Sample fence construction program introduction to construction work?

How should I write a fence construction program? What is included in the construction program? The following is the construction network to bring the content of the fence construction program model detailed introduction for reference.

Construction plan

1, to determine the first construction of brick masonry iron fence wall after the construction of color steel temporary fence: the front of the unit after the end of the sub-construction, immediately start the next construction unit, and clean up the construction waste, and immediately organize the vehicle will be the garbage transported out of the factory, the back of the immediate after the technicians to put a line to copy the level, locate the wall, the masonry works immediately after.

2, structural construction: centralized processing of reinforcing steel, in-situ binding, templates using bamboo glue board templates, wood support. Concrete is mixed on site and transported to the site by dump truck for pouring.

3, time plan: the construction period is 60 days.

Construction preparation

1, measurement and placement, based on the original fence axis position and elevation, to determine the location of the project.

2, the organization study, familiar with the construction drawings, understand the design intent, and do a good job of design and drawing review.

3, the construction technicians and operators to organize training and learning, graded delivery.

4, the preparation of construction progress control implementation details, decomposition of the project progress control objectives, clear their responsibilities to ensure that the schedule.

5, the preparation of project quality implementation details, determine the quality control points, decomposition of construction quality objectives, the establishment of the construction quality assurance system, special parts such as measurement and placement of the preparation of work instructions.

Main project construction methods and technical measures

1, foundation project

1, construction process

Site leveling→positioning line→trench excavation→supporting templates→pouring concrete bar foundation→inspection and acceptance→removal of templates→backfill→moisture-proof layer→acceptance of the foundation structure.

①Wherein: earth excavation process is as follows:

Positioning measurement - burying axial lead pile - spreading out the excavation line - manual excavation --Foundation trench inspection --Foundation abnormality treatment --Entering the next process.

2, construction points

1) The amount of soil in the process of earth excavation, in the vicinity of the site near the pile, in order to be used for backfilling.

2) In the process of excavation, the surveyor readily leveled and nailed elevation control piles on the pit wall to keep track of the excavation depth and prevent over-excavation.

3) When digging, the distribution of underground pipelines should be explored in advance and properly handled.

4) In earthwork construction, attention should be paid to the safe use of construction machinery and overhaul before entering the site. Excavators are not allowed to carry out other operations within the scope of work when excavating, when loading soil, the driver of the car should leave the cab, and it is strictly prohibited to load soil when there are people in the trunk.

②This project is C20 concrete.

To be based on the axial dimensions, the base elevation acceptance after the hidden inspection procedures, survey and put the personnel in a timely manner to mark the 400mm thick concrete on the skin of the elevation control line. Before pouring the concrete, check whether the size and shape of the bedding layer is correct and whether the template support is firm. When pouring the bedding concrete, send a person to randomly check the quality of commercial concrete at any time. The surface of the concrete is scraped with a scraper, and then rubbed and calendared with a wooden trowel, and samples should be taken in time during the construction process, and test blocks should be retained.

3 earth backfill

After the completion of the foundation project, after the quality inspection station acceptance, then the earth backfill.

1) Process

Basic cleaning → inspection of soil quality → layered paving, raking → tamping and compacting → inspection of compactness → repair and leveling → acceptance.

2) Construction method

The bottom of the base trench should be cleaned of garbage and other debris before filling. Before backfilling the foundation, it must be cleaned up to the elevation of the bottom of the foundation, and the loose garbage, mortar, stones and other debris falling back should be cleaned up.

Check the backfill soil with or without debris, whether the particle size is in accordance with the provisions of the water content is within the scope of control. If the water content is high, can be used to turn loose, drying and uniform mixing of dry soil and other measures; in case of backfill soil water content is low, can be used in advance sprinkler wetting and other measures.

After all the filling is completed, the surface should be leveled, and the place over the design elevation should be shoveled in time according to the line, and the place lower than the design elevation should be made up with the soil and compacted.

3) Quality standard

Main control items: the permissible value of elevation deviation -30mm, compaction coefficient of layering in accordance with the design requirements.

