There are many problems in the problem reporting mode, whether it is study or work. When we encounter problems, we always sum up the problems and find out the corresponding solutions. Here are several problem reporting models to share with you. Welcome to read the reference.

Problem report model essay 1 Dear Secretary X, leaders,

Hello everyone! First of all, on behalf of all the staff of * * *, I would like to extend a warm welcome to you and your leaders. The leaders expressed their heartfelt thanks to * * * for their concern, concern and support! The following is a brief report on the present situation and subsequent development of our company:

I. Basic information

* * * There are two 600 MW air-cooled desulfurization coal-fired units. The two units were put into production in March and April, 2009 respectively, and put into commercial operation. After entering the production period, the company further promoted the standardization construction, further consolidated the management foundation, further changed the work style, conscientiously implemented the management concept of "four whatevers", and strictly implemented the post responsibility system for all kinds of personnel at all levels, with high standards, strict requirements and refinement. With the goal of creating a first-class enterprise in the group company, the company has fully implemented the three major projects of sunshine, green and happiness, comprehensively carried out the work of striving for Excellence, and strived to create a * * * talent forest and strive to achieve it.

* * * The company has 328 employees, with an average age of 32.7. By June 20th, 20xx, 785 days of safe production, power generation143.56 million kWh, profits and taxes paid 250 million yuan (as of May 20th), and losses of 654.38+22 million yuan (as of May 20th).

Relying on * * * * good investment environment and solar energy resources, * * * planned the 100MW photovoltaic project in * * *, and established a photovoltaic power generation company, which was managed by **8 company. The first phase of 100 MW photovoltaic grid-connected power station was put into operation on February 30th, 20xx.

The power generation has achieved zero breakthrough in the photovoltaic power generation industry, with a cumulative power generation of 7.09 million kWh. * * * also manages two preparatory offices of * * *, namely, the preparatory office for new energy projects in Ningxia and the preparatory office for thermal power projects in Ningxia.

Two. Production and operation in 20xx and its forecast

(a) the current production and operation situation

As of June 20th, 20xx, * * * had no personal injuries or accidents.

Personal accidents, no traffic accidents and public security accidents, and the unit runs stably. From June 5438 to May this year, the power generation was 31.1.700 million kWh. In terms of operation, due to factors such as rising coal prices and changes in interest rates, the operation situation of * * * is more severe. The unit price of standard coal charged into the furnace is 44 1.26 yuan/ton, which is 4.966 yuan/ton higher than that of 20xx, realizing income of 670 million yuan and loss of 32173,500 yuan.

(2) 20xx annual production and operation forecast

From May 26th, the two units of * * * respectively conducted an investigation for about 45 days.

After minor repairs, the health level of the troops will be greatly improved. It is estimated that the annual power generation will be 723,654.38 billion kWh, and the on-grid electricity will be 6.783 billion kWh. However, in view of the current power supply and demand situation and coal price level in Ningxia, it is predicted that the annual operating indicators are: the on-grid electricity price is 268.33 yuan /MWh, the operating income is 65.438+55.6 million yuan, and the main business cost is 65.438+56.0 million yuan, of which the unit price of standard coal for furnace charging is 48.439 yuan/ton, and the coal consumption for power supply is 339 grams/kwh, of which the total profit is -2.3.

Three. Main Work of the Company during the Twelfth Five-Year Plan Period

(1) Technical transformation work

This year, our company plans to invest 654.38+0.3 billion yuan to carry out initial B-level maintenance of two units, focusing on equipment management and energy-saving transformation to improve the stability of unit operation.

Sex and economy. The key items are:

1, reconstruction of heating surfaces of two boilers;

2. Modification of steam seal of steam turbine flow passage of two units:

3. Transformation of starting and standby transformer lines;

4. Upgrade of desulfurization system. Including desulfurization slurry circulating pump, agitator, absorption tower and flue transformation, desulfurization absorption tower agitator transformation, desulfurization slurry circulating pump transformation, desulfurization wastewater system transformation, desulfurization CEMS spare parts procurement.

Energy-saving projects will be carried out in 20xx, such as electrostatic dust removal optimization and air leakage control of air preheater. Through the equipment management and energy-saving transformation in the next few years, the goal of reducing the standard coal consumption of power supply by 3- 10g/kWh will be realized.

(2) Project development plan

20xx is the first year of the Twelfth Five-Year Plan and the second round of western development. * * will continue to focus on the development theme, according to the requirements of * * and the company's overall development strategy, combined with the characteristics of regional resources, accelerate the project construction, project planning and project reserve in Ningxia, grasp the initiative of development, and strive to make positive contributions to the company's long-term development and regional economic prosperity.

1. Make all preparations before the approval of * * * Photovoltaic Phase II (20MW). The project is expected to invest 400 million yuan, and the land pre-examination, environmental assessment review, water and soil conservation plan review and approval of the project have been completed, and the access system report has also been completed. With the support of the Municipal Development and Reform Bureau, the project application report has also been submitted to the Development and Reform Commission of the Autonomous Region, and is currently awaiting the approval of the Development and Reform Commission of the Autonomous Region. After approval, we will conduct equipment bidding and construction preparation as soon as possible.

