(in accordance with the contract to prepare their own)
Two, engineering equipment input details:
1. Input equipment and materials: 260 tons crane, 70 tons crane, 32 tons crane, transport flatbed trucks, each one; flatbed trailer cars and platform trucks to widen the platform of each one. Widen the platform with 16 # H steel composition. Paving road with steel plate 120m2.
Three, lifting program
1, on-site installation with 260T crane, crane from the south into the foundation for lifting.
2, into the foundation need to pave the road. The road is paved with stones until it is flush with the foundation, and then the upper part is paved with 20mm thick carbon steel plate. Steel plate width 2m, length 10m **** 6 sheets.
3, site loading with 70T crane, to the flatbed trailer fixed transportation. The site is equipped with a 32 cranes, used for paving roads and 260T crane loading and unloading weight.
4, lifting with all the wire rope film protection, to prevent and equipment to produce scratches and other phenomena.
Four, safety measures:
1, lifting staff must be familiar with the whole set of construction program, by professional lifter is responsible for loading and unloading spreader.
2, lifting before all the use of machinery, tools, tools must be checked.
(1) whether the machine spreader normal operation, there is no hidden danger, boot personnel must strictly abide by the rules of construction, not allowed to take sick, drunk boot.
(2) check whether the spreader is normal, can work in the insurance factor range. Do safety without hidden danger, to ensure normal construction.
(3) lifting, lifting work to participate in the technical leadership should be familiar with the lifting program
(4) lifting, in addition to the operator other unrelated personnel shall not enter the safety line, so as not to affect the operation or cause operational errors
(5) lifting equipment, the working load, are not allowed to exceed the provisions of the nameplate
(6) construction of all the equipment before, the rope, (6) before the construction of all equipment, ropes, tools for careful inspection, such as wear and tear, rust and corrosion phenomena, should consider reducing its pressure or not use
(7) to participate in the lifting of equipment, construction personnel must supervise the post, follow the instructions, to do the forbidden, to ensure that the project is safe and smooth completion.
(8) It is strictly prohibited to carry out lifting operations in the wind above level 5.
(9) the work area is equipped with obvious signs, lifting is strictly prohibited unrelated personnel to enter or pass.
(10) construction personnel must enter the site wearing a helmet, on the high ground must wear a safety belt.
(11) construction personnel to comply with the rules and regulations of the service company.
(12) construction workers into the plant wearing appropriate labor protective gear.
(13) construction equipment, prefabricated parts are stacked neatly, and the construction site must be clean at the end of the work.
Five, lifting with the content:
1, lifting and transportation process must ensure that the equipment is intact. No deformation, scratches, damage and other phenomena.
2, the owner needs to ensure that the lifting and transportation during the site transportation road smooth.
3, during the lifting must comply with the contractor's factory rules and regulations and environmental requirements, to obey the contractor's relevant departments to supervise the functions, violators in accordance with the provisions of the contractor to make the appropriate treatment.