General items: backfill soil material, must be in accordance with the provisions of the design or construction specifications, layering thickness and moisture content in accordance with the provisions of the design or construction specifications, the permissible deviation of the surface flatness is not more than 20mm.

Two, fence project

Laying of lines→supporting the mold→pouring of concrete base→maintenance, dismantling of molds→laying of brick pillars→installation and fixing of iron balustrades

( 1)Foundation bedding concrete

Foundation concrete construction must be the concrete bedding and the surface clean, no water, no soil falling into the groove, the side of the template support in the pit wall need to pay attention to the stability of the reinforcement, shall not be the template support bar directly supported in the soil wall, support the lower mouth must be added pads support in the dense soil layer, in order to prevent the pouring of concrete due to the support of the mold run. Foundation beam template, can use diagonal bracing plus buttresses way to reinforce, beam upper mouth specially made bayonet steel or angle should be limited to its width.

When the foundation concrete is poured, no construction joints are left.

(2) brick foundation

Brick foundation construction before the foundation beam side backfill, should avoid the soil scattered in the foundation beam, such as the foundation beam should be cleaned up the mouth of the foundation beam, popping out the brick foundation of the center line and side lines, on a layer of cement mortar, the foundation beam on the upper mouth of the wall parts of the local unevenness of the place to leveling, and then laying bricks to lay the wall. Brick foundation masonry can also be completed, and then backfill, to maintain the brick foundation masonry stage of the original concrete surface clean, so that the quality of masonry to be further guaranteed.

Three, the main structure project

1, wall project

The project masonry materials:

Bricks for wall:

Masonry materials:

Adopt MU10 cement coagulation, M7.5 cement mortar masonry, and outside the pasting of beige culture stone

(1) the materials used in masonry must be tested and used, and it is strictly prohibited to use substandard materials. It is strictly prohibited to use unqualified materials.

(2) masonry mortar: mortar varieties, the standard must meet the design requirements, yellow sand does not contain impurities, the use of tap water, yellow sand impurity content is controlled within the range of less than 3%.

(3) construction preparation, masonry before the brick or block must be wet with water, but not too wet or wet uneven site.

(4) masonry must be cleaned up before the grass-roots surface of the mortar debris, and watering wet, at the same time should be a test pendulum; masonry, should be according to the drawings of the design requirements of reserved holes pipeline and buried parts.

(5) should be strictly in accordance with the brick masonry construction specifications, according to the layer height, window sill and window top height calculated the number of bricks in the layer of the skin, mortar thickness and other data, in the construction part of the pop-up wall axis, set up the skin rod, control the thickness of the mortar, in order to control the height of the masonry, and use the seven points of the brick or small specification with the whole brick block with the corner of the corner and end of the wall, in order to achieve the purpose of the wrong joints.

(6) masonry hewing, must be hewed at the surface clean, watering wet, and should be filled with mortar, keep the gray joints straight.

(7) masonry wall, should check the corrosion of the tie bar, such as corrosion is heavy, must use wire brush and other tools to remove rust before masonry hidden.

(8) Make mortar test blocks according to the specification requirements, and test on schedule.

(9) internal and external scaffolding using mobile temporary scaffolding.

Construction points:

Before installing the iron fence must ensure that the concrete support shaped, the location of the embedded parts is correct, the finished iron in the transportation should also pay attention to, do not be strong pressure deformation and distortion, in the installation of the placement of the position in the axis, and the need to be fixed firmly.

2, reinforcing steel works

1.2.1 rebar processing

A, reinforcing steel in the on-site reinforcing steel processing room (see construction general layout) centralized processing, making should pay attention to the correct shape of the rebar, the plane of no warping uneven phenomenon; reinforcing steel end bending hooks of the headroom of the rebar is not less than the diameter of the rebar of 2.5 times; rebar bending point shall not have cracks, for this reason, for the Ⅱ above the steel can not bend over the head and then bend. The rebar can not be bent over the head and then bent back; rebar processing and molding allowable deviation is: ± 10mm, hoop edge length ± 5mm.

