, so that production will not have harmful effects on the surrounding environment.

2 scope:

The "three wastes" produced in the production process.

3 responsibility:

Production department, engineering department and various production workshops.

4 content:

4. 1 definition of "three wastes": waste water, waste gas and waste residue produced in the production process that cause pollution or harmful effects on the surrounding environment.

4.2 The production department is specifically responsible for the daily treatment of "three wastes" and environmental protection, and shall set up qualified emission signs for the emission sources that meet the standards.

4.3 Establish the post responsibility system for "three wastes" treatment personnel and implement a strict reward and punishment system.

4.4 The production department is responsible for maintaining environmental protection treatment facilities. When the environmental protection treatment facilities fail, the production process with "three wastes" discharge must be stopped to prevent pollutant discharge.

4.5 Conduct regular business training on environmental protection technology to improve the technical quality of employees.

4.6 Do a good job in greening the plant area, improve the production area and surrounding environment, and accept the supervision, inspection and guidance of the municipal environmental protection department.

4.7 wastewater

4.7. 1 purified water station: waste acid and alkali after resin regeneration and waste acid and alkali after cleaning purified water tank.

4.7.2 Boiler room smoke and dust removal wastewater.

4.7.3 Waste water and domestic sewage generated by workshop production.

4.7.4 The wastewater generated by the purified water station, boiler room and workshop directly enters the wastewater treatment station, and is discharged or reused after being treated up to standard, and the domestic sewage is discharged after being filtered up to standard by a filter.

4.8 Waste gas: pollutants such as flue gas, sulfur dioxide and nitrogen oxides generated by boiler combustion are treated by water curtain dust removal.

4.9 Waste packaging materials and boiler ash produced in the production workshop shall be sold, and there shall be no other stacking places.

4. 10 Power equipment such as air conditioner, air compressor and boiler induced draft fan should have sound insulation, sound absorption and vibration reduction measures.

4. 1 1 Dangerous goods in the company must be stored, kept and destroyed in accordance with the relevant provisions on the management of dangerous goods, and shall not cause pollution to the production area and its surrounding environment.

The above text comes from & gt<< Environmental Management System >> column. If you need more related systems, please go to this column to find them yourself.