How to equip the production line and equipment for the monthly production capacity of 200,000 pieces of medium and high frequency transformers?

Monthly production capacity of 20 W. Do you choose to use fully automated equipment for production or use manual production? I use manual production mode to give you an answer. To others to do OEM semi-finished products or finished products or to manufacturers directly supply finished products? To others to do processing, then may be less equipment If you do finished products, then the equipment will be relatively more The following is based on the data you provide and our company's production capacity to provide you with advice:

One, to others processing semi-finished products, the need for equipment: 1, the winding machine (including a single rod / semi-automatic / full-automatic optional), 2, the soldering machine (20W, if a manual tin pot is OK, the best), and then a soldering iron maintenance). And then a soldering iron for maintenance) 3, single-turn tester (you can also use a multi-channel tester for testing)

Two, to others OEM finished products. In addition to the above, but also need: 1 tape machine a number of (less than 10 can be) 2 inductance tester (2 ~ 3 can be) 3 vacuum dipping machine 4 oven a

Three, their own production of finished products directly to the manufacturer. In that case, you need more, but also check the equipment used, including: 1 voltage tester 2 ~ 3, 2 turns withstand voltage tester a 3 integrated tester (price 1.5-3W, you can also use other single tester instead, but the performance and test speed is not necessarily good.) 4 spray code meter a (imported prices between 3W ~ 10W, consumables are slightly more expensive).

Four, an air compressor

As for the production line arrangement, depending on what kind of products you do

Generally speaking, semiautomatic winding machine production capacity of each winding line between 1000-2000, the new workers have just begun to produce a lot less, that is, a few hundred (at most ... ), that is, you just start production, the production capacity of a few hundred (at most), that is, you just start production. That means you need to have more than 2 assembly lines when you first start production.

After winding the wire, dip tin, dip tin is easier to get started, the daily production capacity can quickly reach several K on W, so you only need a maximum of two tin pots can be. If you supply semi-finished products to others, then you can directly test shipments; if you supply finished products, then you need to assemble, general assembly, six people can assemble about 1W per day (except for the difficult to do), including assembly, testing, inspection. Then paint dipping operation, daily capacity of 2-3W it. Finally, the inspection, each inspection line's daily capacity is about 1W, one inspection line is enough.

Now the production of transformers, if the monthly production of 20W, it is estimated that you do the finished product is more likely to do this thing, quality is the most critical, millions of millions of attention to the quality of the production of products Oh

this is the above, these are the full artificial methods of operation If you use the fully automated words, very simple, the ticket to spend a lot of hard... I'm not sure how much I'm going to be able to afford it.