B, each batch of incoming steel should be in accordance with the provisions of the mechanical properties of the test, qualified before processing and tying. Sending test must witness sampling, otherwise it can not be used as a test specimen. The incoming and well-made molding steel must be according to specifications, part by part for listed stacking. Reinforcing steel stacking should be padded up to prevent rusting.

B, rebar connection by tying connection,

C, 8.1.3.2 before tying should be prepared, namely, check the finished rebar with the material list whether it is in line with the material list; prepare the required rebar pads; draw the rebar position line at the tying site.

B, when tying the raft foundation reinforcement, the upper and lower reinforcement cross should be firmly tied at each point. Binding should pay attention to the adjacent binding point of the wire buckle to become eight-type, so as to avoid the mesh skewed deformation. Raft slab foundation upper layer of reinforcement with steel bench support.

C, reinforcing steel protective layer using 1:1 cement mortar to make pad to ensure. The thickness of the pad block should be consistent with the required size of the protective layer.

3 template project

The use of shaped combination of steel templates, templates should have sufficient strength and rigidity, templates should be classified according to specifications after the factory stacked neatly, stacking height of not more than 1.5 m.

Templates should be cleaned and smoothed before use, and brush release agent, demolding should be stacked in a timely manner to the designated location.

The template installation, such as not to catch up with the number of modules, with a small number of wooden molds, wooden mold surface should be planed, steel, wood molds should be connected between firm, flat, to prevent the concrete construction is now convex and concave phenomenon.

The template should be installed after the casting point to find the right, to ensure the accuracy of the template position and verticality and surface flatness, to determine the problem to be fixed in a timely manner (take the method of pulling the top to ensure).

Template demolding time, side mold concrete strength to ensure that the component is not deformed, the corners are intact before dismantling, reserved holes in the internal mold, in the concrete strength to ensure that the surface of the component and hole does not slump and cracks before dismantling; bearer templates demolding time to be controlled by strict specification requirements.

4 Concrete works

1.4.1 Concrete supply

A JGZ350 concrete mixer is set up at the site for mixing and transported to the pouring place by motorized dump truck.

1.4.2 Pouring and vibration of concrete

Foundation concrete is poured at one time without construction joints. During the construction process, attention should be paid to the pouring speed and thickness.

When vibrating the concrete, the vibration duration of each vibration point should make the surface of the concrete show floating slurry and no air bubbles. When using insertion type vibrator, should avoid collision steel, template, etc.; vibrator inserted into the lower layer of concrete depth should not be less than 50mm. surface vibrator, its moving distance should be to ensure that the vibrator's flat plate can cover the edge of the vibrated part.

When pouring the construction in rainy days, there should be covering measures after the concrete is poured to prevent the rain from washing away the mud and affecting the quality of concrete.

1.4.3 Maintenance and test of concrete

After the concrete is poured, the concrete shall be covered and watered within 12 hours; the time of watering and maintenance of the concrete shall not be less than 7d for the concrete mixed with silicate cement, ordinary silicate cement or slag silicate cement and shall not be less than 14d for the concrete mixed with admixtures or the concrete with seepage resistance; the number of times of watering shall be able to keep the concrete in a wet state; the concrete shall be kept in a wet state. In the wetting state; concrete maintenance water should be the same as the water used for mixing.

1.4.4 Transportation and pouring of concrete

Foundation pouring concrete is transported to the site by motorized dump truck. When the mixed concrete is transported to the site, it should be poured in time to avoid construction joints.

5Conservation

Covered with plastic sheeting or grass curtains for moist conservation, partially sprayed with conservation liquid.

6Scaffolding project

1.6.1To ensure that the construction does not interfere with each other, the external scaffolding is required to meet the construction requirements

1.6.2Material requirements

Scaffolding using ?48mm, wall thickness of 3.5mm steel pipe, there is a serious corrosion, bending, flattening or cracking of the steel pipe is strictly prohibited;

The fasteners must be used to qualify the Ma steel Fasteners must use qualified ma steel fasteners, and obtain the certificate of conformity, when the fasteners clamped steel pipe, the minimum distance between the openings should not be less than 5mm;

Wooden scaffolding boards should be made of pine or fir, the thickness of which should not be less than 50mm, and the scaffolding boards should be used on both sides of the galvanized steel wire with the diameter of 4mm for each hoop two ways.