2. Do a good job in the feasibility study review of the * * * wind power project (48MW), with an investment of about 360 million yuan. At present, the pre-examination of the project land and the review of the soil and water conservation plan have been completed.

The EIA report and the access system report have been compiled, and the project application report has been submitted to the Autonomous Region Development and Reform Commission for approval. After approval, we will carry out equipment bidding and construction preparation as soon as possible, and strive to start construction within the year.

3. Strive for the cooperation project of cogeneration of two 330MW units in * * * new material base. Recently, I have been communicating with the Management Committee of New Materials Base and the Municipal Administration for Industry and Commerce, and actively preparing the project plan. It is also hoped that the municipal government will give strong support to incorporate the "two 330MW cogeneration projects in the new material base" into the development plan of the new material base and smoothly promote the follow-up work.

4. Actively strive for the pre-development right of the fourth phase of the dam project (two 1000MW thermal power projects) from the autonomous region. At present, the power supply situation in some provinces and regions in China is tight, and some provinces and cities also have the phenomenon of "power cut", which shows that the power supply construction is relatively backward. At the same time, the rapid growth of electricity consumption and the increasing transmission tasks in the region also put forward new requirements for the installed capacity in the region. In addition, the National Development and Reform Commission recently indicated that it will adjust the approval plan for thermal power projects, which is a favorable opportunity to actively strive for the fourth phase of the dam project. In addition, the fourth stage of the dam itself has great advantages. First, natural material conditions such as water intake, coal transportation and Internet access are convenient. Second, we can rely on the third phase of the dam to carry out the preliminary and infrastructure construction work, with sufficient personnel and management resources.

5. Expand the coal yard and increase the inventory capacity in the factory. Related to the local coal mine.

Integrate, realize joint venture, and reverse the' passive situation' of enterprise losses.

Four. I hope that the government will pay attention to the issue.

1. I hope the government will give policy support in terms of land use and coal yard expansion for subsequent projects. To speed up the examination and approval of project land.

2. I hope to give some preferential treatment in tax. For example, dam property tax relief,

Land use tax relief, two exemptions and three reductions in income tax relief for photovoltaic enterprises in the "western development", and "income tax relief policy for energy-saving and water-saving special equipment".

3. I hope the government will give some policy support to the coal joint venture.

At present, the state and autonomous region are making great efforts to control the illegal transportation of overloaded roads. As a result, the automobile coal freight rate of enterprises continues to rise, and the coal transportation volume drops sharply. The enterprise's coal-fired inventory has obviously decreased, and the fuel cost has risen sharply, resulting in operating losses, and the production and operation form is very severe. I hope * * * the municipal party committee and municipal government can actively coordinate the coal transportation of enterprises.

5. Water source problem of photovoltaic power station. * * * Photovoltaic grid-connected power station is located on the west side of the new material industry base. Since the construction, water for construction, production, living and environmental greening has been transported outside the station, which greatly restricts the production, construction and development of enterprises. Therefore, we suggest that when planning the infrastructure construction, the municipal party committee and municipal government and the management committee of the new material base can incorporate the * * * photovoltaic power station into the water supply pipe network of the base and lay the water supply pipe network of the park to the photovoltaic power station.

Thank you very much, Secretary Gui and other leaders for coming to * * * for research and guidance. I hope the leaders will give us more valuable advice and give us more support and guidance. In the future work, with the care and support of the * * * Municipal Party Committee and Municipal Government, we will thoroughly implement Scientific Outlook on Development, seize the powerful opportunity of the autonomous region to thoroughly implement the strategy of developing the western region, focus on economic benefits, focus on project management, fully promote production and operation and project development, strengthen our confidence, work hard, seize every minute to overcome difficulties, and strive hard to achieve the comprehensive goal of production and operation of * * * enterprises, and achieve * *.

Problem report model essay 2 Leaders and colleagues:

The current work of * * Company is reported as follows:

First, remember "xx". Xx "accident lessons, put an end to safety accidents.

The accident reflects some problems such as inadequate safety management, inadequate technical management, inadequate implementation of safety responsibilities, and inadequate safety production measures. We should learn a profound lesson from this accident, and it is our proper attitude to draw inferences from others. In the future work, we must do a solid job in safety production to prevent safety accidents.

Second, the safety inspection situation

Through the safety inspection of the construction site, it is found that there are many hidden dangers. Now the construction site has been closed. When resuming construction, eliminate potential safety hazards through mechanical operation before construction.

Third, the next stage of work arrangements

1. During shutdown and rectification, do a good job of safety on duty at the demolition site to prevent irrelevant personnel from entering the demolition site and prevent safety accidents.

2, in the construction, one is to implement the safety management system; Second, before the house demolition, according to the characteristics of the demolished house, the construction plan will be determined in conjunction with the demolition headquarters and the investment company; Third, the demolition construction must be carried out in accordance with the operating procedures of the demolition project; Fourth, in the process of construction, there must be someone who is responsible for monitoring the structural state of the demolished houses. When the unstable trend is found, the operation must be stopped and effective measures must be taken to eliminate potential safety hazards. Fifth, do a good job in construction safety protection measures; Sixth, strengthen safety education on the construction site, improve workers' consciousness of observing construction safety discipline, conscientiously implement safety operation procedures, and improve the safety protection awareness and self-protection ability of all employees.