1.6.3 Demolition of external scaffolding

A, the order of demolition should be carried out layer by layer from the top to the bottom, it is strictly prohibited to work on the top and bottom at the same time;

B, all the connecting parts should be demolished layer by layer along with the scaffolding, it is strictly prohibited to dismantle scaffolding after removing the connecting parts of whole layer or layers;

C, when the scaffolding is dismantled to the height of the last long steel pipe in the lower part (about 6.5 meters), it should be set up temporarily at a suitable position first. Temporary casting braces should be erected at appropriate positions to reinforce the scaffolding before dismantling the wall members;

1.6.4 Allowable deviation of scaffolding

Correct the vertical and horizontal deviation of the poles at any time so as to avoid too large a deviation.

A, the vertical deviation and full height deviation of the vertical pole is not more than 100mm;

B, the horizontal deviation of the same row of big horizontal pole is not moved 50mm.

7 Other requirements of scaffolding support:

A, the operator must hang the safety belt during the process of support;

B, the position of the upper and lower horizontal poles' joints is staggered and arranged in the different Longitudinal distance from the uprights, and the distance from the adjacent uprights is not more than 500mm;

C, small cross-bar close to the uprights, over the cross-bar, and fastened with right-angle fasteners;

8 masonry works

1.8.1 Bricklaying construction

Materials Requirements:

A, bricks: varieties, strength grade must meet the design requirements, and have factory certificate or test sheet. test sheet.

B, cement: cement varieties and grade should be selected according to the environment under the masonry parts.

C. Sand: medium sand.

Operating conditions:

A, according to the design of popping out the fence axis.

B, according to the elevation to set up the number of skinned poles, the spacing of skinned poles to 20m as a standard.

Masonry points:

A, brick watering: clay bricks must be watered the day before masonry wet, to water immersed in the four sides of the brick 50mm is appropriate, the water content of 12%.

B, mortar mixing: mortar ratio should be weighted, measurement accuracy cement ± 2%, sand, gray paste control within ± 5%. Suitable for mechanical mixing, mixing time of not less than 1.5 minutes.

C, mortar: the following requirements should be met:

D, after standard maintenance 28 hours after hardening should reach the strength of the design provisions.

E, mortar in transportation and use, shall not produce water secretion, delamination, segregation and other phenomena, to ensure the uniformity of mortar components.

Operating conditions:

A. Brick site for on-site storage should be compacted, leveled, not waterlogged, and the yard should be neat. The loading and unloading process should be light to avoid damage, and the second backward transportation should be minimized.

B, according to the wall size and block specifications, properly arranged rows of masonry masonry plane arrangement design, as far as possible to minimize the amount of on-site cutting. C, the corner of the outer wall, blocks should be divided into skin bite contempt, staggered lap masonry.

D, masonry horizontal mortar thickness is generally 8-12mm; vertical mortar width is generally 8-12mm.

Four, painting project

Iron fence must be good anti-corrosion and anti-rust project. So in the paint and welder construction must be every dead corner and gaps should be handled carefully. Brush anti-rust paint one, silver powder paint two. Before painting, the paint must be stirred evenly (to prevent pigment precipitation in the storage period), and adjusted to the appropriate viscosity, generally judged by experience: that is, after lifting the paint with a brush dip, 30-50 drops per minute of natural flow of drops / minute is appropriate. Less dip more brush, from top to bottom, from left to right, first inside and then outside, first oblique and then straight, first difficult and then easy, vertical and horizontal painting. The last painting should also be noted: for vertical surfaces should be carried out from top to bottom; for horizontal surfaces should be carried out according to the direction of light irradiation.

Cast iron railing installation project main construction methods

Section I quality inspection

1, railing into the field, the organization of the construction unit of relevant personnel for acceptance, check the certificate of conformity and other documents, check the geometry of the size of the accuracy of the products do not meet the quality requirements are strictly prohibited from entering the field.

2, check the quality of asphalt paint, whether there is a missed brush or brush the number of times does not meet the requirements.

Section 2 installation method

Clean up the debris on the top of the pressurized top, calibrate the size, install the cast iron fence on the top of the pressurized top to fix it firmly, and grout the joints with fine stone concrete.

Chapter VI schedule and schedule guarantee measures

Section I schedule

The iron fence and temporary fence is scheduled to start on March 26th and end on May 24th, with a planned construction period of 60 days.

Section II of the overall measures to ensure that the construction period

1, organizational measures:

a, a strong command system:

The project manager with extensive construction experience is responsible for the construction management of this project, while the full range of professional construction and technical management personnel to set up a strong and powerful project department, clear responsibilities, strict job responsibilities, each in its own way, and their own responsibilities, not only to ensure the leadership authority of the project manager, but also to ensure that the project manager has the authority to lead the project. Both to ensure that the project manager's leadership authority, but also pay attention to play the subjective initiative of the functional departments, make concerted efforts to do a good job.

b, excellent construction team:

Good reputation, high quality of labor subcontracting team is to ensure that the project is completed on schedule, one of the basic conditions, choose to investigate the recognition of the construction of similar projects engaged in the construction of high-quality, reputable, hard style of the construction of the project, to ensure that the project is carried out according to plan.

2, material measures:

a, the use of advanced horizontal transportation machinery: the site into three motorized dump truck car, responsible for the site of the horizontal transport of materials. To speed up the construction progress.

b, emergency measures, consider in the first place: the use of fire ponds and underground wells to store water, to ensure the normal operation of the construction of a sudden stoppage of water. Improve the reserve string exchange capacity when materials are in short supply to ensure the timely supply of materials on site.

Quality assurance measures

1, material inspection regulations

Organize inspection and acceptance of all incoming raw materials and semi-finished products, and set up accounts.

The raw materials that need to be retested, such as: cement, steel, reinforcing bars, sand and gravel, a variety of additives, welding rods, fluxes, waterproofing materials, etc., must be in accordance with the provisions of the timely sampling and testing and test report to the superintendent for inspection.

2, the process of inspection and reporting regulations

Strict implementation of the current national norms, standards and enterprise regulations, in strict accordance with the design requirements of the construction organization.

Each sub-projects (processes) before the start of work, points in strict accordance with the requirements of the technology standards for the operation of the team for technical and quality delivery.

Engineering construction of the "three inspection system", should seriously grasp the self-inspection of the team, the establishment of a full-time quality inspector, supervise the self-inspection of the team and fill in the self-inspection records.

3, sub-parts (process) after the completion of the project, the organization of self-inspection and process handover inspection, unqualified sub-projects or processes, not qualified for the construction of the next process shall not be carried out without repair.

Sub-items or processes to achieve a qualified fill in the inspection report and supervisor and the director of the engineer review acceptance, inspection report with self-inspection, handover inspection records, hidden records, pre-check records, quality assessment and other information.

Strictly in accordance with the "three inspection system" organization to check the construction quality of each process. To check the previous process, to ensure that the process, service next process. Really strict control of the quality of the process, unqualified processes are not handed over.

4, quality inspection personnel must strictly control the quality of the construction process, strict control in the construction process, shall not conceal the construction of quality problems, and urge the operator to rectify in a timely manner.

Civilized construction guarantee measures

1, civilized construction to create standards and goals

The project's safety and civilization management goals: civilized construction management to ensure civilized construction order. In accordance with the Chishui City construction project construction site "civilized site" assessment standards for management. Strive to create the project again "construction site civilization site". According to the civilized construction site construction standards, we specifically do: no major accidents; construction site pedestrian traffic, construction areas and non-construction areas are strictly separated; the site set up civilized construction sign, management personnel card on duty; living facilities clean and civilized.

2, the site facilities regulations

2.1, health management

(1) do not bring mud and sand out of the field, and to do along the way not to be left behind not to spread.

(2) The construction site is often kept clean and sanitary. Roads are level, solid, smooth, and have drainage facilities.

(3) The canteen has a person in charge of hygiene, and strictly implements the Food Sanitation Law and other relevant systems.

(4) Drinking water to ensure the supply of boiled water, drinking utensils hygienic.

(5) The toilets on site are cleaned by specialized personnel.

2.2, pollution control

(1) air pollution

Construction garbage set up closed temporary special garbage or containers lifting, is strictly prohibited randomly thrown in the air, garbage removal in a timely manner, the appropriate amount of sprinkling, to reduce dust.

Cement and other fine bulk materials, take indoor (or closed) storage or tight cover, unloading and transportation to take effective measures to reduce dust.

The ground of temporary roads on site is hardened to prevent road dust.

When the mixing equipment is set up on the site, dust blocking devices are installed.

(2) Water Pollution

1) On the site of concrete, mortar and other mixing operations, set up a sedimentation tank, so that the wastewater from the cleaning machinery and transportation trucks can be discharged into the municipal sewage pipeline or recycled for sprinkling and dust reduction after sedimentation.

2) Control the flow of sewage generated by construction to prevent diffusion along, and set up sedimentation tanks in reasonable locations, after precipitation, discharged into the sewage pipeline, and prohibited from flowing out of the construction area and polluting the environment.

3) The storage room for oil stored on site is treated with anti-seepage and leakage, and measures are taken for both storage and use to prevent running, bubbling, dripping and leaking, and polluting the water body.

(3) Noise pollution

1) The construction site in accordance with the "Chinese People's Republic of China **** and the State Construction Noise Limits" (GB12523-90) to develop appropriate systems and measures to reduce noise.

2) strong noise, large vibration operations, strict control of operating hours. Must be day and night continuous operation, take measures to reduce noise and vibration, do a good job around the masses, and report to the relevant environmental protection unit for the record after construction

2.3, site appearance management

(1) in accordance with the requirements of the implementation of closed construction, the construction area fenced enclosure, the gate set up guards, and all idle personnel are not allowed to enter the site.

(2) the management of the construction site, the implementation of the construction site, the implementation of the area divided into blocks, the responsibility of the area of signage, the living area management regulations signboards to show all.

(3) the development of construction site life hygiene management, inspection, evaluation and assessment system.

(4) safe production work on the wall, to do seven cards and a map (project basics, the project's responsible personnel name plate, safety six disciplinary card, safety counting card, ten safety measures, fire prevention notice card, health notice card and site construction general layout).

(5) The site is arranged with safety production slogans and warning signs, so that there is no violation of rules.

(6) Signboards are hung in the construction area, office area and living area, and safety warning signs are set up in the dangerous area. Traffic signs are set up at the main construction road intersections.

(7) to ensure that the surrounding environment is clean and sanitary, so that there is no sewage spillage, no dirt, no materials, no garbage outside the fence.

(8) The environment is clean and tidy, the gutters are smooth, the domestic garbage is bagged and transported out in woven bags every day, and the living areas are regularly sprayed with medicinal water to sterilize and remove pests.

2.4, temporary road management

(1) In and out of the vehicle door to send a person responsible for the command.

(2) The site construction road is smooth.

(3) Do a good job of drainage facilities, the site and roads are not waterlogged.

(4) Before the start of construction, make temporary right-of-way, temporary construction right-of-way surface is higher than the natural ground, and drainage ditch is set on the outside of the road.

2.5, material stacking management

(1) all kinds of equipment, materials as far as possible away from the operation area, and not allowed to stack too high, to prevent the collapse of the fall hurt.

(2) The incoming materials are stacked strictly in accordance with the designated location of the site layout.

(3) the site materials clerk to do a good job of acceptance of materials into the field (including quantity, quality, warranty), and make a good record (including the number of cars, cars, transportation units, etc.).

(4) cement warehouse management regulations and systems, cement stacking ten packets of a stack, over the eye into the number, listed management. Cement issued by the limit of material receipt, the limit of issuance. Warehouse management personnel to do a good job of cement receipt, issuance and storage of running water account.

(5) materials stacked according to the field layout strictly stacked, to eliminate chaotic pile, chaotic, mixed, especially to eliminate the materials stacked against the fence, billboards, in order to prevent the force caused by the collapse and other accidents.

2.6, the management of construction workers

Offices, toilets and other building standards, requirements in accordance with the relevant provisions.

Develop the "office, toilet and other health management system", so that the construction site to be clean and hygienic.

Offices are ventilated, bright, and equipped with washing facilities, managed by specialized personnel.

Construction site with tea supply points, tea with elimination of du facilities, to ensure that there is hot water in winter, cool water supply in summer.

In order to ensure the health of the site construction staff, the site set up a medical point.

2.7, security management measures

Education, improve the general staff to defend the project construction and law-abiding conscientiousness. Often carry out safety inspections centered on fire prevention, explosion-proof, anti-theft, plug the loopholes, the owner in the social security, comprehensive management, traffic management, environmental protection and other aspects of management regulations. And with each professional construction unit layers signed a security responsibility agreement.

Establishment of specialized security institutions, unified leadership of public security and defense work. The gatekeeper is set up at the main entrance, and the entry and exit system is strictly enforced. All personnel entering the site must wear a badge, non-engineering personnel entering the gate must be registered, contacted through the gatekeeper, to be clear that the reception staff before entering.

Staff are not allowed to work on the site under the influence of alcohol or drunkenness, and they are not allowed to bring prohibited goods into the site in order to maintain the safety of property and personnel.

Materials vehicles will be driven away from the site and parked in the designated parking lot immediately after loading and unloading into the unit is completed.

Strengthen the management of valuable materials, important equipment and large-scale equipment on the construction site, strictly related systems, set up protective facilities and alarm equipment to prevent materials from being looted, stolen or destroyed.

Extensively carry out legal propaganda and "four defense" to discover hidden dangers and take timely preventive measures to prevent problems.

Strengthen the management of the outsourcing team, set up a person responsible for the outsourcing team for the legal system, rules and regulations of education, to participate in the construction of the civilian workers to review, register, receive a temporary residence permit, issued by the work permit, before going to work. Suspicious personnel to investigate and understand.

2.8 Measures to prevent nuisance

Reasonable layout of the site, and increase the necessary environmental protection measures and environmental protection, in order to reduce the harm to the surrounding environment.

Assist the owner to coordinate the surrounding environment to ensure the normal operation of the project.

Establishing a public relations and coordination department to strengthen cooperation with community neighborhood committees and police stations.

To assume the responsibility of general contractor management for the possible nuisance and civil disturbance of the project, and be fully responsible for the coordination of all aspects of the work.

Register with the Environmental Protection Inspection Station prior to the commencement of construction and accept environmental monitoring at all times.

Before entering the construction site, and the local government, neighborhood committees to get in touch with the neighboring units and residents are invited to participate in seminars, press conferences, etc., to inform the project overview, nature and construction significance, and actively listen to the neighboring units and the residents of the views and suggestions, try to reduce the impact on the surrounding environment by adopting a reasonable construction program. And the impact of the construction of the project to seek support and understanding of the neighboring units and residents.

To be affected by the construction of noise, glare, dust units and residents to take the necessary measures to compensate. At the same time to take effective preventive measures to reduce these hazards, in order to protect the interests of neighboring units and residents as far as possible.

In the project system to establish the relevant processing coordination leading group. Civilization standardization management team set up a special person to deal with nuisance and civil disturbance problems, so that timely detection of problems, solve the problem.

If the continuous construction and night construction exceed the environmental protection regulations due to special process, please ask the relevant authorities to review and approve. And cooperate with the local government to do a good job of coordination with local residents.

2.9 Reasonable arrangement of the site and machinery and equipment, the use of low-noise new machinery and equipment. Lighting arrangement of the construction site lighting as far as possible away from the residential area.

More about tender writing production, improve the winning rate, click the bottom of the customer service free consultation.